Federal Register / Vol. 71, No.

158 / Wednesday, August 16, 2006 / Notices 47201

agency, Indian Tribe, or person must file p. With this notice, we are initiating Vedula Sarma at (202) 502–6190 or
a request for a study with the consultation with the Montana State vedula.sarma@ferc.gov.
Commission not later than 60 days from Historic Preservation Officer (SHPO), as j. Deadline for filing comments and/
the date of filing of the application, and required by § 106, National Historic or motions: September 8, 2006.
serve a copy of the request on the Preservation Act, and the regulations of k. Description of Filing: TransCanada
applicant. the Advisory Council on Historic Northeast, Inc. proposes to replace
l. Deadline for filing additional study Preservation, 36 CFR, at § 800.4. turbine runners at the Comerford
requests and requests for cooperating q. Procedural schedule: The Development of the project. The project
agency status: October 2, 2006. application will be processed according consists of three developments: the
All documents (original and eight to the following Hydro Licensing Moore, Comerford and McIndoes
copies) should be filed with: Magalie R. Schedule. Revisions to the schedule will developments with a current authorized
Salas, Secretary, Federal Energy be made as appropriate. installed capacity of 291,360 kilowatts
Regulatory Commission, 888 First Issue Deficiency Letter: September (kW) and total hydraulic capacity of
Street, NE., Washington, DC 20426. 2006. 37,400 cfs. The licensee proposes to
Additional study requests and Issue Acceptance Letter: December replace existing four turbine runners of
requests for cooperating agency status 2006. the Comerford Development in two
may be filed electronically via the Issue Scoping Document 1 for phases. Phase 1 involves immediate
Internet in lieu of paper. The comments: January 2007. replacement of turbine runner of Unit 1,
Commission strongly encourages Request Additional Information: and in phase 2 the turbine runners of
electronic filings. See 18 CFR March 2007. the remaining three units would be
385.2001(a)(1)(iii) and the instructions Issue Scoping Document 2: April replaced over a period of four years. The
on the Commission’s Web site (http:// 2007. proposed changes would increase the
www.ferc.gov) under the ‘‘e-Filing’’ link. Notice of application is ready for project’s total installed capacity by
m. The application is not ready for environmental analysis: April 2007. 28,600 kW and the hydraulic capacity
environmental analysis at this time. Notice of the availability of the EA: would be reduced from 37,400 cfs to
n. The proposed project would utilize October 2007. 37,235 cfs.
the existing Bureau of Reclamation’s Ready for Commission’s decision on l. Locations of Applications: A copy of
Clark Canyon dam, and would consist of the application: January 2008. the application is available for
the following new facilities: (1) A steel inspection and reproduction at the
liner in the existing 9-foot-diameter Magalie R. Salas, Commission in the Public Reference
concrete outlet conduit; (2) a new outlet Secretary. Room, located at 888 First Street, NE.,
gate structure; (3) a 9-foot-diameter steel [FR Doc. E6–13364 Filed 8–15–06; 8:45 am] Room 2A, Washington, DC 20426, or by
penstock bifurcating into an 8-foot BILLING CODE 6717–01–P calling (202) 502–8371. This filing may
diameter and a 6-foot diameter steel also be viewed on the Commission’s
penstock directing flow to the turbine Web site at http://www.ferc.gov using
units about 70 feet from the bifurcation; DEPARTMENT OF ENERGY the ‘‘eLibrary’’ link. Enter the docket
(4) a powerhouse containing two number excluding the last three digits in
generating units with a combined Federal Energy Regulatory the docket number field to access the
capacity of 4.75 megawatts; (5) a 300- Commission document. You may also register online
foot-long access road; (6) a switchyard; at http://www.ferc.gov/docs-filing/
Notice of Application for Amendment
(7) about 0.1 mile of transmission line esubscription.asp to be notified via e-
of License and Soliciting Comments,
connecting the project to the local mail of new filings and issuances
Motions To Intervene, and Protests
utility’s transmission system; and (8) related to this or other pending projects.
about 11 miles of existing transmission August 8, 2006. For assistance, call toll-free 1–866–208–
line that would be upgraded. The Take notice that the following 3676 or e-mail
average annual generation is estimated hydroelectric application has been filed FERCOnlineSupport@ferc.gov. For TTY,
to be 16.5 gigawatthours. with the Commission and is available call (202) 502–8659. A copy is also
o. A copy of the application is for public inspection: available for inspection and
available for review at the Commission a. Application Type: Amendment of reproduction at the address in item (h)
in the Public Reference Room or may be license to upgrade the installed above.
viewed on the Commission’s Web site at capacity. m. Individuals desiring to be included
http://www.ferc.gov using the b. Project No: 2077–055. on the Commission’s mailing list should
‘‘eLibrary’’ link. Enter the docket c. Date Filed: June 27, 2006. so indicate by writing to the Secretary
number excluding the last three digits in d. Applicant: TransCanada Hydro of the Commission.
the docket number field to access the Northeast, Inc. n. Comments, Protests, or Motions to
document. For assistance, contact FERC e. Name of Project: Fifteen Mile Falls. Intervene: Anyone may submit
Online Support at f. Location: The project is located on comments, a protest, or a motion to
FERCOnlineSupport@ferc.gov or toll- the Connecticut River near the Town of intervene in accordance with the
free at 1–866–208–3676, or for TTY, Littleton, Grafton County, New requirements of Rules of Practice and
(202) 502–8659. A copy is also available Hampshire, and Caledonia County, Procedure, 18 CFR 385.210, .211, .214.
for inspection and reproduction at the Vermont. In determining the appropriate action to
address in item h above. g. Filed Pursuant to: Federal Power take, the Commission will consider all
You may also register online at Act, 16 U.S.C. 791a–825r. protests or other comments filed, but
http://www.ferc.gov/docs-filing/ h. Applicant Contact: Mr. John only those who file a motion to
jlentini on PROD1PC65 with NOTICES

