SECTION 2e CONCRETE
2e.01 General Requirement
Structural concrete works shall be carried out in accordance with
the Building (Construction) Regulations and the Code of Practice
for the Structural Use of Concrete 2004.
2e.02 Cement
Unless specified otherwise, cement shall be Ordinary Portland
Cement complying with BS12:1996. Other cements shall conform
to the following British Standards:
Sulphate Resisting Portland
Portland Pulverized-fuel Ash
BS 4027:1996
BS 6588:1985
289981923.doc
- S2e/1 -
Dec 2011
General Specification
Section 2e Concrete
Fine aggregate shall be clean sand, free from shells silt, clay, salt
and other impurities. If considered necessary by the Engineer,
the sand shall be rewashed at the Contractor's expense. Subject
to satisfactory grading tests and trial mixes, the Engineer may
approve the use of manufactured sand in place of natural sand.
Aggregates shall be stored on clean hard surfaces or in bunkers in
such a manner as will effectively keep the different sizes separate
and will prevent contamination and excessive segregation.
Provision shall be made to drain off rainwater from the stockpiles.
The Engineer may require samples of aggregates to be taken
from the stockpiles and tested either on site or by an approved
local testing authority. Such tests shall be at the Contractor's
expenses. Periodic tests shall be made to determine the moisture
content of the aggregate.
The Engineer shall be notified
immediately of any alteration in the source of supply of
aggregate.
2e.04 Water
Water shall be clean fresh water free from chemical or organic
impurities.
It shall be obtained by metered supply from
Government mains or from another source approved by the
Engineer, who may require the water to be tested before giving
his approval. If it should be necessary to store water on site, care
shall be taken to prevent contamination.
2e.05 Admixtures
If the Contractor wishes to use any admixtures, he shall first
obtain the approval of the Engineer. Admixtures shall be used
strictly in accordance with the manufacturer's instructions and at
approved dosage levels. When admixtures are used the amount
of water added to the mix shall be adjusted to maintain suitable
workability for placement.
Unless specified otherwise, admixtures when used shall comply
with the following standards:
Pigment for colouring cement and concrete
Accelerators, retarders, normal waterreducing
admixtures and combination of
these
Superplasticising admixtures
BS 1014:1975
BS 5075-1:1982
BS 5075-3:1985
289981923.doc
- S2e/2 -
Dec 2011
General Specification
Section 2e Concrete
effects,
if
any,
of
- S2e/3 -
Dec 2011
General Specification
Section 2e Concrete
2e.07 Mixes
Concrete mixes shall be designed by the Contractor to have the
specified strength or grades shown on the drawings or in the
concrete schedule. Designed mixes (denoted by the suffix D) are
specified by strength and shall comply with the requirements
given in Table 1. Prescribed mixes (denoted by the suffix P) are
specified by grade and shall comply with the requirements of the
Building (Construction) Regulations.
The workability shall be selected with regard to the size of section
to be concreted, the amount of reinforcement and the means of
compaction so that the concrete can be well compacted without
causing segregation of the aggregate or bringing excess water to
the surface. A guide to workability is given in Table 2.
The wet concrete shall be sufficiently cohesive to prevent
segregation during transporting and placing operations. Mixes
which segregate easily shall not be used in the work.
The maximum size of aggregate for structural work shall
generally be 20mm. For thin sections and where reinforcement is
congested 10mm aggregate may be approved or required. For
large sections where the reinforcement is widely spaced and for
mass concrete 40mm aggregate may be approved or required.
The water/cement ratio will generally be chosen to suit strength
and workability requirements but may be limited by the
considerations of durability in accordance with Table 3.
The concrete shall contain the minimum amount of cement for durability
in accordance with Table 3A.
The Contractor shall obtain the Engineer's approval for mix
proportions proposed and for any adjustments which may be
necessary to maintain the required strength and workability
throughout the work. No concreting will be permitted until
approval of the mix proportions and trial mix results has been
given by the Engineer.
289981923.doc
- S2e/4 -
Dec 2011
General Specification
Section 2e Concrete
TABLE 1
DESIGNED CONCRETE MIXES
Specified Grade
Strength (MPa)
Grade
Min Average
Preliminary Cube
Strength (MPa)
At 28
At 28
Days
Days
(150mm) (100mm)
At 3
Days
At 7
Days
At 28
Days
25D
15
20
25
35
30D
18
24
30
35D
21
28
40D
24
45D
50D
Limits of
Aggregate/Cement
Ratio (by Weight)
Max.
