Professional Documents
Culture Documents
information on a company's value and situation. Cash flow can be used, for example,
for calculating parameters: it discloses cash movements over the period.
The role of Cash Flow:
to determine a project's rate of return or value. The time of cash flows into and
out of projects are used as inputs in financial models such as internal rate of
return and net present value.
to determine problems with a business's liquidity. Being profitable does not
necessarily mean being liquid. A company can fail because of a shortage of
cash even while profitable.
as an alternative measure of a business's profits when it is believed that
accrual accounting concepts do not represent economic realities. For instance,
a company may be notionally profitable but generating little operational cash
(as may be the case for a company that barters its products rather than selling
for cash). In such a case, the company may be deriving additional operating
cash by issuing shares or raising additional debt finance.
cash flow can be used to evaluate the 'quality' of income generated by accrual
accounting. When net income is composed of large non-cash items it is
considered low quality.
to evaluate the risks within a financial product, e.g., matching cash
requirements, evaluating default risk, re-investment requirements, etc.
Cash flow notion is based loosely on cash flow statement accounting
standards. It's flexible as it can refer to time intervals spanning over pastfuture. It can refer to the total of all flows involved or a subset of those flows.
Subset terms include net cash flow, operating cash flow and free cash flow.
To avoid the problem of shortage and surplus of funds financial planning is required
in financial management.Financial Planning involves designing the blueprint of the
financial operations of a firm. It ensures that just the right amount of funds are
available for the organisational operations at the right time and thereby, ensuring
smooth functioning of an organisation. The following are the points that highlight
the importance of financial planning in for financial management of an organisation.
3.2 Explain the calculation of unit costs and make pricing decisions
using relevant information
The cost per unit is commonly derived when a company produces a large number of
identical products. The cost is derived from the variable costs and fixed costs incurred
by a production process, divided by the number of units produced.
The cost per unit calculation is:
(Total fixed costs + Total variable costs) / Total units produced
The cost per unit should decline as the number of units produced increases, primarily
because the total fixed costs will be spread over a larger number of units
Pricing Decision:
- Pricing Decision is an analysis process to take your product price, it is the basic
condition for your company can entry and dominate the market.
- There are 3 major influences on pricing decisions:
sizes to build steel rolling furnace, cement metallurgy, glass furnace, ... replace
imported bricks (mainly from China)
Technique information:
- Planned factory capacity: 2200 tons/year
- Maximum capacity: 2500 tons/year
- Total Cost: 14,394,000,000 vnd
Facility Set-Up
No.
1
Names
Cost
1,860,000,000
Masher
Electric facilities
Computers
Shape machine
Machine
Forklift
10
25 tons Furnace
600,000,000
114,000,000
111,000,000
60,000,000
+
Weighting
363,000,000
3,630,000,000
270,000,000
270,000,000
11
12
195,000,000
645,000,000
Total
8,394,000,000
Facilities Cost
8,394,000,000
6,000,000,000
Total Cost
14,394,000,000
Operation Cost
Variance cost per 1 tons:
Variance Cost per 1 tons
Materials
2,760,000
Direct works
1,044,000
600,000
Othes
450,000
Total
4,854,000
Fixed managing cost: 738.77 millions vnd (for manufacturing 1600 - 2500 tons)
Depreciation period of facilities: 5 years; of factory: 7 years
Income Taxs: 25%
Annual Depreciation:
- Facilitty Depreciation:
= 743,800,000
- Factory Depreciation:
+ Depreciation timee: 7 nm
+ Annual Depreciation (Using Linear method)
D=
= 328,571,429
Year 2
Year 3
Year 4
Year 5
Facilitty Depreciation
1679
1679
1679
1679
1679
Factory Depreciation
857
857
857
857
857
Depreciation Total
2536
2536
2536
2536
2536
1714
Depreciation Overleft
Production:
Power production and consumption is expected to 2200 tons/year in which the first
year is expected to reach 80%, 2nd year 90% projected, 3rd year is expected to reach
100%
Planned Capacity: 2.200 tons/years
We have the table
Year
Year
1
Year
2
Year
3
Year
4
Year
5
Consumption rate
80%
90%
100%
100%
100%
1,760
1,980
2,200
2,200
2,200
Production (tons)
Operation Cost:
a. Fixed Cost:
- Fixed managing cost: 738.440.000 vnd
Cost
Weighted (Mil.
