Professional Documents
Culture Documents
Points To Be Raised by SCEPP at The ACTLG On 20 January 2010
Points To Be Raised by SCEPP at The ACTLG On 20 January 2010
3. Contractual Arrangements
3.1. We understand that under the contractual arrangement between EMDA and VSD,
the principal consideration is the timely completion of the work. Whilst recognising
the importance of timely completion, we are concerned that this arrangement will
encourage short cuts at the expense of safety. Delays in the remediation work are,
we believe, inevitable and we would expect to see a provision for this is in the
contract. What are the exceptional weather and environmental conditions set out in
the contract that will allow the contractor to apply for an extension, or that would
trigger an otherwise acceptable delay in the work?