Professional Documents
Culture Documents
Repetitive uniform of work (multiple houses, ) Geometrically linear (pipeline, highways,) Some non typical units may exist Projects assumed to be comprised of n typical units Complex to schedule and monitor
13/01/2002
Emad Elbeltagi
Basic units: activities, durations, relationships Resources are functions of activities durations Resources are assumed to be available
Resource-driven schedule
More focus on resources Meeting a deadline Line of balance (LOB) Summary diagrams
Emad Elbeltagi
13/01/2002
Similar activities in all units are summarized in one activity Activity duration = duration of single unit x no of units To maintain logic: Add S-S relationships and F-F relationships
LagSS ESA LSA EFA LFA LagFF ESB LSB EFB LFB
DA
DB
13/01/2002
Emad Elbeltagi
DA
DB
Forward path
Backward path
13/01/2002
0 3 A1 (3) 0 3
13/01/2002
Emad Elbeltagi
12
12
Lag 2
12
3
B
14
8
Lag 3
Lag 2
14
5
C
16
8
Lag 2
16
13/01/2002
Emad Elbeltagi
13/01/2002
Emad Elbeltagi
Time
13/01/2002
Emad Elbeltagi
13/01/2002
Emad Elbeltagi
Time
Crew synchronization and work continuity equation Computation of project delivery rate to meets a deadline Calculating resource needs Drawing the LOB schedule
13/01/2002
Emad Elbeltagi
Crew synchronization and work continuity equation Computation of project delivery rate to meets a deadline Calculating resource needs Drawing the LOB schedule
13/01/2002
Emad Elbeltagi
C=DxR
C Crews
R
1
Crew 1
Time
13/01/2002
Emad Elbeltagi
C=DxR
Crew 3
Crew 2
1 1 0 D/C R 1 D/C
Crew 1
2 D/C 3
Time
13/01/2002
Emad Elbeltagi
n-1 Time
R = (n 1) / (TL - T1)
13/01/2002 Emad Elbeltagi
Unit n
D B
n-1
Unit 1
A (5) B (5)
TL - T1
D (2) TF = 3
R = (n 1) / (TL - T1) + TF
13/01/2002 Emad Elbeltagi
Draw the CPM for one unit and determine activities floats; TFi Calculate CPM duration for one unit; T1 Calculate Ri = (n-1) / (TL - T1) + TFi Calculating Number of crews needed Ci = Ri x Di Calculate actual number of crews Cai = Round up Ci Then calculate actual delivery rates Rai = Cai / Di
13/01/2002
Emad Elbeltagi
A 5 Kilometer pipeline project The activities involved in one Kilometer is given below Project deadline 30 days Assume 2 days buffer time between activities
Activity no. 1 2 3 4 5 6 Activity name Locate and clear Excavate String pipe Lay pipe Pressure test Backfill Duration (days) 1 3 1 4 1 2 Preceding activities 1 1 2,3 4 5
13/01/2002
Emad Elbeltagi
Activity 1 2 3 4 5 6
Duration Di 1 3 1 4 1 2
Total Float 0 0 2 0 0 0
Cai = Round up Ci 1 2 1 2 1 1
13/01/2002
Emad Elbeltagi
4 5
7 8 9
12
16
20 22 23
29
31
3 2
Time