in Sales
Vn)
Portion
18.06
1.40%
200.00
Utilities
0.22%
30.66
Office Supplies
0.08%
10.71
Professional Fees
0.16%
23.10
Tools, materials
0.12%
16.91
Travelling
Equipment
Maintenance
0.09%
12.29
0.18%
25.73
Land Rental
2.76%
393.33
Miscellaneous
0.05%
7.67
Total
5.05%
738.44
&
Vehicle
- Depreciation: 2.536.000.000 vn
Year 1
Year 2
Year 3
Year 4
Year 5
Facilitty Depreciation
1679
1679
1679
1679
1679
Factory Depreciation
857
857
857
857
857
Depreciation Total
2536
2536
2536
2536
2536
Depreciation Overleft
b. Variance Cost:
+ Fixed Cost in 1st Year: 8.543 Millions Vnd
+ Fixed Cost in 2nd Year: 9.611 Millions Vnd
1714
Fixed expenses
Variance expenses
Total Expenses
Year
1
Year
2
Year 3
Year
4
Year
5
3,882
3,882
3,730
3,579
3,427
8,543
9,611
10,679
10,679
10,679
12,425
13,493
14,409
14,258
14,106
Price:
We have the table of production cost per unit of product annually as follows:
Year
1
Production Cost/Unit
Year
2
7.5209 7.2246
Year
3
Year
4
Year
5
6.9876
6.9876
6.9876
From a manufacturer's perspective, the enterprise profit aims is 25%. Therefore the
selling price of the company is:
Year
1
Year
2
Year
3
Year
4
Year
5
Production Cost/Unit
7.52
7.22
6.99
6.99
6.99
9.40
9.03
8.73
8.73
8.73
Names
Alumin Brick (AL2O345-50%) Std. (230 * 114 * 65) H1
Alumin Brick (AL2O345-50%) T72 + rolling pin hangs
Alumin Brick (AL2O345-50%) deformities series 3 kg
Alumin Brick (AL2O345-50%) deformities series 2 kg
Alumin Brick m (AL2O3 45-50%) deformities series 15-30 kg
Alumin Brick (AL2O3 45-50%) deformities series TL 31-44 kg
Alumin Brick (AL2O345-50%) deformities series TL 45 -60 kg
Alumin Brick (AL2O345-50%) deformities series TL 61 kg
Alumin Brick (AL2O351-55%) Std. (230 * 114 * 65) H1
Average
Price
(vnd/ton)
6,149,000
7,370,000
8,338,000
9,020,000
8,690,000
8,690,000
8,965,000
9,790,000
7,183,000
8,187,300
Year
2
Year
3
Year
4
Year 5
Production Cost
7.24
6.97
6.76
6.69
6.62
Planned Price
8.10
8.15
8.15
8.20
8.20
Aim Cost
6.86
6.70
6.56
6.56
Reduce Level
1.59%
2.33%
2.09% 0.00%
Year
1
Year
2
Year
3
Year
4
Year
5
Consumption rate
80%
90%
100%
100%
100%
Consumption (tons)
Price (mil vnd/tons)
Sales
1,760
1,980
2,200
2,200
2,200
8.10
8.15
8.15
8.20
8.20
Income Statement
Year 1
Year 2
Year 3
Year 4
Year 5
Sales
14,256
16,137
17,930
18,040
18,040
Operating expenses
12,425
13,493
14,409
14,258
14,106
EBT
1,831
2,644
3,521
3,782
3,934
458
661
880
946
983
EAT
1,373
1,983
2,641
2,837
2,950
Year 1
Year 2
Year 3
Year 4
Year 5
1,373
1,983
2,641
2,837
2,950
2,536
2,536
2,536
2,536
2,536
Year 0
Factory Building
14,394
Interest expenses
Outflows
14,394
Debt
Cash Flow
activities
by
operating
Debt Capital
Depreciation
Liquidation and Deperciation
Overleft
1,714
Inflows
Net Cash Flow
Debt cash flow
Equity Cash Flow
3,909
4,519
5,177
5,373
7,201
(14,394)
3,909
4,519
5,177
5,373
7,201
(6,000)
606
2,106
1,955
1,803
1,652
(8,394)
3,303
2,413
3,222
3,570
5,549
= 10,1%
- Cost of Equity: capital costs requires taking by investors, at least with ROE of peers:
20%
=> WACC =
= 12,1% *
+
+ 20% *
= 15.87%
b. NPV appraisal:
NPV = -K +
IRR:
IRR is the value of the WACC to value cash flows owners NPV = 0
From the equity cash flow of the project is to identify IRR = ROE = 28.78%
Payback Period:
With a capital cost k = 15.87%, PB is about time that the recovery of capital projects.
Based on the cash flow we project is PB = 4 years 2 months, it was determined that
the payback period is relatively long, but still within the permissible limits
Break even Point:
Year 1
Year 2
Year 3
Year 4
Year 5
Break-even Point
Break-even Point/Capacity
70.00%
1,291
58.70%
1,272
57.81%
1,253
56.95%
1,253
56.95%
1,400
60.00%
1,200
50.00%
1,000
40.00%
800
30.00%
600
20.00%
400
10.00%
200
0.00%
1,272
57.81%
Break-even
Point
Break-even
Point/Capacit
y
Final Conclusion: The project has high feasibility with NPV = 2961.47 billion vnd,