You are on page 1of 2

6952 Federal Register / Vol. 73, No.

25 / Wednesday, February 6, 2008 / Notices

Docket Numbers: RP08–178–000. be taken, but will not serve to make generator interconnection provisions of
Applicants: Southern Natural Gas protestants parties to the proceeding. its tariff.
Company. Anyone filing a motion to intervene or Any person desiring to intervene or to
Description: Southern Natural Gas Co. protest must serve a copy of that protest this filing must file in
submits Eleventh Revised Sheet 26 et al document on the Applicant. In reference accordance with Rules 211 and 214 of
to FERC Gas Tariff, Seventh Revised to filings initiating a new proceeding, the Commission’s Rules of Practice and
Volume 1, to become effective 3/1/08. interventions or protests submitted on Procedure (18 CFR 385.211, 385.214).
Filed Date: 01/30/2008. or before the comment deadline need Protests will be considered by the
Accession Number: 20080131–0194. not be served on persons other than the Commission in determining the
Comment Date: 5 p.m. Eastern Time Applicant. appropriate action to be taken, but will
on Monday, February 11, 2008. The Commission encourages not serve to make protestants parties to
Docket Numbers: RP08–179–000. electronic submission of protests and the proceeding. Any person wishing to
Applicants: Young Gas Storage interventions in lieu of paper, using the become a party must file a notice of
Company, Ltd. FERC Online links at http:// intervention or motion to intervene, as
Description: Young Gas Storage Co., www.ferc.gov. To facilitate electronic appropriate. The Respondent’s answer
Ltd submits Eighth Revised Sheet 11 et service, persons with Internet access and all interventions, or protests must
al. to FERC Gas Tariff, Original Volume who will eFile a document and/or be be filed on or before the comment date.
1, to become effective 3/1/08. listed as a contact for an intervenor The Respondent’s answer, motions to
Filed Date: 01/30/2008. must create and validate an intervene, and protests must be served
Accession Number: 20080131–0193. eRegistration account using the on the Complainants.
Comment Date: 5 p.m. Eastern Time eRegistration link. Select the eFiling The Commission encourages
on Monday, February 11, 2008. link to log on and submit the electronic submission of answers,
Docket Numbers: RP08–180–000. intervention or protests. protests and interventions in lieu of
Applicants: Southern Natural Gas Persons unable to file electronically paper using the ‘‘eFiling’’ link at
Company. should submit an original and 14 copies http://www.ferc.gov. Persons unable to
Description: Southern Natural Gas Co. of the intervention or protest to the file electronically should submit an
submits Tenth Revised Sheet 26 et al. to Federal Energy Regulatory Commission, original and 14 copies of the protest or
FERC Gas Tariff, Seventh Revised 888 First St. NE., Washington, DC intervention to the Federal Energy
Volume 1, to become effective 3/1/08. 20426. Regulatory Commission, 888 First
Filed Date: 01/30/2008. The filings in the above proceedings Street, NE., Washington, DC 20426.
Accession Number: 20080131–0192. are accessible in the Commission’s This filing is accessible on-line at
Comment Date: 5 p.m. Eastern Time eLibrary system by clicking on the http://www.ferc.gov, using the
on Monday, February 11, 2008. appropriate link in the above list. They ‘‘eLibrary’’ link and is available for
Docket Numbers: RP08–181–000. are also available for review in the review in the Commission’s Public
Applicants: Southern LNG Inc. Commission’s Public Reference Room in Reference Room in Washington, DC.
Description: Southern LNG Inc Washington, DC. There is an There is an ‘‘eSubscription’’ link on the
submits Twentieth Revised Sheet 5 et al. eSubscription link on the Web site that Web site that enables subscribers to
to FERC Gas Tariff, Original Volume 1, enables subscribers to receive e-mail receive e-mail notification when a
to become effective 3/1/08. notification when a document is added document is added to a subscribed
Filed Date: 01/30/2008. to a subscribed dockets(s). For docket(s). For assistance with any FERC
Accession Number: 20080131–0191. assistance with any FERC Online Online service, please e-mail
Comment Date: 5 p.m. Eastern Time service, please e-mail FERCOnlineSupport@ferc.gov, or call
on Monday, February 11, 2008. FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call
Docket Numbers: RP08–182–000. (866) 208–3676 (toll free). For TTY, call (202) 502–8659.
Applicants: Williston Basin Interstate (202) 502–8659. Comment Date: 5 p.m. Eastern Time on
Pipeline Co. Nathaniel J. Davis, Sr., February 11, 2008.
Description: Williston Basin Interstate Deputy Secretary. Kimberly D. Bose,
Pipeline Company submits Third
[FR Doc. E8–2135 Filed 2–5–08; 8:45 am] Secretary.
Revised Sheet 202 et al. to FERC Gas
Tariff, Second Revised Volume 1, to BILLING CODE 6717–01–P [FR Doc. E8–2115 Filed 2–5–08; 8:45 am]
become effective 3/2/08. BILLING CODE 6717–01–P

