Professional Documents
Culture Documents
Cmi1.Whitepaperpdf - Asme & en
Cmi1.Whitepaperpdf - Asme & en
Tendering Manager
CMI Energy
CMI Energy
pascal.fontaine@cmigroupe.com
robert.bonsang@cmigroupe.com
BELGIUM
BELGIUM
Table of Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Introduction .....................................................................................................................2
Heat exchanger tubes.......................................................................................................3
Piping and headers design ...............................................................................................3
Piping weights .................................................................................................................4
Calculated thickness of ASME versus EN .......................................................................6
Piping routing and stress analysis ....................................................................................9
Pipe fittings ...................................................................................................................10
Drum design ..................................................................................................................11
Cycling fatigue analysis.................................................................................................11
Valves design.............................................................................................................13
Safety devices ............................................................................................................15
Pump design ..............................................................................................................16
Quality control of welds .............................................................................................16
Conclusions ...............................................................................................................18
References .................................................................................................................18
Page 1 of 18
1. Introduction
In Europe, boilers that are part of Combined Cycle Power Plants, have to be designed
according to an harmonized code as per the mandatory Pressure Equipment Directive
97/23/EC (PED). National design codes are progressively replaced by the EuroNorm 12952
as it is used in Europe and even abroad, even though the ASME code is still prevailing. These
various design codes must be selected according to PED. Recently, CMI has completed a
Heat Recovery Steam Generator for a 400 MW standard block CCPP in France, for which
ASME code was used for the HRSG design. For that project, CMI has conducted an internal
review based on the EuroNorm instead of the ASME code. The purpose of this exercise was
to study and compare advantages and design features of ASME code versus EuroNorm. This
report presents the conclusions of this review, which will be of interest to the European power
market because EuroNorm is more and more prescribed by specification for CCPP.
Page 2 of 18
ASME material
(welded and seamless)
SA178A
EN material
(all seamless)
EN 10216-2/P235GH
SA178C
EN 10216-3/P355NH
SA178A
SA213 T11(*)
SA178A
SA213T22(*)
SA213T91(*)
EN 10216-2/P235GH
EN 10216-2/13CrMo4-5
EN 10216-2/P235GH
EN 10216-2/10CrMo9-10
EN 10216-2/ X10CrMoVNb9-1
LP , IP superheater
Reheater and HP
Superheater
(*) seamless
Table 1 Finned tubes material used for this particular plant
Following materials selection as per Table 1, and considering a life time of 200000 h for EN,
tubes thickness of finned tubes are the same between codes on LP and IP circuits. However,
the HP circuit is lighter in EN. The weight reduction is as follows: 10.3 t on carbon steel, 5.7 t
on 10CrMo9-10, and 3.2 t on X10CrMoVNb9-1 tubes.
Page 3 of 18
and flanges according to diameters. As each main line has its defined piping specifications,
the 3D model used for the isometric generation picks up the correct rating and thickness of all
accessories located in this pipe or connected pipes subject to the same design conditions. CMI
has developed such piping specifications adapted for either ASME or EN codes (Table 2).
Series 4 to 8 are comparable to SCH 40 to SCH XXS. These are most usual for piping design.
