You are on page 1of 1

WKPP POWER PLANT CONSTRUCTION Q/A ELECTRICAL/ I&C

WHAT WAS LOOKED THIS WEEK, February 2 7 - March 02,2012

1.

Pulling of control cables into CFE panels for EG #s 3 to 6 and preparation of control cable for termination in CFE panel for EG #1. Connection of temperature signal cables to pyropipes for EG #1 and 2. Control cable pulling to CFA 902 panel. storage tanks earth resistance measurements: Fire water tank : 0.15. Clean LO tank : 0.1. Used LO tank : 0.09. LO service tank #1 : 0.13. Lo service tank #2 : 0.15. LFO day tank : 0.1. HFO buffer tank : 0.14. HFO day tank : 0.1. HFO Storage tank #1 : 0.05. HFO Storage tank #2 : 0.04. Sludge tank : 0.17. Oily water buffer tank : 0.14. Thermal oil system instrumentation and piping walk-down Fire water tank level sensor cable installation.

2. 3. 4.

5. 6.

You might also like