You are on page 1of 7

A methodology to define

transition from open pit to


underground operation
of a mine

The surface ore deposits are extracted using open pit mines until this operation
is economically convenient. When the economical ore begins to deepen the
underground mining becomes more profitable. Then the operation of the
mine goes through a transition from open pit to underground.
Nowadays, this transition is implemented in mines such as Chuquicamata
(Chile), in the future, a larger number of mines will change their exploitation
method from open pit to underground mine.
Historically, the beginning of the transition was decided analysing the
operational costs of open pit and underground mines. Later, this methodology
was improved valuing the block model with differential costs and applying
algorithms for optimizing open pit design. However, both methodologies do
not consider the investments and the value of money over time.
The aim of this paper is to describe, with a comprehensive view, the main
aspects and criteria to be considered in making this transition, and a methodology for defining the economic limit between the two exploitation
methods.
The proposed methodology starts defining the economical boundary of
open pit through marginal analysis of the push-backs or phases of the mine
plan, which includes all the push-backs of the open pit and considering the
underground mine exploitation like another phase.
Once the open pit optimum is defined, we must design the underground
mining method feasible for the ore deposit and its main parameters (in the
case of BC: The level of sinking, the maximum column height and exploitation boundary).
When the economic limit and the period to which the open pit operation
must be reached is defined, you must verify that the start of underground
production matches the term of the open pit production, allowing continuity
of supply to plant. This check should be performed putting together an
implementation plan of the underground mine, which should include all
activities necessary to put in underground mine production.

***

Antonio Navarro, Vctor Encina and


Leonardo Fenner. JRI Ingeniera
S.A ., Chile

INTRODUCTION
The mineralization which outcrops ore deposits close to surface are usually exploited by open pit
(OP) method and its limits are defined by the last phase that provides economically NPV. When
these deposits contain mineralization at depth beyond the economic limit of the pit, the natural
continuation of the exploitation is by underground mining (UG).
The previous situation involves making a transition to move from one open pit mine to an
underground mine. This situation has been presented in significant deposits, and this challenge
must be overcome by currently operating pits.
Historically, the boundary between open pit and underground mining was defined using the rate
of change of methods, which basically compares operating costs of both methods. Later, thanks to
the evolution software, some authors proposed an equivalent calculation valuing block models
with differential costs and applying optimisation algorithms to the pits. Both methods did not
consider the cost or investment of money over time.
The aim of this paper is to describe conceptually the main subject and criteria to be considered for
studying this transition, and to find a methodology to define the economic limit between open pit
mine and underground mine.

METHODOLOGY
The proposed methodology to define the economic limit between both open pit mines and
underground mines is the marginal analysis phase. This analysis is determined by the final limit of
the pit and the underground mining is considered as another phase.
For incorporating underground mining it is necessary to define that the method is feasible for
operating the reservoir and its main parameters (for example for Block Caving it would be
necessary to define the level of collapse, the maximum column height and the operating limits).
The methodology starts determining the total NPV considering the latest economic phases of the
pit, and a preliminary design for the underground mine adopting a height of the column measure
from the bottom of the pit. Subsequently, the calculation of the total NPV is repeated, moving
upstream the floor of the pit and the floor of underground mine maintaining constant increasing
the column height from the floor of the new phase pit.
The calculation is repeated to determine the highest total NPV, which determines the last phase to
exploit as an open pit and the time when the underground mine should be begin to exploit.
Due to the high levels of OP production, the underground mine should be consider massive
method of exploitation as Block Caving or Sub Level Caving. The level of production of these
methods is similar to the open pit mines.
For other different types of mineral deposits, such as ore veins, your analysis of the transition can
be made in a similar way, i.e. seeking higher total VPN the both methods. In these cases, methods
exist different underground exploitation and this methods can be coexistent whit open pit, so that
the underground mine has no restrictions for starting your production when end the open pit
production.

