Professional Documents
Culture Documents
1. Efficiency:
2. Utilizaton:
3. Example:
Design capacity = 50 trucks/day
Effective capacity = 40 trucks/day
Actual output = 36 units/day
Get the Efficiency & Utilization?
Sol.
Example:
A coffee shop makes 150 coffees per hour. How efficent is the
operation as labor input produces 200 coffees per hour?
Example:
If productivity increased from 80 to 84, what is the productivity growth rate?
Sol.
Example:
Determine the productivity for the following case:
a) Four workers installed 720 square yards of carpeting in eight hours
b) A machine produced 68 usable pieces in two hours
Sol.
Example:
A company that processes fruits and vegetables is able to produce 400 cases
of canned peaches in one-half hour with four workers.
What is labor productivity?
Sol.
time-series models:
1. Naive Approach:
Example :
Example:
4. Exponential Smoothing:
Example:
Predicted demand (t-1) = 131
Actual demand (t-1) = 142
Smoothing constant = .25
Sol.
New forecast (t) = 131 + 0.25(142 131)
Example:
Predicted demand = 142 Ford Mustangs
Actual demand = 153
Smoothing constant = .20
Sol.
New forecast= 142 + .2(153 - 142)
= 142 + 2.2
= 144.2 ~ 144 cars
Example:
If the department works one eight hour shift, 250 days a year, calculate
the number of machines that would be needed to handle the required
volume.
Sol.
5800/(250)(8) = 2.9 (3 machines are needed)
Cost-volume Relatonshps
EOQ:
Where
Q = quantity to be ordered
H= holding cost per unit (carrying cost per unit)
D = annual demand
S = ordering (setup cost) per order
Example
A local distributor for a national tire company expects to sell approximately
9600 steel-belted radial tires of a certain size and tread design next year.
Annual carrying cost is $16 per tire, and ordering cost is $75. the distributor
operates 288 days a year.
What is the EOQ?
How many times per year does the store reorder?
What is the length of an order cycle?
What is the total annual cost if the EOQ is ordered?
Sol.
D = 9600 tires per year
H = $16 per unit per year
S = $75 per order
Where:
P = production or delivery rate
U = usage rate
The minimum total cost is determined as follows:
Example
A toy manufacturer uses 48000 rubber wheels per year for its popular dump
truck series. The firm makes its own wheels, which it can produce at rate of
800 per day. The toy trucks are assembled uniformly over the entire year.
Carrying cost is $1 per wheel a year. Setup cost for a production run of
wheels is $45. the firm operates 240 days per year.
Determine the
a.Optimal run size
Path:
Sequence of activities that leads from the starting node to the finishing node
Critical path
The longest path; determines expected project duration
Critical activities
Activities on the critical path
Slack
Allowable slippage for path; the difference the length of path and the length
of critical path
Network Conventions:
Time Estimates
a) Deterministic
Time estimates that are fairly certain
b) Probabilistic
Estimates of times that allow for variation
d) Expected Time