Federal Register / Vol. 70, No.

25 / Tuesday, February 8, 2005 / Notices 6645

interventions in lieu of paper using the company would seek to negotiate a right-of-way and aboveground facility
‘‘eFiling’’ link at http://www.ferc.gov. mutually acceptable agreement. sites. The remaining 100.4 acres of land
Persons unable to file electronically However, if the project is approved by would be restored and allowed to revert
should submit an original and 14 copies the Commission, that approval conveys to its former use.
of the protest or intervention to the with it the right of eminent domain.
The EA Process
Federal Energy Regulatory Commission, Therefore, if easement negotiations fail
888 First Street, NE., Washington, DC to produce an agreement, the pipeline The National Environmental Policy
20426. company could initiate condemnation Act (NEPA) requires the Commission to
This filing is accessible on-line at proceedings in accordance with state take into account the environmental
http://www.ferc.gov, using the law. impacts that could result from an action
‘‘eLibrary’’ link and is available for A fact sheet prepared by the FERC whenever it considers the issuance of a
review in the Commission’s Public entitled ‘‘An Interstate Natural Gas Certificate of Public Convenience and
Reference Room in Washington, DC Facility On My Land? What Do I Need Necessity. NEPA also requires us to
There is an ‘‘eSubscription’’ link on the To Know?’’ was attached to the project discover and address concerns the
Web site that enables subscribers to notice Rendezvous provided to public may have about proposals. This
receive e-mail notification when a landowners. This fact sheet addresses a process is referred to as ‘‘scoping’’. The
document is added to a subscribed number of typically asked questions, main goal of the scoping process is to
docket(s). For assistance with any FERC including the use of eminent domain focus the analysis in the EA on the
Online service, please e-mail and how to participate in the important environmental issues. By this
FERCOnlineSupport@ferc.gov, or call Commission’s proceedings. It is Notice of Intent, the Commission staff
(866) 208–3676 (toll free). For TTY, call available for viewing on the FERC requests public comments on the scope
(202) 502–8659. Internet Web site (http://www.ferc.gov). of the issues to address in the EA. All
Linda Mitry, comments received are considered
Summary of the Proposed Project during the preparation of the EA. State
Deputy Secretary.
Rendezvous wants to provide a direct and local government representatives
[FR Doc. E5–510 Filed 2–7–05; 8:45 am]
connection between a gas processing are encouraged to notify their
BILLING CODE 6717–01–P
plant in Uinta County, Wyoming and constituents of this proposed action and
Kern River Gas Transmission Company encourage them to comment on their
in Lincoln County, Wyoming, and to areas of concern.
DEPARTMENT OF ENERGY
transport gas gathered by Rendezvous In the EA we 3 will discuss impacts
Federal Energy Regulatory and its owners, Questar Gas that could occur as a result of the
Commission Management Company and Mountain construction and operation of the
Gas Resources, Inc. Rendezvous seeks proposed project under these general
[Docket No. CP05–40–000] authority to construct and operate: headings:
• 20.8 miles of 20-inch-diameter • Geology and soils.
Rendezvous Gas Services, L.L.C.;
Notice of Intent To Prepare an
pipeline in Uinta and Lincoln Counties, • Land use.
Environmental Assessment for the
Wyoming; • Water resources, fisheries, and
• A mainline valve at milepost 8.1 of wetlands.
Proposed Rendezvous Phase V Project
and Request for Comments on
the proposed pipeline, in Lincoln • Cultural resources.
County; • Vegetation and wildlife.
Environmental Issues
• Filtering, metering, and pigging • Air quality and noise.
February 1, 2005. facilities at the Blacks Fork Gas Plant in • Endangered and threatened species.
The staff of the Federal Energy Uinta County; and • Hazardous waste.
Regulatory Commission (FERC or • A pigging facility at the Muddy • Public safety.
Commission) will prepare an Branch Compressor Station in Lincoln We will also evaluate reasonable
environmental assessment (EA) that will County. alternatives to the proposed project or
discuss the environmental impacts of The general location of the project portions of the project, and make
the Rendezvous Phase V Project facilities is shown in Appendix 1.2 If recommendations on how to lessen or
involving construction and operation of you are interested in obtaining detailed avoid impacts on the various resource
facilities by Rendezvous Gas Services, maps of a specific portion of the project, areas.
L.L.C. (Rendezvous) in Uinta and send in your request using the form in Our independent analysis of the
Lincoln Counties, Wyoming.1 These Appendix 3. issues will be in the EA. Depending on
facilities would consist of about 21 Land Requirements for Construction the comments received during the
miles of 20-inch-diameter pipeline and scoping process, the EA may be
appurtenant facilities. This EA will be Construction of the proposed facilities published and mailed to federal, state,
used by the Commission in its decision- would require about 199.5 acres of land. and local agencies, public interest
making process to determine whether Following construction, about 99.1 acres groups, interested individuals, affected
the project is in the public convenience would be maintained as new permanent landowners, newspapers, libraries, and
and necessity. the Commission’s official service list for
2 The appendices referenced in this notice are not
If you are a landowner receiving this this proceeding. A comment period will
being printed in the Federal Register. Copies of all
notice, you may be contacted by a appendices, other than Appendix 1 (maps), are be allotted for review if the EA is
pipeline company representative about available on the Commission’s Web site at the published. We will consider all
the acquisition of an easement to ‘‘eLibrary’’ link , and all appendices, including comments on the EA before we make
construct, operate, and maintain the Appendix 1, are available from the Commission’s our recommendations to the
Public Reference Room, 888 First Street, NE.,
proposed facilities. The pipeline Washington, DC 20426, or call (202) 502–8371. For Commission.
instructions on connecting to eLibrary refer to the
1 Rendezvous’ application was filed with the last page of this notice. Copies of the appendices 3 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the