Filed Date: 01/31/2008. DEPARTMENT OF ENERGY


Accession Number: 20080201–0102.
Comment Date: 5 p.m. Eastern Time DEPARTMENT OF ENERGY
Federal Energy Regulatory
on Tuesday, February 12, 2008. Commission Federal Energy Regulatory
Any person desiring to intervene or to Commission
[Docket No. EL08–36–000]
protest in any of the above proceedings
must file in accordance with Rules 211 Dominion Resources Services, Inc. Notice of Effectiveness of Exempt
and 214 of the Commission’s Rules of Complainant, v. PJM Interconnection, Wholesale Generator or Foreign Utility
Practice and Procedure (18 CFR 385.211 LLC Respondent; Notice of Complaint, Company Status
and 385.214) on or before 5 p.m. Eastern Request for Fast Track Processing
time on the specified comment date. It January 29, 2008.
is not necessary to separately intervene January 30, 2008.
pwalker on PROD1PC71 with NOTICES

Docket Nos.
again in a subdocket related to a Take notice that on January 28, 2008,
compliance filing if you have previously Dominion Resources Services, Inc. filed Reliant Energy Mandalay, Inc EG08–1–000
intervened in the same docket. Protests a complaint under section 206 of the Arlington Wind Power Project EG08–2–000
will be considered by the Commission Federal Power Act alleging that the PJM LLC.
in determining the appropriate action to Interconnection, LLC is violating the Forked River Power LLC ....... EG08–3–000

VerDate Aug<31>2005 18:21 Feb 05, 2008 Jkt 214001 PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 E:\FR\FM\06FEN1.SGM 06FEN1
Federal Register / Vol. 73, No. 25 / Wednesday, February 6, 2008 / Notices 6953

