Professional Documents
Culture Documents
18 Investment Appraisal
Power system economic analysis may be defined as the process by which the impact of investment in power generation or transmission plant on the financial results of an organisation's operations is measured. Its purpose is to supply one of the bases for management decision. The function of economic analysis is to estimate as closely as possible the economic benefit to the utility of proceeding with an investment in power generation or transmission equipment.
The way in which investment is analysed economically varies to reflect the differing requirements of invested capital.
18.2 Inflation
Inflation is a positive feedback sociological and economic effect that links cost of production (2-3% pa) cost of living (3-4% pa) salaries (1-2% pa)
cost of production (2-3% pa) Affects different sectors of ESI costing processes differently, linked to interest borrowing rates and fuel/energy costs
Payback
Future Worth of all Cost and Benefit Streams % annual inc 3 Year Capital O&M+fuel Benefit 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 -210400000 -23034469 -24437268 -25170386 -25925498 -26703263 -27504361 -28329491 -29179376 -30054757 -30956400 -31885092 -32841645 -33826894 -34841701 -35886952 63912960 66495044 67824944 69181443 70565072 71976374 73415901 74884219 76381904 77909542 79467732 81057087 82678229 84331793 86018429 Years to payback -12624000 -10928731 -9060988 -7045374 -4872739 -2533395 -17078 0 0 0 0 0 2 Interest 6 Amount ow ed -182145509 -151016464 -117422894 -81212322 -42223251 -284633 44784698 90489541 136816687 183769829 231352469 279567911 Cash flow 28254491 31129045 33593570 36210572 38989070 41938618 45069332 45704843 46327146 46953141 47582640 48215442
-210400000 -210400000
0 328419246 48851335 0 377909338 49490092 0 428040815 50131477 7 NPV from Excel287,566,868 IRR fm Excel 16.29%
All cash incomes are tabulated over the trading period The total cash income for each year is then discounted back the present, or year 0, and added up to give a single sum. 1
PWF
1 PWF 1 k n
1 k n
Difference present value of income and present value of expenditure is a good guide to the economic viability of a project must always be positive, when a project will produce net income.
Discount Rate 3 O&M cost Year Disc factor Stream 0 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 0.971 0.943 0.915 0.888 0.863 0.837 0.813 0.789 0.766 0.744 0.722 0.701 0.681 0.661 0.642 Pres Worth
Present Worth of all Cost and Benefit Streams Interest Charge Benefit Stream 62051417 62677956 62069432 61466816 60870051 60279080 59693846 59114294 58540369 57972016 57409181 56851810 56299851 55753250 55211957 886261326 Amt Ow ed Cash flow -210400000 -210400000 -182968455 -153626345 -122883469 -90710845 -57078530 -21955598 14689893 50769718 86275618 121213165 155587877 189405218 222670599 255389381 287566868 Calc NPV 27431545 29342110 30742876 32172624 33632314 35122932 36645491 36079825 35505900 34937547 34374712 33817341 33265382 32718781 32177488 287566868
-22363562 -12256311 -23034469 -10301377 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -8292087 -6259723 -4203268 -2121678 -13886 0 0 0 0 0 0 0 0
-344846128 -43448330
PW benefits
Discount Rate 3 O&M cost Year Disc factor Stream 0 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 0.971 0.943 0.915 0.888 0.863 0.837 0.813 0.789 0.766 0.744 0.722 0.701 0.681 0.661 0.642 Pres Worth
Present Worth of all Cost and Benefit Streams Interest Charge Benefit Stream 62051417 62677956 62069432 61466816 60870051 60279080 59693846 59114294 58540369 57972016 57409181 56851810 56299851 55753250 55211957 886261326 Amt Ow ed Cash flow -210400000 -210400000 -182968455 -153626345 -122883469 -90710845 -57078530 -21955598 14689893 50769718 86275618 121213165 155587877 189405218 222670599 255389381 287566868 Calc NPV 27431545 29342110 30742876 32172624 33632314 35122932 36645491 36079825 35505900 34937547 34374712 33817341 33265382 32718781 32177488 287566868
-22363562 -12256311 -23034469 -10301377 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -8292087 -6259723 -4203268 -2121678 -13886 0 0 0 0 0 0 0 0
-344846128 -43448330
Forecast load to be met (16.2) Demand profile and load duration curve (16.3) Installed plant capacity(ies) Plant and project economic lifetimes (16.8) Capacity factors and network margins (16.10) Additional infrastructure required roads, electrical network extension
18.7 Profit
When all expenses have been covered there remains a surplus which is in part put back into the enterprise for expansion and in part paid in the form of dividends to the owners of the power utility, that is, the share-holders. It is a reward for risks taken and for a management task well done. Without this profit there would be no incentive for people to invest their money in the enterprise, or for the management to feel personal responsibility for cost-efficient operation. It should be noted that the simple payback period calculated as above would be extended by the taking early positive revenue to profit since it pays shareholders at the expense of not reducing the amount owed as rapidly as possible.
an increase in demand of 200MW is to be met by installation of an open cycle gas turbine which requires a switchyard to connect into the 132kV network and a 20km extension to the 132kV network.