Min.
37
6.5 : 1
4:1
40
42
5.0 : 1
3:1
35
45
47
5.0 : 1
3:1
32
40
50
52
4.5 : 1
3:1
27
36
45
55
57
4.5 : 1
3:1
30
40
50
60
62
4.5 : 1
3:1
NOTES :
1.
2.
3.
289981923.doc
- S2e/5 -
Dec 2011
General Specification
Section 2e Concrete
TABLE 2
GUIDE TO WORKABILITY
Approximate Value of Consistency
Tests
Vebe
Slump
Compactin Consistomet
(mm)
g Factor
er
(Seconds)
Conditions of Placing
Degree of
Workabilit
y
Very low
0 10
0.76
More than 12
Lightly reinforced
sections with vibration
Low
10 50
0.85
4 12
Heavily reinforced
sections with vibration
Medium
50 100
0.92
24
High
100 200
0.95
02
1. The consistency tests are useful for comparing different mixes within
certain limits, but are not always reliable as a measure of
workabilitysuitable for the conditions under which the concrete will be
placed.
2. Compacting Factor and Vebe Tests in accordance with Hong Kong
Construction Standard CS1:2010.
TABLE 3
MAXIMUM WATER/CEMENT RATIO
Low
Exposure
Medium
High
0.50
0.45
0.40
Medium sections
0.55
0.50
0.45
0.60
0.55
0.50
Type of Structure
289981923.doc
- S2e/6 -
Dec 2011
General Specification
Section 2e Concrete
TABLE 3A
MINIMUM CEMENT CONTENT kg/cu m
Maximum Aggregate Size
Reinforced Concrete :
- 20mm
- 10mm
Prestressed Concrete :
- 20mm
- 10mm
Plain Concrete :
- 40mm
- 20mm
Tremie Concrete :
- All sizes
Low
Exposure
Medium
290
340
360
410
300
340
360
410
220
250
270
310
400
400
High
To be
Determined
by the
Engineer
289981923.doc
- S2e/7 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
- S2e/8 -
Dec 2011
General Specification
Section 2e Concrete
Type of Concrete
Prestressed concrete; steam cured
structural concrete
Reinforced concrete with sulphate resisting
Portland cement
Reinforced concrete; concrete with
embedded metal
- S2e/9 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/10 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
Dec 2011
General Specification
Section 2e Concrete
(e)
(f)
(e.g.
(ii) The range of the three measured slump values for each
batch of concrete shall not exceed 20% of the average of
the three measured slump values for that batch. For flow
table tests, the range of the three measured flow values
for each batch of concrete shall be within 70mm.
289981923.doc
- S2e/12 -
Dec 2011
General Specification
Section 2e Concrete
Average of 18 cube
results to exceed
specified grade strength
by at least
Individual cube
result to exceed
specified grade
strength by at
least
14 MPa
10 MPa
7 MPa
3 MPa
12 MPa
8 MPa
6 MPa
2 MPa
100mm cubes
5.5 MPa or above
Below 5.5 MPa
150mm cubes
5.0 MPa or above
Below 5.0 MPa
289981923.doc
- S2e/13 -
Dec 2011
General Specification
Section 2e Concrete
Type of equipment.
General arrangement and methods of support of pipe lines.
Procedure for charging and emptying pipelines.
Organisation for ensuring a continuous supply of concrete
at the required rate.
Procedures in case of delays and breakdowns.
The inside diameter of the pipes and hoses shall not be less than
three times the maximum size of the aggregate. Aluminium
pipes shall not be used. Extra strong couplings shall be used on
vertical runs and on sections which are not easily accessible.
The grout or mortar used to lubricate the pipe line before
charging it with concrete shall not be deposited in the forms and
suitable means of disposal must be provided.
Water shall be used for emptying pipe lines supplied by piston or
squeeze pressure pumps. When the pipe line is emptied towards
the point of placement a suitable arrangement shall be made to
collect the water and prevent it from flowing over the freshly
placed concrete.
289981923.doc
- S2e/14 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
- S2e/15 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/16 -
Dec 2011
General Specification
Section 2e Concrete
When the concrete has sufficient strength and before placing new
concrete, the surface of the joint shall be thoroughly roughened
and cleaned. Any laitance or scum on horizontal joints shall be
removed by brushing, spraying with water and compressed air,
chipping or sand blasting.