THICKNESS
DIAMETER
mm
Series 2
Series 3
Sch.40
Series 4
21,3
2
2,3
2,6
2,6
2,6
2,9
2,9
3,2
3,6
4
4,5
2,6
2,6
3,2
3,6
3,6
3,6
3,6
4,0
4,5
5,0
5,6
2,77
2,87
3,38
3,56
3,68
3,91
5,16
5,49
6,02
6,55
7,11
3,2
3,2
4
4
4
4
4,5
5,6
6,3
6,3
7,1
26,7(26,9)
33,4(33,7)
42,2(42,4)
48,3
60,3
73(76,1)
88,9
114,3
141,3(139,7)
168,3
Sch.20
6,35
6,35
323,8(323,9) 6,35
7,92
355,6
7,92
406,4
7,92
457
9,53
508
9,53
559
9,53
610
12,70
660
12,70
711
12,70
762
219,1
273
Sch.ST
D
9,53
9,53
9,53
9,53
9,53
9,53
9,53
Sch.80
Series 5
Sch.120 Series 6
Sch.160
3,73 4,0
4,78
3,91 4,0
4,5 5,56
4,55 4,5
5,6 6,35
4,85 5,0
6,3 6,35
5,08 5,0
6,3 7,14
5,54 5,6
7,1 8,74
7,01 7,1
9,53
8
7,62 8,0
8,8 11,13
8,56 8,8
13,49
11,13 11
9,53 10,0
15,88
12,5
12,7
10,97 11,0
18,26
14,27 14,2
Series7
Sch.XXS
Series 8
5,0
5,6
6,3
8,0
8,0
8,8
10,0
11,0
14,2
16,0
17,5
7,47
7,82
9,09
9,70
10,15
11,07
14,02
15,24
17,12
19,05
21,95
7,1
8,0
8,8
10,0
10,0
11,0
14,2
16,0
17,5
20,0
22,2
Series2
Sch.30
Series 3
Sch.40
Series 4
Sch.60
Series 5
Sch.80
Series 6
Sch.120 Series 7
Sch.160 Series 8
6,3
6,3
7,1
8,0
8,8
10,0
10,0
10,0
10,0
10,0
10,0
10,0
7,04
7,80
8,38
9,53
11,13
12,70
12,70
14,27
n.a.
7,1
8,8
8,8
10,0
10,0
11,0
11,0
n.a.
12,5
12,5
12,5
12,5
8,18
9,27
10,31
11,13
12,70
14,27
15,09
n.a.
17,48
8,0
10,0
10,0
12,5
12,5
12,5
12,5
12,5
17,5
17,5
25,0
25,0
10,31
12,70
14,27
15,09
16,66
19,05
20,62
22,23
24,61
12,5
12,5
12,5
16,0
17,5
17,5
17,5
20,0
25,0
12,7
15,09
17,48
19,05
21,44
23,83
26,19
28,58
30,96
16,0
16,0
17,5
20,0
22,2
22,2
25,0
28,0
30,0
18,26
21,44
25,40
27,79
30,96
34,93
38,10
41,28
46,02
23,01
28,58
33,32
35,71
40,49
45,24
50,01
53,98
59,54
17,5
22,2
25,0
28,0
30,0
32,0
36,0
n.a.
45,0
22,2
30,0
32,0
36,0
40,0
45,0
50,0
n.a.
60,0
Page 4 of 18
Designation
O.D
mm
Thickness
ASME
mm
A
B
C
X
Y
Z
508
508
273
457
610
610
15.09
15.09
15.09
9.53
30.96
30.96
Thickness
EN
mm
Material
ASME
Material
EN
12.5
12.5
12.5
12.5
45
45
SA335P11
SA335P11
SA106B
SA106B
SA335P22
SA335P22
13CrMo4-5
13CrMo4-5
P265GH
P265GH
10CrMo9-10
10CrMo9-10
Weight
difference
(ENASME)
-0.4 t
- 1.3 t
- 1.3 t
+ 2.5 t
+ 2.1 t
+ 8.9 t
Designation
O.D.
A
B
C
X
Y
Z
508
508
273
457
610
610
Calculated
thickness
ASME
10.05
10.05
4.70
2.12
26.35
26.35
Calculated
thickness
EN
8.69
8.69
4.59
2.24
28.91
28.91
Weight difference
(EN ASME)
-0.22 t
-0.69 t
-0.06 t
+0.09 t
+ 0.45 t
+ 1.18 t
Page 5 of 18
ASME Formula
Thickness = (P * D ) / (2* f + P )
The formulas output are identical when Y =0.5; meaning at 510C. Below 480C, the
formulas lead to the same thicknesses when MAS-f = 0.1 P, and above 540C, when MAS-f
= - 0.2 P. Even at high pressure (110 bar g), it means MAS-f= 1.1 and -2.2 MPa respectively.
This is negligible compared to the design stresses admitted.
