Professional Documents
Culture Documents
Recognizing that current Federal, State and local disaster response capabilities needed to be
enhanced to better address the anticipated effects of truly catastrophic disasters, FEMA
embarked on a "Catastrophic Planning" initiative in FY 2003. The goal was to identify areas
of the country that could be vulnerable to catastrophic disasters and, in cooperation with the
relevant State and local governments, to:
. Examine projected damages and effects associated with a catastrophic disaster
. Confirm current disaster response capabilities
. Identify anticipated response shortfalls, and
. Initiate comprehensive planning strategies to address the shortfalls
Products developed under the "Catastrophic Planning" initiative were envisioned to include
incident-specific response plans for pre-selected geographic regions and disasters, planning
templates that could be applied to other areas, and new response contingencies.
Thirteen southeastern Louisiana Parishes (including the City of New Orleans) were selected as
the initial geographic focus area for FEMA's "Catastrophic Planning" initiative because of
their vulnerability to hurricane disasters. The Southeast Louisiana Catastrophic Hurricane
Planning Project documents the results of this collaborative effort.
More specifically, the Southeast Louisiana Catastrophic Hurricane Planning Project was
designed to bring together responders and decision makers from all levels of government and
the American Red Cross to begin analyzing and addressing the overwhelming operational
complexities that would be involved in responding to a catastrophic hurricane striking
southeast Louisiana. Accepting the fact that only limited funding and time were available,
topic specific "planning workshops" using a catastrophic hurricane scenario (Hurricane Pam)
to frame the discussions were selected as the best approach for identifying and qualifying the
scale of requirements needed to build a plan for responding to a catastrophic hurricane. The
results were intended to reveal to the Louisiana Office of Homeland Security and Emergency
Preparedness (LOHSEP) and FEMA the shortfalls in existing plans and to begin developing
additional plans for catastrophic hurricane response.
Existing plans, strategies, policies, and capabilities were reviewed by LOHSEP before the first
workshop. As pre-planning for the first workshop, conducted in July 2004, LOHSEP and
Federal representatives identified a list of planning topics as the most urgent or complex topics
needing discussion, including:
Although the catastrophic planning process has been interrupted by the impacts of Hurricanes
Katrina and Rita, the workshops and planning process - knowledge of inter-jurisdictional
relationships and capabilities, identification of issues, and rudimentary concepts for handling
the consequences - have been beneficial to hurricane response activities.
September 23,2005
Preface to the Louisiana Catastrophic Hurricane Planning Documents
The Louisiana Catastrophic Hurricane Planning Project begun in 2004 was funded by the Federal
Emergency Management Agency. The project is assisting the State of Louisiana, the southern most
13 Louisiana parishes (including the City of New Orleans) that will be most affected by a catastrophic
hurricane, appropriate federal regional personnel, and FEMA HQ representatives in conducting
catastrophic hurricane planning in Southeast Louisiana.
The plan is not complete, but represents the immediate response needs as identified by the
State. Also per the State's request, the planning workshops were organized around planning topics,
not by ESFs. Participants collaborated with each other to develop plans that documented a response
process. The "Matrixof Planning Topics and ESFs" crosswalks the workshop Planning Topics to
the 15 Emergency Support Functions contained in the NationalResponse Plan. This document was
originally developed in late 2004 but was modified in August 2005 to add explanatory information.
The planning process consisted of a series of week long planning workshops attended by response
operations personnel as listed above. The workshops were conducted in July 2004, November 2004,
July 2005, and August 2005.
The family of documents that were produced includes the:
. "Southeast LouisianaCatastrophicHurricanePlan" and the "Southeast Louisiana
Catastrophic Hurricane Plan -Appendices" which are current as of December 2004;
. "Transportation, Staging, and Distribution of Critical Resources" (draft functional plan),
the "Transportation, Staging, and Distribution of Critical Resources - Appendices, the
"Temporary Housing Functional Plan" (draft), and the "Temporary Housing Site Data
Collection Form" (draft) which were produced at the July 2005 workshop (they are still very
rough and conflicts have not yet been resolved with the "Southeast Louisiana Catastrophic
Hurricane Plan"); and
. "Temporary Medical Care" (draft) and "Appendices" (draft) which were produced during a
two-day workshop in August 23 & 24, 2005, after transcription by the contractor and
consultation and approval by the State. This document was forwarded to FEMA HQ on
September 3, 2005.
The period of performance for the contract that funded development of these documents was
originally September 30, 2005. In early August 2005, FEMA Region VI requested an extension to
November 30, 2005, to give more time to the contractor to integrate sections of the document
developed in July and August 2005 (the July workshop was originally scheduled for April 2005).
The extension was agreed to by the COTR in conversation with the contractor but has not been
formalized in a memorandum to the Contracting Officer at FEMA HQ.
- ueel1
'
If Il1for1l1a t
1011/tet ,
Memorandum ~ IEM.
