R.

ID

Risk Name

Description

Probability of occurrence

Impact

Risk Owner

Priority

Category

Status

Risk response Solution strategy

R.1

Increased turnover

Employees leave Medium the job as a result of resistance to change

High

Organization

10

Management

New

Risk Avoidance& Risk Transference

Hire Skilled employees

R.2

Failure training

in Employees

are Medium

High

Project Manager

10

Human Resources

Ongoing

Risk Mitigation

Insist

on

unaware of how to use the system

employee training as part of job scope

R.3

Inefficient distribution costs

Less costs spent Medium of on Prevention

High

Project Manager

10

Management

Ongoing

Risk Avoidance

Spending more money on

prevention R.4 Bugs system in the The system has Low errors Low Project Manager 7 Software New Risk Mitigation Spending money in

catering to the risk R.5 Time estimated The is not precise estimated inaccurate duration Medium is Medium Project Manager 9 Management New Risk Avoidance Counter check the

calculations

R.6

Lack of support Sponsors pull out Low from sponsors support project of the

High

Project Manager

10

Management

Progress

Risk Avoidance

Communic ation

R.7

Uncooperative customers

Customers changing minds

keep Medium their

High

Project Manager

Management

New

Risk Avoidance

Ensure

Contract is signed

R.8

Lack of project The status of the Low report status report known is not

Medium

Project Manager

Management

New

Risk Mitigation

Weekly reports and hire skilled members

R.9

Complaints

Jeeves PLC is not Medium

High

Project Manager

Project board

Progress

Risk Mitigation

Training and employ skilled personnel

from customers satisfied with the after installation system

R.10

Delay receiving hardware software

in Delay

at

the Low

High

Project manager

Procurement

Progress

Risk Avoidance

Clear contract

hardware vendors and shop

R.11

Errors in user Several manual grammatical errors

Low

Low

Project board

Procurement

New

Risk Mitigation/ Avoidance

Contract

R.12

Hard failure

disk The data saved is Low not available

High

Project board

Management

Ongoing

Risk Avoidance

Keep backup