Figure 4
Page 6 of 18
Figure 5
Figure 6
Page 7 of 18
Figure 7
Globally, calculated thicknesses can be summarized as indicated in Table 5 here below:
Material
Useful zone
100C/400C
Pipes thinner
with EN
100C/240C
Pipes thinner
with ASME
240C/400C
SA106B or
EN10216-2/P265GH
SA335P11 or
EN10216-2/13CrMo4-5
SA335P22 or
EN10216-2/10CrMo9-10
SA335P91 or
EN10216-2/X10CrMoVNb91
300C/525C
300C/525C
n.a.
400C/570C
400C/540C
540C/570C
500C/600C
500C/600C
n.a.
Page 8 of 18
The design code does not much influence pipe routings, except possibly for piping around
control valves. Control valve suppliers, which are usually working according to ASME code,
proposes valves which are straight in-line type. Other suppliers, which are usually working
according to DIN standards, usually offer control valves based on angle or Z types, even if
they can propose sometimes straight in-line type also. This can lead to very different pipe
routings, as shown on Figure 8. That has little impact on the pipe length and weight, but this
can hold the designer at the early project phase, as the valve supplier is not selected yet, and
no detailed drawings are available.
Page 9 of 18
7. Pipe fittings
Regarding pipe fittings, there is a big difference between ASME and EN codes because:
-
EN 12952-3 does not allow socket welding above 20 bar G or 350C. Even if socket
could still be use on the LP circuit, CMI decided to apply full penetration weld for all
welds.
CMI has developed a catalog of EN fittings, based on butt weld ends (Figure 9), to be
manufactured according to specific design conditions and drawings. This applied solution is
more expensive than ASME standard fittings out of the shelf, but this is necessary for piping
design according to EN code. Otherwise reinforcement pads must be used locally.
For low pressure carbon steel piping, we have identified that some fittings can be up to 10
times more expensive to source in EN. However, for high pressure alloyed steel piping like
P91, prices of fitting are comparable.
Page 10 of 18
8. Drum design
For this particular project, the HP drum was manufactured in SA302 GrB material, resulting
in a calculated drum thickness of 114 mm. For the EN version of this boiler, CMI selected the
material EN 10028-2/15NiCuMoNb5-6-4. Currently, this material has no equivalent in
ASMEI. Although more expensive, it is more resistant. The calculated thickness was only 75
mm in EN, instead of 114 mm in ASME. It is to be noted that this material is well known by
CMI, as its DIN equivalent has been used for numerous HP drums fabricated in CMI
workshops. Also, this EN 10028-2/15NiCuMoNb5-6-4 requires special welding procedure.
Regarding IP and LP drums, plate thicknesses were the same, as material selected was EN
10028-2/P295GH equivalent to SA516 Gr70. Also, let us note that EN 12952-7 requests that
the internal side of the shell must remain visible for inspection. Consequently, the standard
design of drum internals was adapted.
Page 11 of 18
The sensitivity and the probabilistic nature of fatigue results in an uncertainty in fatigue
lifetime analysis. Some uncertainties come from simplified the Stress Induced Factors.
Compared to the former TRD301 German code, from which this EN part is derived largely,
finite element analysis can be used to determine SIF. Euro Norm appears to be less
conservative than its former TRD 301.
Fig.10 Whler curve from EN 12952-3 showing material fatigue for symmetric stress range
(amplitude fa) versus allowable number of cycles Na for various material tensile strength Rm.
Page 12 of 18
EN fatigue analysis is applied to thick HP drum walls, to outlet headers of reheater and HP
superheater. An interesting point is the ramp rate variation versus operating pressure (Fig.
11): as pressure increases, the allowable pressure ramp rate also increases. As noted, the
allowable gradient can be optimized as pressure is building up. These calculated
temperature/time gradients are converted into pressure/time gradients as these are more
accessible and controllable parameters during transients. This feature is used to optimize the
start-up by applying progressive pressure ramp rates (Fig. 12), which allows optimisation of
the overall boiler start-up time, without consuming any extra lifetime of the boiler. Such
progressive pressure gradients are implemented into the plant DCS as set points applied on
the HP steam turbine by-pass valve.
