Renewable Purchase Obligation Issues and Challenges

Mithun Chakraborty Corporate Strategy and Planning Tata Power Delhi Distribution Limited

TATA POWER DELHI DISTRIBUTION LIMITED

Joint Venture of Tata Power and Govt. of Delh

License Area: North and North West Delhi (51 Consumer Base: 1.3 Million Employee Base: 3858 Peak Load Served: 1500 MW

ISO 9001, 14001, 18001, 27001 ; SA 8000 Cer

Delhi Renewable Power Obligation Regulations

Regulations notified by DERC on October 1, 2012

mandate - 3.40% (out of which 0.15% Solar) in FY 13 to increase to 9% (out of w % Solar) in FY 17.

can be met through Own Generation /Purchase from other licensee(s)/ sources hase of RECs

term Power Purchase arrangements shall be made with prior approval of mission ; long term PPAs to be approved on case to case basis.

matic approval on year to year basis if tariff considering capital subsidies/GBI/ on credits etc. is < APPC during a particular year

ailing to fulfill RPO, DERC may direct entity to deposit an amount determined by C on basis of shortfall in units of RPO and forbearance price decided by CERC

ch of license conditions if licensee fails to deposit within 15 days of direction

TPDDL Renewable Purchase Obligation


Units Input Non Solar Solar (MUs) Non Total Solar (MUs) (MUs)

Solar

Total

Equivalent Generation Capacities (MW

Solar

Bio Mass 68% 44 67 93 124 158

Small Hydro 40% 74 113 158 210 269

Bagasse

Wi

8% 8,000 8,640 9,331 0.15% 3.25% 3.40% 0.20% 4.60% 4.80% 0.25% 5.95% 6.20% 12 17 23 30 38 260 397 555 736 941 272 415 579 766 980

19% 7 10 14 18 23

46% 65 99 138 183 234

23

12

19

27

10,078 0.30% 7.30% 7.60% 10,884 0.35% 8.65% 9.00%

36

46

TPDDL Solar Journey


Name of Solar plant Corporate Office Cenpeid Solar Traffic light Madhuban chowk Pooth Khurd Keshav Puram Cennet Narela-7 Clear Water Bawana Narela-II DSIDC GTK Grid RG-5 Grid RG-22 RG-23 RG-24 RG-2 Total installed Capacity Capacity in KW 3.96 14.85 1.5 54 1000 25 45 43 60 25 225 50 55 24 24.5 1650.81 Status Commissioned on 26th Dec08 Commissioned on 24th Dec08 Off grid-Commissioned on 10th Jan10 Commissioned on 18th Mar10 Commissioned on 16th Nov10 Commissioned on 27th Dec10 Commissioned on 7th Dec10 Commissioned on 19th April11 Commissioned 27th July11 Commissioned on 5th Oct11 Commissioned on 30th Mar12 Commissioned on 30th Mar12 Commissioned on 30th Mar12 Commissioned on 30th Mar12 Commissioned on 30th Mar12

Snapshot of Solar Projects

olar Photovoltaic project

15 kWp Solar Photovo

225 kWp Solar Photovoltaic project

Solar Photovoltaic project

55 kWp Solar Photovolta

Some Issues

Unavailability of sufficient renewable capacity/ RECs to meet RPOs

Mode for tie up of Renewable Energy Competitive Bidding / Bilateral oute or both

9% CUF specified; may be difficult to achieve as per our experience

mposition of intrastate Transmission charges and losses on Renewable nergy

mart Grid infrastructure to integrate rooftop renewable projects