Commission under section 7 of the Natural Gas Act were sent to all those receiving this notice in the environmental staff of the Office of Energy Projects
and part 157 of the Commission’s regulations. mail. (OEP).

VerDate jul<14>2003 18:12 Feb 07, 2005 Jkt 205001 PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 E:\FR\FM\08FEN1.SGM 08FEN1
6646 Federal Register / Vol. 70, No. 25 / Tuesday, February 8, 2005 / Notices

To ensure your comments are for this proceeding. If you want to the documents. Go to http://
considered, please carefully follow the become an intervenor you must file a www.ferc.gov/esubscribenow.htm.
instructions in the public participation motion to intervene according to Rule Finally, public meetings or site visits
section beginning on page 4. 214 of the Commission’s Rules of will be posted on the Commission’s
Practice and Procedure (18 CFR calendar located at http://www.ferc.gov/
Public Participation
385.214) (see Appendix 2).4 Only EventCalendar/EventsList.aspx along
You can make a difference by intervenors have the right to seek with other related information.
providing us with your specific rehearing of the Commission’s decision.
comments or concerns about the project. Magalie R. Salas,
Affected landowners and parties with
By becoming a commentor, your environmental concerns may be granted Secretary.
concerns will be addressed in the EA intervenor status upon showing good [FR Doc. E5–499 Filed 2–7–05; 8:45 am]
and considered by the Commission. You cause by stating that they have a clear BILLING CODE 6717–01–P
should focus on the potential and direct interest in this proceeding
environmental effects of the proposal, which would not be adequately
alternatives to the proposal (including represented by any other parties. You do DEPARTMENT OF ENERGY
alternative routes), and measures to not need intervenor status to have your
avoid or lessen environmental impact. Federal Energy Regulatory
environmental comments considered.
The more specific your comments, the Commission
more useful they will be. Please Environmental Mailing List [Project No. 2194–020]
carefully follow these instructions to An effort is being made to send this
ensure that your comments are received notice to all individuals, organizations, FPL Energy Maine Hydro LLC; Notice
in time and properly recorded: and government entities interested in of Application Ready for
• Send an original and two copies of and/or potentially affected by the Environmental Analysis and Soliciting
your letter to: Magalie R. Salas, proposed project. This includes all Comments, Recommendations, Terms
Secretary, Federal Energy Regulatory landowners who are potential right-of- and Conditions, and Prescriptions
Commission, 888 First St., NE., Room way grantors, whose property may be February 1, 2005.
1A, Washington, DC 20426. used temporarily for project purposes,
• Label one copy of the comments for Take notice that the following
or who own homes within distances
the attention of Gas Branch 3. hydroelectric application has been filed
defined in the Commission’s regulations
• Reference Docket No. CP05–40– with the Commission and is available
of certain aboveground facilities. By this
000. for public inspection.
notice we are also asking governmental
• Mail your comments so that they a. Type of Application: New major
agencies, especially those in Appendix
will be received in Washington, DC on license.
3, to express their interest in becoming
or before March 7, 2005. b. Project No.: P–2194–020.
cooperating agencies for the preparation
The Commission strongly encourages c. Date Filed: June 30, 2003.
of the EA.