Docket Nos. D. Bose, Secretary, Federal Energy elevation of approximately 4,254 feet
Regulatory Commission, 888 First ASL. Currently, water entering Lake
FPL Energy Oliver Wind II, EG08–4–000 Street, NE., Washington, DC 20426. Abert remains in Lake Abert until it
LCC. Comments, protests and interventions evaporates, i.e. Lake Abert occurs
Marble River, LLC .................. EG08–5–000 may be filed electronically via the within a closed topographic basin with
Santa Rosa Energy Center, EG08–6–000 Internet in lieu of paper; see 18 CFR no outlets. Lake Abert has an
LLC.
385.2001(a)(1)(iii) and the instructions approximate storage capacity of 400,000
Long Beach Peakers LLC ...... EG08–7–000
Plum Point Energy Associ- EG08–8–000 on the Commission’s Web site under the acre-feet.
ates, L.L.C. ‘‘e-Filing’’ link. The Commission A new 45-mile-long 128-kV
Wharton County Generation, EG08–9–000 strongly encourages electronic filings. transmission line will be constructed to
LLC. Please include the project number (P– interconnect the proposed project with
Macquarie Bank Limited ........ FC08–1–000 13054–000) on any comments or an existing Bonneville Power
motions filed. Administration 500-kV, AC
Take notice that during the month of The Commission’s Rules of Practice transmission line located northwest of
December 2007, the status of the above- and Procedure require all intervenors Lake Abert. This interconnection will
captioned entities as Exempt Wholesale filing documents with the Commission link the proposed project with the both
Generators or Foreign Utility Companies to serve a copy of that document on the California-Nevada and Pacific
became effective by operation of the each person in the official service list Northwest power grids. A new
Commission’s regulations. 18 CFR for the project. Further, if an intervenor substation would be constructed at the
366.7(a). files comments or documents with the point of interconnection. The proposed
Commission relating to the merits of an project would have an annual
Kimberly D. Bose, issue that may affect the responsibilities generation of 489.1 GWh.
Secretary. of a particular resource agency, they k. Location of Applications: A copy of
[FR Doc. E8–2109 Filed 2–5–08; 8:45 am] must also serve a copy of the document the application is available for
BILLING CODE 6717–01–P on that resource agency. inspection and reproduction at the
j. Description of Existing Facilities Commission in the Public Reference
and Proposed Project: The proposed Room or may be viewed on the
DEPARTMENT OF ENERGY Abert Rim Pumped Storage Project will Commission’s Web site at http://
consist of the existing Mule Lake, which www.ferc.gov using the ‘‘eLibrary’’ link.
Federal Energy Regulatory is an existing small lake, and Lake Enter the docket number excluding the
Commission Abert, which is an existing alkali lake. last three digits in the docket number
[Project No. 13054–000] Both water bodies are located on BLM field to access the document. For
lands. Under the proposed project, Mule assistance, call toll-free 1–866–208–
Nt Hydro; Notice of Application Lake Reservoir and Lake Abert will be 3676 or e-mail
Accepted for Filing and Soliciting connected by a 6,200 foot-long pipeline FERCOnlineSupport@ferc.gov. For TTY,
Comments, Protests, and Motions To consisting of two eight-foot-diameter call (202) 502–8659. A copy is also
Intervene steel pipes with a hydraulic capacity of available for inspection and
approximately 700 cubic feet per second reproduction at the address in item g
January 30, 2008. (cfs) each. The pipeline will include a above.
Take notice that the following 6,200-foot-long tunnel immediately l. Individuals desiring to be included
hydroelectric application has been filed below Abert Rim Wilderness Study on the Commission’s mailing list should
with the Commission and is available Area. A powerhouse/pumphouse will be so indicate by writing to the Secretary
for public inspection: located near the shore of Lake Abert, of the Commission.
a. Type of Application: Preliminary containing two 67 megawatt (MW)/700 m. Competing Preliminary Permit—
Permit. cfs pump-turbines, and appurtenant Anyone desiring to file a competing
b. Project No.: 13054–000. facilities. The powerhouse/pumphouse application for preliminary permit for a
c. Date filed: October 22, 2007. would be a metal building with a proposed project must submit the
d. Applicant: NT Hydro. concrete foundation, approximately competing application itself, or a notice
e. Name and Location of Project: The 120-foot-wide by 60-foot-long and 30- of intent to file such an application, to
proposed Abert Rim Pumped Storage foot-high. the Commission on or before the
Hydroelectric Project would be located Mule Lake, which stores runoff from specified comment date for the
in Lake County, Oregon and would intermittent streams, has a normal particular application (see 18 CFR 4.36).
utilize the existing Mule Lake and Lake maximum water surface elevation of Submission of a timely notice of intent
Albert, both located on U.S. Bureau of approximately 5,605 feet above sea level allows an interested person to file the
Land Management (BLM) land. (ASL). USGS topographic data indicate competing preliminary permit
f. Filed Pursuant to: Federal Power that Mule Lake occurs within a closed application no later than 30 days after
Act, 16 U.S.C. 791(a)–825(r). basin, with no outlet streams. Currently, the specified comment date for the
g. Applicant contact: Mr. Ted Mule Lake has an approximate storage particular application. A competing
Sorenson, Sorenson Engineering, 5203 capacity of 1,600 acre-feet. Under the preliminary permit application must
South 11th, East Idaho Falls, ID 83404, proposed project, storage in Mule Lake conform with 18 CFR 4.30(b) and 4.36.
(208) 522–8069. would be increased to about 4,000 acre- n. Competing Development
h. FERC Contact: Tom Papsidero, feet by increasing the lake level 20 feet. Application—Any qualified
(202) 502–6002. Because Mule Lake is in a closed basin, development applicant desiring to file a
i. Deadline for filing comments, no new dam would be required to competing development application
pwalker on PROD1PC71 with NOTICES

protests, and motions to intervene: 60 increase the lake level and storage. Lake must submit to the Commission, on or
days from the issuance date of this Abert, which receives water from before a specified comment date for the
notice. Chewaucan River, various springs and particular application, either a
All documents (original and eight intermittent runoff streams, has a competing development application or a
copies) should be filed with: Kimberly normal maximum water surface notice of intent to file such an

VerDate Aug<31>2005 18:21 Feb 05, 2008 Jkt 214001 PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 E:\FR\FM\06FEN1.SGM 06FEN1