Professional Documents
Culture Documents
Fareed Ebrahim
ACM Automation Inc.
#700, 940 6th Avenue SW
Calgary, Alberta
febrahim@acm.ca
German Luna-Mejias, P. Eng
ACM Automation Inc.
gluna@acm.ca
Fareed Ebrahim
ACM Automation Inc.
#700, 940 6th Avenue SW
Calgary, Alberta
febrahim@acm.ca
German Luna-Mejias, P. Eng
ACM Automation Inc.
Keywords: Procedure HAZOP, Start-up/Shutdown
Abstract
Statistics show that approximately 65% of process safety related incidents occur during the startup/shutdown operations of the plant. Yet, the bulk of the risk assessments performed today focus
on the normal operation of the plant. A major contributor to the lack of start-up/shutdown risk
assessments is the lack of a strongly documented methodology. One method of performing this
assessment is through the HAZOP of start-up/shutdown procedures. This HAZOP involves a
step by step review of the procedure with consideration given to the sequencing, delay, or
missing of steps involved in the procedure. By performing this review, required permissives are
identified, contingencies are developed and essential safeguards are identified. This will help
ensure the operations team is confident that they are performing the start-up/shutdown in a safe
manner. This paper focuses on the framework for guidelines, procedures and templates that are
necessary to perform this HAZOP. A practical approach with examples is presented.
1. Introduction
Currently, it is common practice to reserve a deviation in a continuous process HAZOP for startup and shutdown issues. Unfortunately, during analysis, this deviation if often not explored to its
full potential. This abrupt analysis is often due to the lack of available information and expertise,
lack specificity within the deviation, and time constraints. Yet, statistics provide a compelling
argument to improve the rigour associated with start-up/shutdown analysis. Approximately 65%
of process safety related incidents occur during these modes of operations1. To improve the
rigour associated with the assessment of start-up/shutdown, the HAZOP technique must be
further extended to the procedures for these modes of operation. Many sources are available
which explore the fundamentals of performing such a HAZOP1,2, and therefore, this paper will
focus on developing a methodology by expanding upon the commonly used HAZOP technique
for normal operating modes.
information, as well as the operating window for all instrumentation that will be referenced
during the start-up/shutdown operation.
2.2 Required Personnel
In addition to compiling the correct documents for the session, it is of equal importance to ensure
the correct personnel are in the room during the HAZOP. Similar to a process HAZOP,
representation from the process team, instrumentation, and operation is required. It is suggested
to have extra representation from the operations group to provide a more diverse perspective for
the brainstorming process. Furthermore, if the HAZOP is being performed at the commissioning
phase, it is recommended for the construction manager or equivalent representative to be present.
All seven guidewords may not be used for each start-up/shutdown procedure being analyzed.
Guidewords should be applied based on the complexity of the procedure. An example of a
simplified method is the two-guideword approach2 is contained in Table 2 below.
Table 2. Two-Guideword approach for Procedure HAZOP2
Guideword
Description
Omit
Incorrect
3.1
Application of Guidewords
Once pilots are lit, start lighting main burners (two per cell).
After completing the first ten pilots, light another ten but evenly distributed per cell.
Wait for 30 minutes or until the heater outlet temperature is stable
Continue lighting burners to increase the heater temperature at a rate of 50C/hour
until a temperature of 380C is reached.
5. Once temperature is stable and maintains at 380C, start injecting HP Steam and
continue lighting burners as required to prevent the heater temperature from dropping
below 350C.
3.2.1
Less
Example Deviation from Step 3: Adequate time is not allotted by operator for heater outlet
temperature to stabilize in an attempt to speed up start-up.
Consequence: Potential for a sudden temperature increase in heater leading to refractory damage
or flame impingement.
3.2.2 More
Example Deviation from Step 1: More than two burners are lit per cell in order to speed up startup of unit.
Consequence: Potential for a sudden temperature increase in heater leading to refractory damage
or flame impingement.
3.2.3 No
Example Deviation from Step 4: Additional burners are not lit by operator.
Consequence: If steam is injected into the heater when temperature is below 350C there will be
deactivation of catalyst within heater tubes.
3.2.4 Reverse
Example: Deviation from Step 3: Additional burners are lit prior to stabilization of heater outlet
temperature.
Consequence: Potential for a sudden temperature increase in heater leading to refractory damage
or flame impingement.
3.2.5
As well as
Example: Deviation from Step 2: Steam is injected by operator as well as lighting the additional
burners.
Consequence: If steam is injected into the heater when temperature is below 350C there will be
deactivation of catalyst within heater tubes.
3.2.6
Other than
Example: Deviation from Step 5: Natural Gas is injected into the heater instead of Steam.
Consequence: Overheating of tubes in reactor leading to tube damage and potential explosion.
3.2.7
Sooner/Later
Example: Deviation from Step 5: Steam injected to heater prior to temperature reaching 350C.
Consequence: If steam is injected into the heater when temperature is below 350C there will be
deactivation of catalyst within heater tubes.
3.3
As HAZOPs have developed over time, there has been a continued emphasis to add more semiquantitative aspects to the study. A major element of this semi-quantitative aspect is the
application of a risk matrix. Unfortunately, risk matrices are designed using a per year time
frame. This per year concept is of course not applicable to a procedure. Therefore, when
performing the procedure HAZOP, two options are available. One, is to avoid the risk ranking
and perform a fully qualitative analysis. Second, is to apply the risk matrix by avoiding the
yearly references contained in the likelihood, and setting a default likelihood of making an error
in the procedure to correspond with highest likelihood available (ie. frequent) on the matrix. This
is to quantify the fact that there is a possibility to make a mistake in executing the procedure at
any given opportunity for execution. For example, if a procedure step is incorrectly worded,
there is an opportunity for error every time that step is executed. The consequence levels outlined
in the risk matrix are not time constrained and therefore are easily applied to a start-up/shutdown
procedure HAZOP. Safeguards can then be applied in a fashion similar to process HAZOPs by
dropping the likelihood by one level.
3.4
Adding Safeguards
4.
Conclusion
5. References
[1]
Bridges, Bill. "Paper: How to Efficiently Perform the Hazard Evaluation Required for
Non-Routine Modes of Operation (Start-up, Shutdown, Online Maintenance)." Proc. of
2011 Global Congress on Process Safety., 2011
[2]
CCPS. "9. Extensions and Special Applications." Guidelines for Hazard Evaluation
Procedures. New York: Center for Chemical Process Safety of the American Institute of
Chemical Engineers, 1992. 257-67.
[3]