Professional Documents
Culture Documents
Constructor
Project Title:
LOADING / OFFLOADING STATIONS AND METERING SKIDS INSTALLATION AT TANK BATTERY / GUEBIBA BASE & TRAPSA
Submission Date
Oct 28 2013
Revision Details
Submitted for approval
Prepared By Checked By
A.FERCHICHI A.FERCHICHI
Approved by
This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of Halwani Company being obtained. Halwani Company accepts no responsibility or liability for the consequences of this document being used for a purpose other than the purposes for which it was commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm his agreement to indemnify Mott MacDonald for all loss or damage resulting therefrom. Halwani Company accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned.
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
: :
OF 053/2013 Supply and Erection of Trucks loading and offloading steel stations at Tank Battery / Guebiba base & Trapsa, including procurement and pre-construction will all Civil & Steel Works needs. TANK BATTERY Station GUEBIBA Base TRAPSA Terminal Civil Works: Concrete Mixer Truck, Concrete Pump, Hoses / Concrete shoots, Concrete buckets, Air Compressor, Survey Equipment, Level, Total Station ( Surveying instrument for checking the levels & distances ), Masonry Accessories, Wheel Barrows, Concrete Vibrators Erection Steel Works: Ladders, Mobile Scaffold, Hand tools, Forklifts, Crane
Site(s)
Equipment to be used
: : :
Oil & Gas production and/or Storage area(s) Working at height, weather, moving vehicles, Safety harness & lanyard, hard hats, gloves, overall clothing (with hi-viz clothing in need), goggles, safety footwear All staff are experienced in the erection of steel frames structure and fully aware of risks involved. Only qualified personnel to operate plant. Young persons, persons with condition, anyone with a disability. a medical
Employees involved
Rev. : 00
Sheet : 2 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
ACTIVITY Sequence of working activities Vehicle/ Equipment movement inside the restricted area
HAZARDS The potential to cause harm (heath, Injury, Property damage, environment etc.) Vehicle movement
CONSEQUANCES (The harm which could possibly occur) Driver Labors Forman
Close supervision Identify vehicle routes Vehicle to leave the area once job is complete Journey Management system to be implemented
Manual Excavation
Labors Forman
HIGH
All heavy machinery / vehicles should not be allowed working without assessing banks man Carry out a physical survey to whole surrounding area Limited workers allow to work at one location Close supervision
LOW
Mechanical excavation
Employees working near the moving equipment/trench Environmental hazard Equipment moving
HIGH
Emergency procedure and contingency plan to be in place and cascaded to all crew members and really available at sit locations Primary and secondary assembly point to be assigned by considering the prevailing Close supervision
LOW
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 3 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
Lifting operation and installation of pre-cast foundations and slabs foundations and slabs into the trench
Labors Forman
HIGH
Close supervision Identify rigging location Lifting machine placement shall be at safe distance from live lines/equipment Lifting machine leave the plant once complete the job
LOW
Labors Forman
HIGH
Close supervision
LOW
HIGH
All rotating parts of the machine should be in place Avoid long time exposure to dust/vibration: frequent rests Employ a minimum hand grip to observe less vibration
LOW
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 4 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
fall of person from height Failure of slings or other lifting gears Electrocution from portable hand tools Cut and bruise injuries to erectors Unsafe lifting and fixing by erectors Untrained erectors Miss communication between rigger, tirfor lifters and crane operator. Structural failure Collapse of edge protection
Erector Forman
HIGH
All works to be carried out as per approved method statement document All crane lifts to be controlled by a competent and authorize signaler/Banks man. The crane will be tested and certified as per manufacturers regulations. All lifting gear (Slings, chain, etc.) to be tested. Daily before the start of work Forman should visually examine all lifting gears for any defects: Responsibility Site Forman Only competent erectors to be used for the structure erection Mutually understandable signals to be used between crane operator and rigger. If necessary use the walky talkie All erectors to use full body harness and latch them to the standard lifeline Forman should inspect the precast structure on arrive for any crack or defects than can lead to the collapse of it during erection All the workers and staff should have specifics site safety induction by safety officer and records to be kept. recommendations and statuary
LOW
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 5 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
Failure of Crane, Slings, clutch Fall of persons from height Crushing injuries to workers caused by coming between structure parts and truck Overloading the crane Structural failure Impact or collision
Labor Operator
HIGH
Respective supervisor/ operator should examine the slings Clutches, before starting the work. Cranes should have valid third party inspection certificate Clearly marking safe working load Labors should use ladders to go up release the clutch Labors always wear full body harness and latch them at Top Labors should be very careful during the work and not to put body parts under the structure part(s) Competent and trained operator to do the lift Every lift has to be pre-planned.
