The 4th Bridge Project

LA 143 US 165 Connector and Ouachita River Bridge Ouachita Parish State Project No. H.004782.2 Federal Aid Project No. H.004782

Scott Hoffeld, CEP Scott.Hoffeld@arcadis-us.com 225-572-7111


Imagine the result 27 February 2013 1
2012 ARCADIS

Safety Moment

27 February 2013

2012 ARCADIS

Parking Lot Safety


Watch where you park Panic buttons, keys, sprays, and your elbow Suspicious vehicles / people Look behind/front, side, and in car before entering Get in; Drive off

27 February 2013

2012 ARCADIS

Project Team Acknowledgement

27 February 2013

2012 ARCADIS

Project Consultant Team

Project Management NEPA Analysis and Documentation Public and Agency Outreach Bridge Concept , Line & Grade

Level 1 Toll Study Bridge Constructability and Construction Sequencing

Topographic Survey Property Research Elected Official and Stakeholder Coordination

Architectural Resources Terrestrial and Marine Archaeology Section 106 Consulting Parties Coordination

27 February 2013

2012 ARCADIS

Delivery Schedule
Notice of Intent

Federal Register June 28, 2012


SOV June 27, 2012 Interagency Meeting July 31, 2012 Stakeholder and Public Meetings August 14, 2012

Agency Coordination and Public Scoping

Alternatives Development /Screening

Research, Field Data, Level 1 Toll Study, Alternatives Development and Screening.
Summer 2013 Summer / Fall 2013 Winter 2014 Winter / Spring 2014 Spring / Summer 2014

Draft EIS

Public and Agency Review and Comments

Final EIS

Final Comments

Record of Decision

Funding, Design, Right-of-Way, Construction


6 27 February 2013 2012 ARCADIS

Description and Location

27 February 2013

2012 ARCADIS

Description
LA 143 to US 165 Connector Ouachita River Bridge (4th Bridge) 4-Lane Facility with Construction Phasing Level 1 Toll Study

27 February 2013

2012 ARCADIS

27 February 2013

2012 ARCADIS

Project History

10

27 February 2013

2012 ARCADIS

4th Bridges Long History


1968 1st reference 1971 Monroe Metropolitan Area Stage 1 Priority 1981 Twin Cities Expressway Corridor Study 1996 Ouachita Loop MIS 2007 Legislation establishing Ouachita Expressway Authority 2008 Stage 0 Feasibility Study 2012 EIS / Line & Grade / Level 1 Toll Study Contract

11

27 February 2013

2012 ARCADIS

Proposed project is a Section of Independent Utility within the long-range plan (unfunded) project known as the Ouachita Loop

12

27 February 2013

2012 ARCADIS

Current Study Area

What is the Project?

13

27 February 2013

2012 ARCADIS

Project Need

14

27 February 2013

2012 ARCADIS

Need
Maintain east-west mobility for local and long-distance travel Create rural transportation system linkages across Ouachita River north of congested urbanized areas of Monroe and West Monroe

15

27 February 2013

2012 ARCADIS

2015 Traffic Congestion Projection

165

20 20

16

27 February 2013

2012 ARCADIS

2035 Traffic Congestion Projection

165

4th Bridge
20 20

17

27 February 2013

2012 ARCADIS

With Loop

48% of all trips are Rural to Rural

18 18 27 February 2013 2012 ARCADIS

4th Bridge Trip Sources with Loop With Loop

Note: This map shows the roads that contribute traffic to/get traffic from the Fourth Bridge. Also shown are the trip origin zones and the corresponding traffic volumes. These volumes were extracted from CDM Smiths year 2035 travel demand models for the toll scenario with the outer loop.
19 19 27 February 2013 2012 ARCADIS

4th Bridge Trip Sources without Loop Without Loop

Note: This map shows the roads that contribute traffic to/get traffic from the Fourth Bridge. Also shown are the trip origin zones and the corresponding traffic volumes. These volumes were extracted from CDM Smiths year 2035 travel demand models for the toll scenario without the outer loop.
20 20 27 February 2013 2012 ARCADIS

Level 1 Toll Study

21

27 February 2013

2012 ARCADIS

Stage 0 Concepts (2008)


2

165

143

165

22 22 27 February 2013

143

2012 ARCADIS

Level 1 Toll Study Results


Finks Hideaway Connection most important on east LA 143 terminus has more utility the further south Two lanes are adequate through a portion of the planning period Tolling will likely pay for only a portion of costs

23

27 February 2013

2012 ARCADIS

Funding

24

27 February 2013

2012 ARCADIS

Costs and Funding


Costs: $300-400M (2007$ Est.) SAFETEA-LU Ouachita Expressway Authority has bonding authority, among other powers

25

27 February 2013

2012 ARCADIS

Alternatives Development

26

27 February 2013

2012 ARCADIS

Stage 0 Concepts (2008)


2

165

143

165

27 27 27 February 2013

143

2012 ARCADIS

Resource Data

Elevation

Wetlands

Floodplain

Land Cover

29

27 February 2013

2012 ARCADIS

30

27 February 2013

2012 ARCADIS

31

27 February 2013

2012 ARCADIS

Stage 0 Alts + All New Segments

32

27 February 2013

2012 ARCADIS

All Segments without Stage 0 Concepts

33

27 February 2013

2012 ARCADIS

Screening
Termini Comparisons Wetland Minimization Centerlines Trade-Off Optimization Retained: Best Wetland Minimization and Trade-Off Optimization Centerlines Corridor centerlines then developed into alternative corridors
34 27 February 2013 2012 ARCADIS

Remaining Segments

35 35 27 February 2013 2012 ARCADIS

Example of Optimization

Optimization Line: Structures and Wetlands

36

27 February 2013

2012 ARCADIS

Preliminary Corridors

Preliminary. Subject to Change.


37 37 27 February 2013 2012 ARCADIS

Preliminary Alternatives
NE

1 SE 2

NW

SW

Preliminary. Subject to Change.


38 38 27 February 2013 2012 ARCADIS

What are the Next Steps?

39

27 February 2013

2012 ARCADIS

Tasks to be Completed
Alternatives Impact Analysis Draft EIS Final EIS and ROD

40

27 February 2013

2012 ARCADIS

Questions?