Immediately before placing concrete against the joint, the surface
shall be wetted and in horizontal joints in walls and columns, a
layer of freshly mixed mortar of the same proportions of cement
and sand as the concrete mix shall be placed along the joint to a
depth of about 40mm.
Special care shall be taken in compacting concrete against a
joint.
2e.17 Expansion Joint
Expansion joints shall be formed in the locations and of the
widths shown on the drawings.
Unless other materials are shown on the drawings expansion join
gaps shall be formed with bitumen impregnated soft board of
approved quality wherever the filler is to remain in place and of
expanded polystyrene sheets where the filler has to be removed
to form an open gap.
2e.18 Contraction Joints
Contraction joints shall be formed in the locations indicated on
the drawings. Stop boards for contraction joints shall be as
specified for construction joints. The surface of the joint shall be
coated with an approved compound to prevent adhesion of the
new concrete. Contraction joints in slabs laid on the ground may
be made with approved crack inducers set in the forms or by saw
cuts after the concrete has gained sufficient strength. Chases
shall be formed for joint sealers where required.
2e.19 The Junction of Different Concretes in Monolithic Works
The change from one grade of concrete to another will generally
be made at a construction joint. Where the drawings require
different grades of concrete to be cast together without
construction joints the higher strength concrete shall be placed
first. The lower strength concrete shall be placed before the high
strength concrete has set and the two shall be well vibrated
together.
The high strength concrete shall extend at least 600mm or such
distance as is shown on the drawings beyond the junction of the
two members, towards the area of the lower strength concrete.
289981923.doc
- S2e/17 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/18 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
- S2e/19 -
Dec 2011
General Specification
Section 2e Concrete
Concrete Quantity
Represented by Each Sample
10 cu m or 10 batches is the
smaller volume
25 cu m or 25 batches is the
smaller volume
100 cu m or 100
whichever is the smaller
batches
- S2e/20 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/21 -
Dec 2011
General Specification
Section 2e Concrete
with CS1, of each core shall not be less than 75% of the
specified grade strength, and the average estimated in-situ
cube strength of each set of 3 or 12 cores shall not be less
than 85% of the specified grade strength.
2e.23 Defective Work
The Contractor shall inspect the concrete immediately after
stripping the forms and report any honeycombing or other
defects to the Engineer or his representative.
If tests show that the strength of the concrete is less than the
specified strength or if there should be serious honeycombing,
cracking or excessive creep, or shrinkage, or other defects, the
Engineer may order the defective work to be cut out and properly
reconstructed at the Contractor's expense. Such cutting out shall
extend to a position suitable, in the opinion of the Engineer, for a
construction joint.
When defective work is to be made good without reconstruction,
the Contractor shall first obtain the Engineer's approval of his
proposals for remedial work. No patching shall be done until the
defect has been inspected and the patching approved by the
Engineer or his representative.
If the concrete strength is less than the specified strength, the
Engineer may stop concreting in other parts of the structure
which may be relevant to the design.
2e.24 Load Test
The Engineer may order a load test:
(a) in the event of defective work;
(b) in the event of premature removal of props or the gross
overloading of any part of the structure; or
(c) for any other reason.
In the cases (a) and (b), the test shall be at the Contractor's
expense, in the third case (c), the Contractor shall be reimbursed
the cost of the test.
Such load test shall not be carried out until at least 28 days after
the date of concreting of the part of the structure to be load
tested.
The Contractor shall erect adequate struts and props to take the
whole of the test loads under the members to be tested and
leaving an adequate gap. The Contractor shall carry out all
proper safety precautions during the load test.
289981923.doc
- S2e/22 -
Dec 2011
General Specification
Section 2e Concrete
Both the test loads and the test shall be conducted in accordance
with the recommendation of the Code of Practice for Structural
Use of Concrete 2004 issued by the Buildings Department unless
otherwise specified, or as directed by the Engineer.
2e.25 Waterstop
Waterstops shall be installed where shown on the drawings or
where directed by the Engineer.
They shall be of proprietary brands approved by the Engineer.
Waterstops for walls and slabs below ground shall be of the
ribbed type suitable for installing on the outer face. Waterstops
for expansion or construction joints shall be types suitable to
accommodate movement.
Waterstops shall be mitred and jointed as required and shall be
carefully positioned to allow concrete to be placed and
compacted to form water tight joints.