LOW
Collapse of scaffold Fall from height Falling from ladders Falling objects Crane associated hazards Splinters, protruding nails, sharp edges Unsafe positioning of
HIGH
Scaffold must be erected by competent person/ under competent supervision. All crane lifts to be controlled by a competent and authorize signaler /Banks man. This risk assessment must be communicated to the workers on site. An effective access/egress design is to be followed All platforms are to be fully boarded and hand
MED
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 6 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
ladders
railed No board is to be unrestrained at its ends. Toe boards are to be installed on all used platform levels. Tool-retainers (boxes and buckets) to be used to reduce the risk of tools falling form scaffold. All workers in elevated positions are to wear a safety harness. Secure the ladders/ stairs properly. Minimize number of people in the area. A suitable qualified supervisor or deputy should be present during the erection of the scaffolds. Stairs should have regular landings where workers can rest effectively. Regular cleaning will be done to minimize trip hazards and the buildup of surplus materials on platforms
10
Fire and explosion Metal spatter Prolonged exposure to heat Gases & fumes Improper welding equipments
Welder Helper
HIGH
A competent fire watch with suitable fire extinguishers must be Improper welding equipments present at hot work area Where possible all flammable material should be removed from the welding operations area. Only competent and authorized personnel to use equipment (i.e. welders, cutter/burners).
LOW
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 7 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
Appropriate PPE to be used when carrying out hot works operations Equipment to be well maintained and inspected as per Manufacturers recommendations. All oxy/Acetylene cutting sets must be provided with flash back arresters. Cylinders must be stored, handled and transported in a safe manner. Effective fume control equipment should be provided when working in confined area. (in need) Extra ventilation should be introduced to reduce the likelihood of heat stress occurrence. (in need) The placing of a second person on stand-by in case of emergency should be considered. Prolonged welding operations to be shielded from the sightline of adjacent operatives to reduce the risk of 'arc-eve'.
11
Work at height
Fall person Absence edge protection Trips Falling object from up Improper Accesses
Labor Staff
HIGH
Provide guardrail all the un-protected edges Close the open wholes property Arrange barricading and warning signs wherever needed. Must wear full body harness and latch the lanyard. Work area very clear
MED
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 8 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
Make sure nobody can have work in the up Before using any access make inspection it is safe Secured your tools by wire rope
12
Fire Poor House keeping Slip, trip and falls Poor posture Improper use of work station Over loading of electric sockets Trailing cables on walk ways
Office Staffs
HIGH
Good housekeeping habit must be enforced Control smoking in temporary cabins Ensure firefighting procedure Provide emergency access and keep them clear always. Train employees on manual handling and ergonomics where applicable. Use conduits for electrical cords. Use right kitchen wares and equipments Prepare emergency evacuation plan and taught to office staffs Assign trained fire warden for all areas.
LOW
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 9 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
1. Risk assessment to be made available and approved by the Owner of the project 2. Method Statement to be made available and approved by the Owner of the project 3. Ensure that all manpower safety inducted and know the Emergency numbers (Fire = 198 | Medical 190)
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 10 of 11
HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: RISK ASSESSMENT PROJECT: LOADING / OFFLOADING STATIONS
F = Frequency
S = Severity
R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)
Rev. : 00
Sheet : 11 of 11