System Demand Demand Type Plant margin Rated plant capacity Plant capacity factor Average plant output pow er Availability Annual operating time Annual energy sent out Generator efficiency Turbine efficiency Boiler efficiency
200 MW base load 20 % 240 MW 80 % 192 MW 95 % 8322 hrs 1597824 MWh/year 92 % 35 % Not applicable
Tariff Annual energy sent out Annual income to benefit stream Other w orks costs Annual OW cost Total OW + fuel costs to cost streams
Average chemical Pow er In 596.27 MW Annual chemical Energy In 17863870807 MJ Calorific value of gas 50,000 MJ/tonne Annual volume of gas required 357277 tonnes Cost of gas Fuel costs Capital Cost Estimation Plant item Generating Plant Sw itchyard Transformer 20km 132kV line Cost/kW Unit cost 000/** Rated plant capacity **MW/MVA 750 240 300 Total 877 Cost () 180000000 10000000 5400000 15000000 -210400000 to cost stream 60 /tonne 21436645 /year
18000 750
System Demand Demand Type Plant margin Rated plant capacity Plant capacity factor Average plant output pow er Availability Annual operating time Annual energy sent out Generator efficiency Turbine efficiency Boiler efficiency
200 MW base load 20 % 240 MW 80 % 192 MW 95 % 8322 hrs 1597824 MWh/year 92 % 35 % Not applicable
Tariff Annual energy sent out Annual income to benefit stream Other w orks costs Annual OW cost Total OW + fuel costs to cost streams
Average chemical Pow er In 596.27 MW Annual chemical Energy In 17863870807 MJ Calorific value of gas 50,000 MJ/tonne Annual volume of gas required 357277 tonnes Cost of gas Fuel costs Capital Cost Estimation Plant item Generating Plant Sw itchyard Transformer 20km 132kV line Cost/kW Unit cost 000/** Rated plant capacity **MW/MVA 750 240 300 Total 877 Cost () 180000000 10000000 5400000 15000000 -210400000 to cost stream 60 /tonne 21436645 /year
18000 750
System Demand Demand Type Plant margin Rated plant capacity Plant capacity factor Average plant output pow er Availability Annual operating time Annual energy sent out Generator efficiency Turbine efficiency Boiler efficiency
200 MW base load 20 % 240 MW 80 % 192 MW 95 % 8322 hrs 1597824 MWh/year 92 % 35 % Not applicable
Tariff Annual energy sent out Annual income to benefit stream Other w orks costs Annual OW cost Total OW + fuel costs to cost streams
Average chemical Pow er In 596.27 MW Annual chemical Energy In 17863870807 MJ Calorific value of gas 50,000 MJ/tonne Annual volume of gas required 357277 tonnes Cost of gas Fuel costs Capital Cost Estimation Plant item Generating Plant Sw itchyard Transformer 20km 132kV line Cost/kW Unit cost 000/** Rated plant capacity **MW/MVA 750 240 300 Total 877 Cost () 180000000 10000000 5400000 15000000 -210400000 to cost stream 60 /tonne 21436645 /year
18000 750
is 7 years when evaluated with PW income and expenditure. This is found to be the same in the PW trading account when based on a discount rate of 3%
Future Worth of all Cost and Benefit Streams 3 2 6 Amount Cash Benefit 63912960 66495044 67824944 69181443 70565072 71976374 73415901 74884219 76381904 77909542 79467732 81057087 82678229 84331793 86018429 Years to payback Interest -12624000 -10928731 -9060988 -7045374 -4872739 -2533395 -17078 0 0 0 0 0 ow ed -182145509 -151016464 -117422894 -81212322 -42223251 -284633 44784698 90489541 136816687 183769829 231352469 279567911 flow 28254491 31129045 33593570 36210572 38989070 41938618 45069332 45704843 46327146 46953141 47582640 48215442 -210400000 -210400000 -23034469 -24437268 -25170386 -25925498 -26703263 -27504361 -28329491 -29179376 -30054757 -30956400 -31885092 -32841645 -33826894 -34841701 -35886952
0 328419246 48851335 0 377909338 49490092 0 428040815 50131477 7 NPV from Excel287,566,868 IRR fm Excel 16.29%
Discount Rate 3 O&M cost Year Disc factor Stream 0 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 0.971 0.943 0.915 0.888 0.863 0.837 0.813 0.789 0.766 0.744 0.722 0.701 0.681 0.661 0.642 Pres Worth
Present Worth of all Cost and Benefit Streams Interest Charge Benefit Stream 62051417 62677956 62069432 61466816 60870051 60279080 59693846 59114294 58540369 57972016 57409181 56851810 56299851 55753250 55211957 886261326 Amt Ow ed Cash flow -210400000 -210400000 -182968455 -153626345 -122883469 -90710845 -57078530 -21955598 14689893 50769718 86275618 121213165 155587877 189405218 222670599 255389381 287566868 Calc NPV 27431545 29342110 30742876 32172624 33632314 35122932 36645491 36079825 35505900 34937547 34374712 33817341 33265382 32718781 32177488 287566868
-22363562 -12256311 -23034469 -10301377 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -23034469 -8292087 -6259723 -4203268 -2121678 -13886 0 0 0 0 0 0 0 0
-344846128 -43448330
When tested with a 16.3% discount rate = IRR , NPV becomes 0 and BCR becomes 1