Re: Development History of the Southeast Louisiana Catastrophic Hurricane
Plan Documentation
The current version of the Southeast Louisiana Catastrophic Hurricane Plan Documentation
is Revision 5, dated January 5, 2005. It was delivered to FEMA HQ, FEMA Region VI,
and the Louisiana Office of Homeland Security and Emergency Preparedness (LOHSEP)
for review and comment. Revision 5 contains information developed during Phase 1 (July
16-23,2004) and Phase lA (November 29-December 3,2004) of the Southeast Louisiana
Catastrophic Hurricane Planning Workshop.
These two sections were released as separate files to FEMA on August 27,2005.
Following Phase 1B, on August 23-24, 2005, the Southeast Louisiana Catastrophic
Hurricane Temporary Medical Care Supplementary Planning Workshop was held. As a
result, Temporary Medical Care (Section 14) was updated with notes taken at the
workshop. This section was submitted to FEMA on September 1,2005, as Update 1. It was
replaced on September 3,2005, as Update 2, incorporating additional appendices along
with updates to the Concept of Operations (CONOPS).
In the summer and fall of 2004 emergency management and disaster responders from the local,
state and federal levels met to develop a comprehensive, integrated plan to guide response and
recovery efforts in the event a major hurricane hits southeast Louisiana causing catastrophic
damage, injury and loss of life.
More than 250 people worked together for more than a week in Jul/ to develop several
component or "functional" plans addressing specific dimensions of an integrated response effort.
In August, 2004, leaders from three of the planning groups2met to review their plans and design
a follow-up workshop to further develop and enhance their plans. These three leadership teams
drafted the objectives and agendas for a smaller, more focused workshop, which was held
November29 - December3, 2004.
The attached table lists the various topics or issues for which plans were developed during the
Louisiana Catastrophic Hurricane Planning Project in addition to projected topics for later
discussion. Ofthe "Topics Proposed for Future Planning" listed at the bottom of the following
matrix, only Transportation was discussed at the subsequent workshop in July, 2005.
Participants .at a workshop in August 2005 discussed aspects of Temporary Medical Care not
covered in earlier workshops.
1 State and federal personnel met July 16-18to develop pre-landfall plans. Local personnel joined them July 19-23
to develop post-landfall plans.
2 The three leadership teams meeting on August i 8, 2004 were those planning for Temporary Medical Services,
Sheltering, and Temporary Housing. .
;::
"' ~ ""§
._;:;
Q)
-
.f'
..
>-.:::
~ 0
E ~ u ~ ;:; '2'-
~~
",.Vj 1:: ::E ~
"en ~3
::: '" ~;:;~ E.-
r/J
::: :::~
0 §;:;~o~
0 u 0. -y;:;oZ
"" 0 0. ~E'-;::~
0:2: .-
0 ~ X! :2: :I:'s: g. -£ ..<::"E ~ ~ .c u IS
.~
~ i3
.- .. g?
0.-.5 01) >-.
u e-..'" r/J 0:; Q) ~
'" "'''
N en e;:; en ~'" E ~>-."""
'j
.. :::;S:" ~ ::: ",r/J 1$:I:en Q) ~-~1$ r/J""-
8. ;:; u ~ ~ ~ u::: .. u 8 en ""'.~"3" >-. u <¥ ~ "' E
en
::: ~ :.=.5 ~
..DOl) '"
.. en "'
'" E 15 :'='-
en en..D>..D § ~ ~"enQ).~ i5 i:?
'" :.=
..D 01)
:::u0 ~
~ 0 E
;:;:::.!:: "';:; '" ;:; \) .. :-;::'" 01)'" ::: ;:; 0 '" x
Plannin2 Topics E-< U ~ ~ "'" ~ :2::I: " ~ r/J :J 0:2: ~" ~ ~ 1" ~
Pre-Landfall
Annex A: Incident Action Plans
Annex B: Louisiana State Hurricane Checklist
Annex~: FEMA Region VI Hurricane X X X X X X X X X X X X X X X
Checklist
Annex D: Pre-Landfall Concept of Support
Post-Landfall
Main Planning Topics
Debris X X X X X .X
Schools X X X X X
Search and Rescue X X ? X X X X X ? X
Sheltering X X X X X X X? X
Temporary Housing X X X X X X X?? X
Temporary Medical Care X X X X X X X X ?? X
Discrete Planning Topics
(The "?','s represent ESFs that may be applicable to the topic indicated depending on how the ESF is defined in the new NRP.)
3 The Louisiana Catastrophic Hurricane Plan was developed under the Federal Response Plan. Under that plan some Emergency Support Functions
(ESFs) had different names or did not exist. The differences are listed below.
ESF #5 was Informatipn & Planning ESF #13 did not exist
ESF #6 was Mass Care ESF #14 did not exist
ESF #8 was Health & Medical Services ESF #15 did not exist
ESF#10 was HazardousMaterials
ESF #11 was Food
4 This includes movement of people ITom Search and Rescue to Temporary Medical Care to Sheltering to Temporary Housing.
August 28, 2005 Page 2 of2
Louisiana - Southeast Parishes by Population Included in the
Catastrophic Hurricane Planning Project
"
,rJ -Legend
~,
.~J Population by Parish
tf
..-
D 0 -48,072
- 48,073 - 104,503
104,504 - 191,268
191,269 - 484,674
+
10 20 40 60
mn"
MaplD 1b6aeff3a8e