Consulting firms typically use which of the following techniques to plan and monitor the engagements
of the firm or specific projects?
Qualitative forecasting
Quantitative layout
Materials requirements planning (MRP)
CPM/PERT
Which project progress technique includes the essential features of a project plan, budgeted cost of
work scheduled and budgeted cost of work performed?
Gantt chart
Cost analysis
Critical path method
Earned value management
Which of the following would be the result of subdividing a project?
Job categories
Job orders
Work events
Tasks
The vertical axis on a Gantt chart is usually which of the following?
Activities
Cost
Time
Profit