electronic filing of any comments or d. Applicant: FPL Energy Maine
interventions or protests to this Additional Information Hydro LLC.
proceeding. See 18 CFR Additional information about the e. Name of Project: Bar Mills
385.2001(a)(1)(iii) and the instructions project is available from the Hydroelectric Project.
on the Commission’s Web site at Commission’s Office of External Affairs, f. Location: Located on the Saco River
http://www.ferc.gov under the ‘‘e- at 1–866–208–FERC or on the FERC in the towns of Buxton and Hollis, York
Filing’’ link and the link to the User’s Internet website (http://www.ferc.gov) County, Maine. This project does not
Guide. Before you can file comments using the eLibrary link. Click on the use federal lands.
you will need to create a free account eLibrary link, click on ‘‘General Search’’ g. Filed Pursuant to: Federal Power
which can be created on-line. and enter the docket number excluding Act 16 U.S.C. 791 (a)–825(r).
We might mail the EA for comment. the last three digits in the Docket h. Applicant Contact: Frank Dunlap,
If you are interested in receiving it, Number field. Be sure you have selected FPL Energy Maine Hydro LLC, 160
please return the Information Request an appropriate date range. For Capitol Street, Augusta, ME 04330, (207)
(Appendix 4). If you do not return the assistance, please contact FERC Online 623–8417.
Information Request, you will be taken Support at FercOnlineSupport@ferc.gov i. FERC Contact: Jack Hannula, (202)
off the mailing list. or toll free at 1–866–208–3676, or for 502–8917, john.hannula@ferc.gov.
j. Deadline for Filing Comments,
Becoming an Intervenor TTY, contact (202) 502–8659. The
Recommendations, Terms and
eLibrary link also provides access to the
In addition to involvement in the EA Conditions, and Prescriptions: 60 days
texts of formal documents issued by the
scoping process, you may want to from the issuance date of this notice;
Commission, such as orders, notices,
become an official party to the reply comments are due 105 days from
and rulemakings.
proceeding known as an ‘‘intervenor’’. issuance date of this notice.
In addition, the Commission now
Intervenors play a more formal role in All documents (original and eight
offers a free service called eSubscription
the process. Among other things, copies) should be filed with: Magalie R.
which allows you to keep track of all
intervenors have the right to receive Salas, Secretary, Federal Energy
formal issuances and submittals in
copies of case-related Commission Regulatory Commission, 888 First
specific dockets. This can reduce the
documents and filings by other Street, NE., Washington, DC 20426.
amount of time you spend researching
intervenors. Likewise, each intervenor The Commission’s Rules of Practice
proceedings by automatically providing
must send one electronic copy (using and Procedure require all intervenors
you with notification of these filings,
the Commission’s eFiling system) or 14 filing documents with the Commission
document summaries and direct links to
paper copies of its filings to the to serve a copy of that document on
Secretary of the Commission and must 4 Interventions may also be filed electronically via each person whose name appears on the
send a copy of its filings to all other the Internet in lieu of paper. See the previous official service list for the project.
parties on the Commission’s service list discussion on filing comments electronically. Further, if an intervenor files comments

VerDate jul<14>2003 18:12 Feb 07, 2005 Jkt 205001 PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 E:\FR\FM\08FEN1.SGM 08FEN1

You might also like