You are on page 1of 12

United Engineers ( Singapore ) Pte. Ltd.

257 Jalan Ahmad Ibrahim


Singapore 629147
Tel: +6562660988
Fax: +6562686993

CONTENTS:

1. Scope of works
2. Project organization for Health & Safety Control
3. Health & Safety Risk and Control
4. Access / Egress
5. Lighting
6. Plant & Equipment
7. Personnel Training Certificate
8. Hazardous Materials & Substances
9. Waste Management
10. Special Control Measures
11. Appendixes
Appendixes
Appendix 1: Checklist for Lightning Protection System
Appendix 2: Project Organization for Health & Safety control
Appendix 3: Risk Assessment
Appendix 4: Personnel Training Certificate
Appendix 5: MSDS for UPS Battery

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

1. Scope of Works
I.

Scope of Activities

This scope defines the minimum standards to be adopted when installing


Uninterrupted Power Supply (UPS). The UPS, Batteries, I/O Panel with integrated
PDU and all the internal power / control cabling will be provided and installed.

II.

Site Procedure

Site mobilization shall be done with real time monitoring the conditions & progress of
builder works. Before commencement of the work, carry out examination of the
physical condition of the area. Photographs should be taken where necessary, prior
to commencement and during works.

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

Method Statement
III.

Preparation stage
a. The delivery vehicle will be parked in the loading area; the equipment will be
unpacked removed from vehicle using the tail lift.
b. Verify compliance between type label on reverse side and system ordered.
c. Check input and output voltage.
d. Copy the type label data to label copy below for easy identification of the
system.
e. Use a fork lift or pallet to transport the system to installation site.
f. Open UPS doors and unscrew metal straps mounted on front cover of UPS.
g. The UPS equipment will then be moved into position using scoots and pallet
trucks.
h. The batteries and stand will be moved into the UPS room using pallet trucks

IV.

Installation Stage
UPS
a. All parts are accessible from front or top of UPS.
b. Identify and check against delivery note all batteries, links and cables are
sufficient and correct.
c. Study the installation guide and layout drawings supplied by the
manufacture.
d. Attach incoming and out-going cables to terminals.
e. Always keep AC, DC and communication able separate.
f. Follow the installation guide for power and communication cable entry.

g. Use commercially available approved solderless lugs for the wire size
h.
i.
j.
k.

required for your application. Connect wire to the lug using appropriate tool.
Input, output and DC cables are routed in separate conduits.
Verify all power connections are tight.
Verify all control wire connections are tight.
Verify all power wires connections have proper spacing between exposed

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

surfaces, phase to phase and phase to ground.


l. Verify that all power & control wires are run in individual, separate conduits.
Battery
a. Load new batteries paying particular attention to placement according
to diagram and polarity.
b. Connect positive and negative feeds to the start and finish of the string
c. Connect one of the centre links and note the voltage and polarity
d. The installation of batteries requires battery knowledge and should
only be carried out/supervised by qualified electricians familiar with
batteries. Keep unauthorized personnel away from batteries.
e. Avoid rough treatment and opening of batteries. Released electrolyte is
f.
g.
h.
i.
j.
k.

harmful to skin and eyes, and may be toxic. Refer Annexure:5


During installation, remove watches, rings, and other metal objects.
Use tool with insulated handles.
Wear rubber gloves and boots.
Do not leave tools or metal parts on top of batteries.
Disconnect charging source prior to connecting batteries.
Determine if the battery is inadvertently grounded. If inadvertently
grounded, remove unwanted ground source. Any contact with
grounded batteries may result in electric shocks. The likelihood of
shocks will be reduced if grounds are removed during installation and
maintenance.

m. After installation of UPS, Engineer-in-charge shall check the complete works


and complete the Inspection checklist for UPS installation works. ( See
annex. 1 )
n. Engineer-in-charge shall arrange and request for inspection with the
Owners representative M&E Residential Technical Officer (RTO) using
approved Main con Request for Inspection (RIN) form.
Testing and commissioning

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

a.
b.
c.
d.
e.

Check the power quality of UPS output.


Check whether the harmonics are within the limit
Check the transfer time.
Check the sine wave composition.
Check battery voltage and internal resistance of each cell, including

f.
g.
h.
i.

inter-cell and inter-tier connectors.


Check the temperature of battery.
Check the currents and discharge events.
Check the individual cell voltage.
Check to verify that the UPS systems are performing to manufacturer
specifications.

V.

Preferred Brands
UPS

MGE, Emerson, Socomec, Eaton, Chloride & GE-Lanpro

2. Project organization for Health & Safety Control


(See annex. 2)
3. Health & Safety risks and controls
(Please refer to attach Risk assessment in respect to above scope of works Annex.3)

4. Access / Egress
The person in charge of the work will ensure that he and all operatives under his
supervision are familiar with the correct access and procedures to the place of
work.
The correct access and egress procedure will be adhered to at all times .
5. Lighting
Adequate temporary/task lighting shall be provided if work to be carried at night
or at dark places.

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

6. Plant & Equipment


S/N
1
2
3
4

Description
Hand Tools
Power Tools (if required)
Electrical drill (only for surface installation works)
Diagonal-Cutting Pliers

Unit
1 lot
1 lot
1 lot
1 lot

Wire Stripper/Cutter with Spring

1 lot

Side-Cutting Pliers

1 lot

Shank Screwdriver/Flat screw driver

1 lot

Compression lug crimp tool

1lot

Cable to service bypass panel from system feeder

1lot

10

Cable to UPS input from service bypass panel

1lot

11

Cable to UPS input from external batteries

1lot

12

Necessary conduit for above listed cabling

1lot

13

Knock out set (for conduit)

1 lot

14

P.P.E. Personal Protective Equipment (safety helmet, Boots,


gloves & safety vest )

1 set per worker

*The above machinery & Equipment used quantity will be varied depending on site conditions
and production rate.

7. Personnel Training Certificate


(Annexure 4)
8. Hazardous Materials & Substances
(Refer Annexure: 5)
9. Waste management
The Rubbish which would be created from our scope of works will be disposed to the
designated dumping ground.

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

10. Special Control measures


The following general control measures against Safety, Environment and Quality shall be
required for our scope of work and special control measures are not applicable for us

Proper PPE must be worn at all time

Permit to work at height > 2m where applicable

Lifting operation permit (using crane) where applicable.

Confined space permit where applicable.

Approved work method statement and risk assessment will be made available to site. All
workers doing the work shall be briefed on this method statement and risk
assessment.
11. Appendix

ANNEX 1:

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

Inspection Checklist
UPS
Installation

ANNEX 2:

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

Project Organisation
for Health & Safety
Control

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

ANNEX 3:
Risk Assessment

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

ANNEX 4:
Personnel Training
Certificate

United Engineers ( Singapore ) Pte. Ltd.


257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

ANNEX 5:
MSDS for UPS
Battery

You might also like