You are on page 1of 29

www.lipower.

org
THREE PHASE PADMOUNTED
TRANSFORMER TRAINING
What is a Three-Phase Pad Mounted Transformer?
What are its Applications?
How is it Installed?
How is it Wired?
The Specification Package
The Specification Letter
Miscellaneous
What We Will Cover
What is a Three-Phase Pad Mounted Transformer?


Outside


Metal Encased, Tank, Fins, Cabinet
Sits on a Three Piece Vault
Fragile Enclosure, Not for Storage


Inside Contains


Oil Tank, Windings, Terminals


Primary and Secondary Compartments


Grounding Loop


Cables and Terminations
What is a Three-Phase Pad Mounted Transformer?


Steps Down Primary Voltage to Secondary


Primary Side (4kV, 13kV, or both)


Secondary Side (120/208v, 277/480v)


Three Phase Wye Configuration Only


Pad Mounted, or Submersible


Di-Electric Fluid (insulates and cools)


LIPA Sizes Range From:


75KVA to 1000KVA for 120/208


75KVA to 1500KVA for 277/480


Special Order 2500KVAs
The outside of a Three-Phase Pad Mounted Transformer
Side View of a 150KVA Pad Mounted Transformer
The Outside of a Three-Phase Pad Mounted Transformer


Orientation Away From Building


Clearances


5 From Transformer to Building Wall


10 to Vent Openings, Doors, Windows


25 to Non-Fire-Rated Openings


Auditorium Exits


Truck Accessible (delivery & removal purposes)


NEC Class 1, Division 1, and 2 Locations Shall Require a
Minimum 25 ft. Clearance (oil, gas, etc)


Set Vault Level, Grade to Slope Away


Traffic Protection
The Inside of a Three-Phase Pad Mounted Transformer
Inside a Three-Phase Pad Mounted Transformer
Primary Compartment
(left side)


Primary Connections
(radial, or loop)


Incoming - H1C, H1A,
H1B


Outgoing - H2B, H2A,
H2C


No Load Tap Changer


A Through E (2.5%
increments, middle
is zero boost)


Bayonet Fuses, Protect
Primary Side of
Transformer
Primary Compartment


Load Break Elbows


Sizes: #2, 1/0, 3/0


Lightning Arrestor
Elbows (radials, and
open points)


Static Drain Wires
(#14, and #10 Cu.)


Grounding Loop
#2BTN, One HLC


Primary Bushings


Standoff Bushing
Slots (open point)
Inside a Three-Phase Pad Mounted Transformer
Primary L/B Elbow


Load Break Elbow, Bushing,
Static Drain Wire, and Primary
Cable


Detail in Spec. Package


Follow Mfg. Instructions


Pulling Eye


Test Point, & Cap


5 of Taped Neutral


#2 EPR Insulated May be
Hylinked


Sealing Strip, 36 Below Hose
Clamp
Inside a Three-Phase Pad Mounted Transformer
Primary Bushing


Supplied by LIPA with
L/B, L/A Elbow


Screws in


Must be Kept Clean,
Contamination Will
Cause Electrical
Failure


#14 Static Drain Wire
From Eyelet to
Grounding Split Bolt


L/B Elbow Should
Cover Yellow (now
RED) Band
Inside a Three-Phase Pad Mounted Transformer
Secondary Compartment
(right side)


Secondary Spades;
X0, X1, X2, X3


Nema 2 Hole Lugs
(tinned alum. Or Cu.)


Al Lug - Extra
Belleville Washer Req


Oxide Inhibitor on Al


Cu to be Tinned, or
Alloy plated


750 Cu now Accepted


Buss Supports
Inside a Three-Phase Pad Mounted Transformer
Secondary
Compartment


Color Coding


120/208v or
277/480v


Integrated/Isolat
ed


8 Sets Max


Grounding Pads,
Loop, Split Bolts,
Ground Rods


Oil Drain Valve
Inside a Three-Phase Pad Mounted Transformer
Secondary
Compartment
Pressure
Relief Valve
Do Not Pull
Oil Fill Level
Oil
Temperature
Gauge
Oil Level
Gauge
Inside a Three-Phase Pad Mounted Transformer
Nameplate


Identifies Primary and
Secondary Voltage


Indicates Voltage on
Different Tap Settings


Shows Internal Coil
Configuration


Indicates Transformer
Weight


Indicates Transformer
Impedance
Inside a Three-Phase Pad Mounted Transformer
Common equipment


Primary Cable


Sizes: 3-2/c#2, 1/0, 3/0


Secondary Cable


Sizes: Minimum #2, Maximum 750


Maintain 5 min. Slack in Vault


Maintain as Much Physical Separation as Possible


Grounding Pads, Lugs, and Split Bolts


Bare #6 Cu to Ground Rods


Bare Tinned Copper #2 for Ground Loop
Inside a Three-Phase Pad Mounted Transformer
What are its Applications?


