Main Contractor
DFC BACKUP CONTROL ROOM
AL FUTTAIM
TECHN
OLOGIE
S
Document No : AFE/CL/FF-01
Rev.
: 0
Date
: 26-01-2015
FIRE FIGHTING WORKS NOVEC 1230
QUALITY CONTROL CHECK LIST
LOCATION / AREA :
Report No :
Date
:
AFE
Check approved Materials are used for installation.
Check the Installation of the Piping System as per the approved drawings
and Method of Statement
.3
Check the location of the Cylinder as per the approved drawings and
Method of Statement
8
9
Check the Painting of the Piping System.
10
Check that all Warning Signs and Labels are fixed as per requirement.
Others
6
7
11
CONSULTANT / REMARKS
CLIENT
Check the Pressure Testing of the Piping system at 40 psi bar for 10 min.
Check that the Discharge Nozzle Head are installed according to the
approved shop drawings
Check that the Smoke Detectors are installed according to the approved
shop drawings
Check that all Electrical Devises / Control Panel are installed according
to the approved shop drawings
Check adequate Supports are provided in the System
AFT
Comments / Discrepancies (if any)
PLEASE FIND ATTACHED EXTRACTS/REDUCTIONS OF REFERENCE DRAWINGS:
Engineer : _____________________
Note: Works in compliance with ITP, Method Statement, and Drawings & Specifications.