esubscription.asp to be notified via Ragonese, TransCanada Northeast, Inc., intervene in accordance with the
e-mail of new filings and issuances 4 Park Street, Suite 402, Concord, NH Commission’s Rules may become a
related to this or other pending projects. 03301–3260. Tel: (603) 225–3260. party to the proceeding. Any comments,
For assistance, contact FERC Online i. FERC Contact: Any questions on protests, or motions to intervene must
Support. this notice should be addressed to be received on or before the specified

VerDate Aug<31>2005 20:24 Aug 15, 2006 Jkt 208001 PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 E:\FR\FM\16AUN1.SGM 16AUN1
47202 Federal Register / Vol. 71, No. 158 / Wednesday, August 16, 2006 / Notices

comment date for the particular an irrigation district owned by Eagle the ‘‘eLibrary’’ link. Enter the docket
application. Point Irrigation District. number excluding the last three digits in
o. Filing and Service of Responsive g. Filed Pursuant to: Federal Power the docket number field to access the
Documents: Any filings must bear in all Act, 16 U.S.C. 791(a)–825(r). document. For assistance, call toll-free
capital letters the title ‘‘COMMENTS’’, h. Applicant Contact: Mr. Richard 1–866–208–3676 or e-mail
‘‘RECOMMENDATIONS FOR TERMS Enloe, Enloe & Associates, Inc., 2350 FERCOnlineSupport@ferc.gov. For TTY,
AND CONDITIONS’’, ‘‘PROTEST’’, OR Ave. G, White City, OR 97503, (541) call (202) 502–8659. A copy is also
‘‘MOTION TO INTERVENE’’, as 826–9422, Ext. 1016, E-mail available for inspection and
applicable, and the Project Number of enloe2@earthlink.net. reproduction at the address in item h
the particular application to which the i. FERC Contact: Patricia W. Gillis at above.
filing refers. All documents (original (202) 502–8735. m. Individuals desiring to be included
and eight copies) should be filed with: j. Deadline for filing comments, on the Commission’s mailing list should
Magalie R. Salas, Secretary, Federal protests, and motions to intervene: 60 so indicate by writing to the Secretary
Energy Regulatory Commission, 888 days from the issuance date of this of the Commission.
First Street, NE., Washington, DC 20426. notice. n. Competing Preliminary Permit:
A copy of any motion to intervene must The Commission’s Rules of Practice Anyone desiring to file a competing
also be served upon each representative and Procedure require all intervenors application for preliminary permit for a
of the Applicant specified in the filing documents with the Commission proposed project must submit the
particular application. to serve a copy of that document on competing application itself, or a notice
p. Agency Comments: Federal, state, each person in the official service list of intent to file such an application, to
and local agencies are invited to file for the project. Further, if an intervenor the Commission on or before the
comments on the described application. files comments or documents with the specified comment date for the
A copy of the application may be Commission relating to the merits of an particular application (see 18 CFR 4.36).
obtained by agencies directly from the issue that may affect the responsibilities Submission of a timely notice of intent
Applicant. If an agency does not file of a particular resource agency, they allows an interested person to file the
must also serve a copy of the document competing preliminary permit
comments within the time specified for
on that resource agency. application no later than 30 days after
filing comments, it will be presumed to
k. Description of Project: The the specified comment date for the
have no comments. One copy of an
proposed project would consist of the particular application. A competing
agency’s comments must also be sent to
following two developments: preliminary permit application must