The Contractor shall submit details of the waterstop types and
method of installation prior to construction for the approval of the
Engineer.
2e.26 Bending and Fixing Reinforcement
Reinforcement shall be bent to the dimensions shown on the
drawings or in the bar schedules in a manner which will not injure
the material. All bending shall be done cold unless the written
approval of the Engineer is obtained. If approval is given the bars
shall be bent at a cherry-red heat (not exceeding 8400C) and
shall be cooled slowly.
Re-bending of high yield bars will not be permitted. Where it is
necessary to bend mild steel reinforcement already cast in the
concrete, the internal radius of the bend shall be not less then
twice the diameter of the bar.
All cutting, bends and bending tolerances shall conform to B.S.
8666:2000. Where bars are cranked at laps the slope of the
crank shall not be more than 1 in 12.
All reinforcement shall be securely tied together with soft
annealed iron wire of sufficient strength and at sufficient
intersections to prevent displacement during concreting. The
ends of the binding wire shall be turned inwards and shall not
project into the concrete cover.
The cover provided to the reinforcement shall not be less than
the minimum shown on the drawings or specified in Table 4 after
289981923.doc
- S2e/23 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
- S2e/24 -
Dec 2011
General Specification
Section 2e Concrete
At foot of chairs
Columns
Walls
Beams
Slabs/Stairs
NOTE: More than the minimum cover may be required for marine works.
2e.27 Welding Reinforcement
The Engineer's approval must first be obtained before welding
reinforcement. In general, mild steel bars are reaily weldable.
High yield steel bars are weldable if the carbon equivalent is not
more than 0.51. When welding is permitted care shall be taken to
prevent fires and suitable fire extinguishers shall be provided
close to each working point. Where there is a risk of sparks or
hot weld metal falling on flammable material below, a man with a
portable fire extinguisher shall be on watch at the lower level.
Only skilled welders shall be employed on the work. For all welds
other than tack welds, full details of the welding procedure
(including type of electrode the preparation of the joint) shall be
submitted for the Engineer's approval.
2e.28 Use of Mechanical Couplers
Where the use of mechanical couplers is specified or approved,
the couplers shall be of a proprietary type, approved by the
Engineer and shall be installed strictly in accordance with the
manufacturer's instructions and the Code of Practice for
Structural Use of Concrete 2004 issued by the Buildings
Department.
Unless otherwise stated, mechanical couplers shall be capable of
splicing bars in tension. They shall also be suitable for the
conditions of the bars with respect to rotation. Where mechanical
couplers are left in place for future connection, they shall be
adequately protected against ingress of grout during concreting
and subsequently against corrosion.
The position of splices shall be as shown on the drawings. The
289981923.doc
- S2e/25 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/26 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
- S2e/27 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/28 -
Dec 2011
General Specification
Section 2e Concrete
289981923.doc
- S2e/29 -
Dec 2011
General Specification
Section 2e Concrete
The periods for which the formwork and props for concrete made
with Ordinary Portland Cement shall be left in place will depend
on the weather conditions, methods of curing, gain in strength,
type of member and subsequent loading but shall not be less
than the following:
Vertical formwork for sides of Beams, Columns, 12 Hrs
Walls and similar locations (Unloaded)
(to
be
increased if
concrete
with PFA)
Soffit formwork of Slabs (with props left in 4 Days
place)
Waffle Slab moulds (with props to Ribs left in 4 Days
place)
Soffit formwork of Beams (with props left in 7 Days
place)
Props for Slabs between Beams
10 Days
Props to Beams, Flat Slabs & Waffle Slab Ribs
14 Days
Props to Cantilevers
14 Days
When construction loads will exceed the design loads or cause
deflections which may affect the tolerance specified for
subsequent work, sufficient props shall be left in place to
distribute the loads over a number of storeys as directed by the
Engineer.
2e.34 Propping and Reshoring
Adequate props shall be retained in position until new
construction has sufficient strength to support its designed load
or any temporary load to be placed on it during subsequent
construction operations.
In multi-storey construction, particularly where long span or
cantilevers occur, propping to successive floors shall be left in
place and carried down far enough to distribute the construction
loads to avoid overstress or excessive deflection.
Whenever possible, the formwork shall be constructed so that it
can be removed without disturbing the props which are required
to be left in place. Where this is not practicable, the structure
shall be reshored immediately after removing the formwork.