Typical for Large Load, Non-
Residential Customers; Long
Distance From Existing
Facilities; and Looped
Commercial Industrial Parks


Pad Mounted Transformers are
LIPAs Standard Installation,
Non-Standard is Submersible, or
Network


Transformer is Delivered,
Owned, and Maintained by LIPA
for Secondary Metered Service
How is the Three-Phase Pad Mounted Transformer
Installed?


Set on a Three Piece Vault, Always Provided
by Contractor (see approved vendor list)


Pad Orientation


Primary Side, Secondary Side


Doors to Face Away From Building


10 Clear in Front of Pad for Switching


Grade Away 1% Slope


Old Way Poured Foundation (slab)
Primary and Secondary Cables Have no
Slack


Boom Truck Delivers Transformer, Lifts it
onto Vault

How is the Three-Phase Pad Mounted Transformer
Installed?
Boom Truck


Can Deliver All
Transformers
Line Truck


Delivers up to
500 kVA
Who Wires the Three-Phase Pad Mounted
Transformer?
LIPA Provides


Three Load Break Elbows (rated for 200
ampere)


Three Lightning Arrestor Elbows


With Three NEMA 2-Hole Lugs


One Hot Line Clamp


Bushings Come as a Pair With L/B Elbow and
L/A Arrestor Elbow
Radial Installation


Contractor Installs Primary and Secondary Cable


Contractor Wires L/B and L/A Elbows


Contractor Makes Secondary Connections


Contractor Wires All Grounding


Contractor Supplies Secondary Lugs, Static Drain
Wires, Ground Rods, Ground Wire, and Grounding
Split Bolts
CIPUD Installation


Contractor Supplies and Wires Secondary


LIPA Wires Primary & Grounding
Who Wires the Three-Phase Pad Mounted
Transformer?
Specification Package Details


Provides Information Common to All Jobs


Pad Specifications, Vault Details


Primary Side, Secondary Side


Contractor to Discuss Location Before Pad is Set


Knock Outs: 4 PVC Sleeve Flush With Wall, Concreted in Place


Duct Seal or Cap Unused Conduits


Galvanized Conduits Require Bonding


Protection From Traffic


Bollard 3.5 Heavy Steel Wall (minimum)


Concrete Filled


Must be Painted Yellow


Doors Must be Able to Open


Required on All Sides Subject to Vehicular Traffic
Primary Cables


Phases Must be Identified (1, 2, 3 rings), on Both
Extremities


15kV Tree-Retardant Cross-Linked Polyethylene for
Aluminum (TR-XLPE)


Ethylene Propylene Rubber (EPR) for Copper


Semi-Con 12 Mil


Insulation 220 Mil, Insulation Shield 30 Mil Semi-Con


J acket 50 Mil Semi-Con
Specification Package Details
Secondary Services


480v - One Service


Exception: Fire Pumps


208v - Multiple Services


Services Must be Labeled
Cables


480v (must be installed in conduit)


USE-2, XHHW-2, or RHW-2


8 Sets Max


208v


USE-2, THW-2, THWN-2, XHHW-2, or RHW-2*


*With neoprene or hypalon jacket only
Specification Package Details
Three-Phase Specification Letter


Gives Project Specific Details, Such as:


Reiterates Customer Load Letter


Designated Riser Pole, or Point of Termination


Describes Cable Ownership


Provides Costs, if Any


Inrush Information, Motor Starting Limitations


Restates Basic Installation Rules,


Call Before You Dig


Repeats Primary and Secondary Cable
Specifications
Miscellaneous


Provide Advance Notification of Projects


Access to an Energized Vault is Forbidden


Industrial Code Rules 753, and 57


These Requirements Conform to the NEC


Contractor to Comply With:


Applicable Codes


Three Phase Transformer Spec. Package


Redbook


Lists Distribution Design Representatives


www.lipower.org
QUESTIONS
?