the Applicant’s representatives.
conform with 18 CFR 4.30(b) and 4.36.
q. Comments, protests and The Lower Development o. Competing Development
interventions may be filed electronically (1) An existing channel, (2) a Application: Any qualified development
via the Internet in lieu of paper. See 18 proposed intake structure, (3) a applicant desiring to file a competing
CFR 385.2001(a)(1)(iii) and the proposed underground 4,300-foot-long, development application must submit to
instructions on the Commission’s Web 48-inch-diameter steel penstock, (4) a the Commission, on or before a
site at http://www.ferc.gov under the ‘‘e- proposed powerhouse containing one specified comment date for the
Filing’’ link. generating unit with an installed particular application, either a
Magalie R. Salas, capacity of 600-kilowatts, (5) a proposed competing development application or a
Secretary. 4,500-foot-long, 12.47 kilovolt notice of intent to file such an
[FR Doc. E6–13365 Filed 8–15–06; 8:45 am] transmission line, and (6) appurtenant application. Submission of a timely
facilities. The proposed project would notice of intent to file a development
BILLING CODE 6717–01–P
have an average annual generation of application allows an interested person
2,623 gigawatt-hours, which would be to file the competing application no
DEPARTMENT OF ENERGY sold to a local utility. later than 120 days after the specified
comment date for the particular
The Upper Development application. A competing license
Federal Energy Regulatory
Commission (1) An existing channel, (2) a application must conform with 18 CFR
proposed intake structure, (3) a 4.30(b) and 4.36.
Notice of Application Accepted for proposed underground 1,450-foot-long p. Notice of Intent: A notice of intent
Filing and Soliciting Motions To 36-inch-diameter steel penstock, (4) a must specify the exact name, business
Intervene, Protests, and Comments proposed powerhouse containing one address, and telephone number of the
generating unit with an installed prospective applicant, and must include
August 9, 2006. capacity of 400-kilowatts, (5) a proposed an unequivocal statement of intent to
Take notice that the following 1,450-foot-long 12.47 kilowatt submit, if such an application may be
hydroelectric application has been filed transmission line, and appurtenant filed, either a preliminary permit
with the Commission and is available facilities. The proposed project would application or a development
for public inspection: have an average annual generation of application (specify which type of
a. Type of Application: Preliminary 1,352 gigawatt-hours, which would be application). A notice of intent must be
Permit. sold to a local utility. served on the applicant(s) named in this
b. Project No.: 12700–000. l. Locations of Applications: A copy of public notice.
c. Date filed: June 8, 2006. the application is available for q. Proposed Scope of Studies under
d. Applicant: Georges C. St Laurent, inspection and reproduction at the Permit: A preliminary permit, if issued,
Jr. Commission in the Public Reference does not authorize construction. The
jlentini on PROD1PC65 with NOTICES

e. Name of Project: St Laurent Land Room, located at 888 First Street NE., term of the proposed preliminary permit
and Cattle Company. Room 2A, Washington, DC 20426, or by would be 36 months. The work
f. Location: On a 1500 acre private calling (202) 502–8371. This filing may proposed under the preliminary permit
ranch in Jackson County, Oregon. The also be viewed on the Commission’s would include economic analysis,
water is from the Nichols Gap Creek and Web site at http://www.ferc.gov using preparation of preliminary engineering

VerDate Aug<31>2005 20:24 Aug 15, 2006 Jkt 208001 PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 E:\FR\FM\16AUN1.SGM 16AUN1