During the stripping and reshoring operation, no construction
loads shall be placed on the new construction. The operation
shall be planned and performed so that no large areas are left
unsupported at any time. The shores replaced shall be positioned
over the shores on the floow below. Care shall be taken to
tighten them sufficiently to prevent significant shortening under
289981923.doc
- S2e/30 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/31 -
Dec 2011
General Specification
Section 2e Concrete
the aggregate.
When slabs are to be finished without a topping, they shall be
trowelled with a rotary trowel or tamped to produce a rough finish
as required by the schedule of finishes.
When slabs are to have a topping applied after the concrete has
hardened, they shall be finished with a wooden float.
Top surface to concrete floors and roofs which are to receive
finishes direct (i.e. without cement and sand screeds) shall be
finished to provide the same standard of finish as would be given
by a normal cement and sand screed. Normal structural
tolerances will apply but additionally no lips, bumps or hollows
will be permitted.
The Contractor's attention is drawn to the problems inherent in
achieving this kind of finish. A special concrete mix design which
is suitable for finishing may be required. Special precautions shall
be taken to prevent inclement weather affecting the surfaces
during placing and subsequently until the concrete is fully cured.
Care shall be taken to avoid damaging the surface during
subsequent construction. Before construction commences, the
Contractor shall submit for approval his proposals and methods
for carrying out this section of the work.
The first area of concrete cast by the Contractor with this finish
shall be submitted for approval. Immediately after the sample
bay has sufficiently matured, the Contractor shall obtain evidence
that his Flooring Sub-Contractor is satisfied that the standard of
finish is suitable for flooring to be laid directly on to the surface.
2e.37 Tolerances for In-Situ Construction
Unless shown otherwise on the drawings, tolerances shall not
exceed the values shown in the schedules for the respective parts
of the work. The tolerances shown shall not be considered
cumulatively. The tolerances shown shall not include deflection of
the structure.
In general, the provisions of this clause must be complied in full.
Wherever any construction tolerance limits specified in Section
10 of the Code of Practice for Structural Use of Concrete 2004 are
not covered in this clause, the tolerance limits specified in
Section 10 of the Code of Practice for Structural Use of Concrete
2004 shall be adopted.
Schedule of Tolerances for Insitu Construction
(a)
289981923.doc
Dec 2011
General Specification
Section 2e Concrete
(c)
289981923.doc
- S2e/33 -
Dec 2011
General Specification
Section 2e Concrete
(d)
Means Levels
Maximum deviation of mean level from the level:
(e)
i)
6mm
ii)
12 mm
iii)
20 mm
iv)
20 mm
(f)
Conspicuous Horizontals
Deviation of edges of exposed lintels, sills, parapets,
horizontal grooves and other conspicuous lines from the
horizontal:
- 6mm in any 6 metres of length
- 10mm in any 12 metres or more
(g)
Cross Sections
Maximum deviation from the values of the cross section
dimensions of columns, beams, walls, floors, roof slabs, and
other structures:
289981923.doc
(i)
+10mm
3mm
(ii)
+12mm
6mm
- S2e/34 -
Dec 2011
General Specification
Section 2e Concrete
(h)
Openings
Maximum deviation from the sizes and locations of openings
in floors and walls:
6 mm
Notwithstanding the above tolerances, the Contractor will
be responsible for providing for any additional margin as
may be required for window, door or lift door frame,
installation.
(i)
Stairs
Deviation in risers:
- In consecutive steps
- In any flight
Deviation in treads:
- In consecutive steps
- In any flight
(j)
3 mm
6 mm
(k)
2 mm
6 mm
25 mm
6 mm
+12m
m
6mm
(ii)
- S2e/35 -
Dec 2011
General Specification
Section 2e Concrete
400
480
560
640
800
0.86
1.55
2.40
3.10
5.20
289981923.doc
- S2e/36 -
Dec 2011
General Specification
Section 2e Concrete
- S2e/37 -
Dec 2011
General Specification
Section 2e Concrete
exceeding
Exceeding 1m,
but not
exceeding 2m
Exceeding 2m,
289981923.doc
Depth of
Lintel
(mm)
150
225
8mm dia.
300
10mm dia.
- S2e/38 -
Single
Stirrups at
300mm c/c
8mm dia.
Dec 2011
General Specification
Section 2e Concrete
but not
exceeding 3m
289981923.doc
- S2e/39 -
Dec 2011