Once the economical limit is determined, the underground mine master plan should be verify to
ensure that the production of the underground mine begin with the end of the open pit exploitation
(see Figure 4). This check should be done considering an underground mine plan, which include
all the activities necessary for the development of the underground mine production.
The plan should also consider the detailed mining ramp up of underground mine production, and
the gradual decline in the production of the pit to ensure the continuity of mineral supply to the
plant.
Finally, the operational interference between construction of the underground mine and the open
pit operation should be review for safety assurance.
According to the methodology proposed to carry out the transition from an open pit (OP) to an
underground operation (UG), should be perform the following planning activities:

Marginal analysis phase OP


This analysis provides the economical limit of the open pit operation determining the NPV of each
phase and the depth of the exploitable pit. This analysis allows obtain the last period of
exploitation, which in turn determines the period that underground mining will start production.
In Figure 1, below shows an example of marginal analysis phase.

Figure 1 NPV Open Pit mining


Figure 1 shows a decrease of NPV at phase N. Then, the end of the open pit should be the phase N1.

Preliminary design of underground mining


The project should include an underground mining ore zone considered in the final stages of open
pit, and an underground mine to compete with. In this area, if the method is the Block Caving, mine
design should be consider:
The level of the bottom of the first undercut is defined based on a global analysis study of the
underground mine.
The maximum column height is defined by the bottom of the final pit and by the first undercut
level.
A production plan considering the production rate of OP should be develop to estimate the
capacity of the process plant.
The plan of underground mine construction including the access, the ventilation levels, the
haulage levels, and infrastructure for services should be developed.
The capital expenditures (CAPEX) and operating expense (OPEX) and NPV of underground
mines should be calculated.
And the Total NPV of open pit and underground mine should be calculated.
In Figure 2, it is shown schematically the column heights of underground mine for the different
final phase of the OP.

Figure 2 Preliminary design of underground mine level

Determination of economic limit and time of transition


The NPV Total (OP + UG) is calculated considering different column heights changing the final
phase of the open pit. From this calculation is obtained a maximum value of NPV. For example, in
Figure 3 it is shown that the highest Total NPV is obtained for the Phase N-2 of the OP. Then, this
phase is defined as the economic limit for the open pit operation. At this time the underground
mine should be operating.

Figure 3 NPV Open Pit + Underground mining

Project Execution Plan


This plan should be consider all activities and milestones for assure that underground mine
production begins with the ending open pit production. This plan includes the following:
Project Description.
Strategy Execution: Awards, Pre-feasibility, Feasibility, DIA, Early Works, Contracts
Strategy.
Major Projects in Execution.
Organisation for implementation phase.
Master Plan. The helpfulness of this plan consists of verifying the feasibility of coincidence of
the end of open pit production with the beginning of underground mine production. The
Figure 4 shows a general master plan.

Figure 4 Underground Mine Master Plan

In the case that some milestone delays, it is possible to develop Fast Track Pans to reduce losses of
NPV due to send less minerals to process plant with less, or to process mineral with lower grades or
higher costs of exploitation.

Mine Planning
A detailed Mine Planning should be develop considering the time up to production rate (ramp
up) for the underground mine and the time during the decrease of the production at the ended of
the open pit. This program allows identifying any difficulties arising in this period.

RESULTS AND DISCUSSION


The methodology presented has made some assumptions that can be reviewed or changed
according to the particular case being studied:
In estimating the production plan of the UG, it can be assumed that the reserves that are
competing with the pit are mined in the same period as this.

For this production plan, in addition, these reserves could be affected by dilution, such as in the
case study.
The first panel of the UG was defined with a fixed transport layer and a column height that
varied, but this may be limited to a maximum, forcing to vary the height of the transport layer.
After the economic limit and the transition period, it is recommended to make a detailed plan
with the Ramp up the UG and the end of production of the OP. This ramp-up period should be
maintained at full capacity in the plant feed.

CONCLUSION
Depending on the complexity of the operations facing the transition, it may be advisable to treat it
as a special project whose target is to:
Ensure that the production in this period will generate alternative or contingency plans.
Coordinate the closing of the OP and the opening of the UG, generating the conversion plans of
staff, infrastructure and other disarmament.
Study and resolve potential interference.
Update the determination of economic threshold for transition and implementation plans of the
UG in its engineering stages.

REFERENCES
Pea, J.C. (2003) Transicin Minera Rajo Abierto a Minera Subterrnea, XIII Simposium de Ingeniera de Mina.
Andrs A. Solar D., Enrique Rubio E. & Alexandra Newman (2010) Transicin rajo subterrnea, una
oportunidad en el valor a largo plazo, Taller de planificacin minera Delphos 2010, Universidad de
Chile.

You might also like