1. Installation must be performed by a licensed electrician and all
wiring must conform to local electrical code. Read all instructions
before beginning installation. Contact R&B Wagner, Inc. with any
questions at 888-243-6914 or systems@mailwagner.com.

10. Carefully push the remaining wire into the hole. Push the Ledpod
into the hole. The witness mark on the Ledpod should be pointed
towards the pathway. If the Ledpod does not push in, remove and
check spring alignment (g. 6).

2. Turn off the power before terminating the Driver or xtures. Never
perform electrical work on a live circuit.

11. Mount driver in a suitable NEMA rated enclosure. Ledpods may be


used in wet location if driver is mounted in suitable rated enclosure
and wire connections are made with listed wet location terminations.
Note: Driver must be a Listed Component, Class 2, and 24 VDC.

3. Ensure all Ledpod holes are de-bured inside and out.


4. Install 24 VDC positive (+) and negative (-) wires down hand rail
(g. 1). Refer to driver spec sheet for wire gauge recommendations.

12. Connect the driver to the AC power mains using location appropriate electrical terminations. Ground the driver and enclosure using
the mounting studs inside the enclosure.

5. Pull a loop of the 24 VDC wires out of the 25mm Ledpod hole (g.
2).
6. Install the retaining spring (g. 3).
7. Install the Scotchlocs to the 24 VDC main wires and the step
down transformer (fig. 4). Ensure that the polarity of wires from
the step-down transformer (+ = red, - = black) connect to the
correct polarity main 24 VDC wires.
8. Carefully push wires, Scotchlocs, and step down transformer
into the hole (g. 5).
9. Plug the Ledpod into the step-down transformer.

g. 1

g. 2

g. 3

24 VDC wires
Spring Clip

g. 5

g. 4

g. 6

Scotchlocs
Step-down
transformer

WAGNER ARCHITECTURAL | (414) 716 8401 | SYSTEMS@MAILWAGNER.COM | WAGNERARCHITECTURAL.COM

2013

Wagner Lumenrail Ledpod


Post Mount Wiring Diagram
3M Scotchlock wire connectors
Ledpod assembly

Driver with Enclosure


Soft Start
Relay

120 - 277 Volt Input


(Conduit Entry)

120 - 277 Volt Input


(Conduit Entry)

Secondary Feed Routed


Through Stainless Bracket

Soft Start
Relay

Wall Mount Wiring Diagram


3M Scotchlock wire connectors
Ledpod assembly

Driver with Enclosure


Soft Start
Relay
120 - 277 Volt Input
(Conduit Entry)

Secondary Feed Routed


Through Stainless Bracket

Soft Start
Relay

120 - 277 Volt Input


(Conduit Entry)

Remote Distance Chart


EMBEDDED

SURFACE MOUNT

MAXIMUM DISTANCE FROM DRIVER TO FIRST LED


Anchor Plate
With Cover Flange

Cover Flange
With or Without
Set Screw

WIRE SIZE

10
AWG

12
AWG

14
AWG

16
AWG

18
AWG

DISTANCE

120'

71'

46'

29'

18'

13/16"

1"

24 VDC
100W
Driver

41/2"

Concrete

Rockite
or Kwixset

Concrete

or
conduit

NOTE: Wire to be supplied by installer, appropriately sized, and meeting local


electical code.