Professional Documents
Culture Documents
Windows Period Nielsen
Windows Period Nielsen
Introduction
Components
Quantification
- Windows
Causation
- Issues that Caused Impact to Project Execution
Responsibility
- Determination of Parties Responsible
Damages
- Allows for the Quantification of Damages, typically
Extended Site Office Overhead and Unabsorbed
Home Office Overhead
Page 3
Page 4
Window Analysis
Developed In-House
Contemporaneous
Applies No Hindsight
Critical Path Driven
Uses Schedules As-Is
Objective only Uses Facts
Avoids Manipulation
Dynamic Consistent with CPM Scheduling
Page 5
Page 6
Page 7
Eight steps:
1.
2.
3.
4.
5.
6.
7.
8.
Project familiarisation
Initial and revised schedule reasonableness
Identify critical paths
Determine window time periods
Confirm actual dates for critical activities
Perform delay calculations for each window
Tally calculated delay for all windows
Validate results [iterative process]
Page 8
Number of Activities
Number of Relationships
Activity Sequencing
Timing of Events
Use of Constraints
Resource Loading
Claim Digger
Page 11
Page 12
Activity
ID
Activity
Description
SEP
OCT
1999
NOV
DEC
JAN
2000
MAR
FEB
APR
MAY
JUN
BA450
AS201
BA480
AS202
BA411
BA421
Data Date
AS213
Revision
issued here
(Change in
critical path)
BA412
BA407
BA422
BA413
BA550
AS214
BA423
BA600
Deliver Brick
BA408
AS215
BA409
BA620
CS400
CS410
CS420
Award Contract
CS450
Window Timeframe
Award Contract
Fabricate and Deliver Conveyors
Vendor
AS206
Sheet 2 of 7
Page 13
Window
Analysis
Garbage In
=
Garbage Out
Page 14
Start Gain
Start Delay
Production Gain
Production Delay
Page 15
DURATION
DEPENDENT
Nielsen-Wurster Asia Pacific
Start Gain
Start Gain
- Dependent upon its predecessor
Start Delay
Start Delay
-
Production Delay/Gain
Delay:
This period of time
is delay to the
project
Gain
Rules
There can only be one unit (day) of delay or
gain for any one unit of time*
If there is an equal amount of delay and gain
on a given day, the effects offset
Gain and delay quantum only applies to critical
activities
Float on near-critical paths must be absorbed
prior to counting delay
*Exceptions are with multiple shifts, rescheduling and change
of scope
Page 19
Concurrency
Page 20
Concurrency
Two Start delays
in the same time
frame = concurrent
delay
Page 21
Page 22
Window Analysis
SIMPLE
EXAMPLE
Page 24
Activity
ID
0005
0010
0020
0030
0040
0050
0060
0070
Start Date
13JAN00
Finish Date
04FEB00
Data Date
13JAN00
Run Date
13JAN00 17:38
ACTIVITY A
ACTIVITY B
ACTIVITY C
ACTIVITY D
ACTIVITY E
ACTIVITY F
PROJECT COMPLE
Early Bar
Date
Progress Bar
Revision
Checked
Approved
Critical Activity
Page 25
Activity
ID
0005
0010
0020
0030
0040
0050
0060
0070
Start Date
13JAN00
Finish Date
04FEB00
Data Date
13JAN00
Run Date
13JAN00 17:38
ACTIVITY A
ACTIVITY B
ACTIVITY C
ACTIVITY D
ACTIVITY E
ACTIVITY F
PROJECT COMPLE
Early Bar
Date
Early Bar
Revision
Checked
Approved
Progress Bar
Critical Activity
Page 26
Activity
ID
0005
0010
0020
0030
xx
ACTIVITY A
x x xx
ACTIVITY B
ACTIVITY C
o o oo
0040
0050
0060
0070
ACTIVITY D
ACTIVITY E
ACTIVITY F
PROJECT COMPLE
xx
- - - - x
13JAN00
Finish Date
04FEB00
Data Date
13JAN00
Run Date
13JAN00 17:38
Early Bar
Date
Early Bar
Revision
Checked
Approved
Progress Bar
Critical Activity
Page 27