You are on page 1of 9

B P M IG A S

Marginal Field Incentive

by Benny Lubiantara

Evaluation & Dev. Plan Division, BPMIGAS The Executive Agency for Upstream Oil & Gas Activities

B P M IG A S

DEFINITION
A marginal field is an oil field located within a producing block that, under the current PSC terms and conditions, is not economics to be developed.

Old Definition in PSC Contract:


Marginal Field is the first field of the Contract Area proposed by Contractor for development and approved, capable of Crude Oil production not exceeding 10,000 Barrels daily average projected for the initial two (2) production years (24 production months).
2

B P M IG A S

Conditions for Marginal Field

Located within a producing block. Its main product is oil. The exploration costs for that field has been fully recovered, i.e. no more sunk costs considered. If calculate based on the current PSC terms and conditions and other incentive packages that may be applied for that field in accordance with laws and regulations, the Internal Rate of Return (IRR) is estimated less than 15%.
3

B P M IG A S

Marginal Field Candidates

Working Area / Block

Undeveloped Field

Field "A" (producing)

Field "B" (producing)

B P M IG A S

Type of Incentive
20% Operating Cost*) recovery up-lift.
Other incentive packages that may be applied for that field in accordance with the prevailing PSC, laws and regulations.

*) Under Definition of the PSC, the Operating Cost consist of:


1. Current Years Non Capital Costs 2. Current Years Depreciation for Capital Costs

Marginal Field Incentive


B P M IG A S

The Mechanism

Incentive is not permanently given and will be evaluated on yearly basis. The new incentive package is issued in order to improve the economics of the field, after receiving the incentive, the IRR of the field is expected at least 15%. (The Incentive is ON) The Incentive will be removed if the actual cumulative IRR has reached 30% (The Incentive is OFF). The Incentive will be re - a pllied if the actual cumulative IRR in the followong year has dropped below 15%.
6

B P M IG A S

The Concept of IRR Cumulative


10,000
Net Cash Flow

5,000

US$ (000)

2005 2006 2007 2008 2009 2010 2011 2012 2013

(5,000)

(10,000)

IRR = 18.5%

(15,000)

Year
7

20%

IRR Cumulative
B P M IG A S

10% 0%
2005 2006 2007 2008 2009 2010 2011 2012 2013

-10% -20% -30% -40%


10,000
Net Cash Flow

IRR = 18.5%

5,000

2005 2006 2007 2008 2009 2010 2011 2012 2013

(5,000)

(10,000)
8

(15,000)

B P M IG A S

Incentive OFF
50% 40% 30% 20% 10% 0%
2005 2006 2007 2008 2009 2010 2011 2012 2013 IRR Cumulative if Incentive not OFF IRR Cumulative

-10% -20% -30%


9

B P M IG A S

Most Likely Case


"On - Off" Mechanism
Expected IRR Cumulative Trend if the Incentive is NOT Removed

IRR Cumulative

Incentive "Off"

Incentive "On"

30%

15%

Year
10

B P M IG A S

Extreme - Case
"On - Off" Mechanism
Expected IRR Cumulative Trend if Incentive is NOT Removed

IRR Cumulative

Incentive "On"

Incentive "Off"

30%

15%
Incentive "On" Incentive "Off"

Year
11

B P M IG A S

Illutration

Marginal Field ( Realization) Marginal Field ( Initial Condition )

Field "A" (producing) Field "B" (producing)

12

B P M IG A S

Always On - Case
"On - Off" Mechanism

IRR Cumulative

Incentive always "On"

30%

15%

Year
13

B P M IG A S

Procedure

Registration & Submission


1. PSC could register the candidates for marginal field by submitting the summary of POD. BPMIGAS will response by sending the written answer no longer than 10 working days. No longer than 6 months following the registration, PSC should submit complete POD (in order to speed-up the process, the draft of AFE proposal need also to be attached). Registration period is 12 months (25 April 2005 24 April 2006)

2.

3.

14

B P M IG A S

Procedure

Evaluation, Approval & Implementation 1. When submitting the POD, the assumption for oil price is US$ 25 per barrel. 2. BPMIGAS will approve or not approve the POD proposal by sending the written answer to the PSC no longer than 30 days after receiving the POD proposal. 3. PSC should commence the activities no longer than one year after POD approved.
15

B P M IG A S

Procedure

Evaluation, Approval & Implementation

4. The commencement of the activies is declared if:


Tender Plan is appoved; or Tender Announced; or Execution of the Field Development

16

B P M IG A S

Procedure

Implementing and Reporting 1. PSC should make the special book account for marginal field. 2. The marginal field insentive is taxable.

17

You might also like