Fig. 12 Optimized pressure gradients set points resulting from application of EN 12952-3
Regarding the on-off valves, EN12516 proposes two methods for valve selection:
-
a calculation method similar to DIN 3840, for which the designer must calculate the
wall thickness.
Page 13 of 18
Table 6 shows a typical table which can be found in the tabulation method. Ratings are noted
as Bxx (similar to PNxx in DIN), or as CLxxx (similar to ANSI). Ratings can be standard or
special ratings, and materials are presented by groups (Table 6 features group 1C1).
Some groups are specially devoted to ASTM materials, and some other groups are devoted to
EN materials. As the EN12516-1 gives wall thicknesses close to those of ASME B16.34, it is
easy for valves suppliers to switch from ASME to EN codes.
EN give much more flexibility in valve selection than ASME code does. As an example, there
are up to four different body lengths for each valve. In practice, the valve manufacturer selects
one of the allowed lengths, as available. As the valve suppliers will be selected in due course
of project execution, isometric pipe drawings are initially drawn with the maximum valve
lengths, in order to avoid interferences. Once valves are ordered, isometric drawings are
updated, and the requested pipe material is checked to avoid any shortage for pipe spools.
Page 14 of 18
based on safety valves, which can either be spring loaded (similar to ASME), or
assisted, or supplementary loaded , or pilot operated.
without safety valves, using a Controlled Safety Pressure Relief System (CSPRS).
When using one of the three first safety valve types, at least 75% of the required discharge
capacity must be on drum and the rest at superheater outlet; when using the pilot operated
safety valves or CSPRS, at least 25% of this capacity must be on the drum, or even 0% if at
least one pressure signal is transmitted to the control unit from the drum. This means that the
HP safety relief valves can be replaced by a secured steam by-pass between HP circuit and
cold reheat line. This design is quite common with the DIN design, and expected by German
plant operators. It has the advantage of removing safety valves on the HP drum and HP
superheater, but needs a secured bypass, with a local sophisticated hydraulic enclosure. As the
assumption of failure in the supply of desuperheating water must be considered, the design of
the cold reheat line must include the possibility of temporary high temperature.
Page 15 of 18
Page 16 of 18
Type of connection
Heat exchangers:
Tube to header( tube thk<5 mm)
EN requirements
ASME requirements
No requirement
10% UT or RT
No requirement
( but CMI req.: 10% RT or UT )
88.9x5.49 (SA335P11)
No requirement
273 x10
100%(MT or PT) + 10%(RT or
UT)
273 x 9.27
No requirement
457 x 12.5
100%(MT or PT) + 10%(RT or
UT)
610 x 25(X10CrMoVNb9-1)
(EN12952)
100% MT + 100% UT)
219.1 x 22.2
100%(MT or PT) + 10%(RT or
UT)
355.6 x 36
100%(MT or PT) + 10%(RT or
UT)
355.6 x 35.71
100%(UT or RT)
323.9 x 32(X10CrMoVNb9-1) (
EN12952)
100% MT + 100% UT
No requirement
Drums:
-Longitudinal and circumferential
welds:
-15<e<25(full penetration ):
100% MT (+10% UT if
dia>142mm )
-e<15 :
10%MT
Page 17 of 18
14. Conclusions
Following this detailed comparison study on a recent HRSG design, we can conclude that the
most significant differences between EN and ASME design codes are as follows:
1. Both EN and ASME codes resulted in similar pressure parts and piping weights.
2. Compared to ASME code, EN allows to calculate pressure parts in more details. EN
provide therefore further possibilities for boiler optimisation. In particular, finite
element analysis is more broadly used on EN.
3. Compared to ASME, the HP drum thickness is much lower on EN. As such, pressure
gradients and cycling capabilities of EN boilers are enhanced compared to ASME.
4. Euro Norm shows that allowable pressure gradient varies with pressure. Therefore,
boiler start-up time can be optimized without consuming fatigue lifetime by using
progressive pressure gradients. This interesting feature, derived directly from a fatigue
analysis, is used by CMI on a standard basis even for ASME boiler
5. Unlike ASME code, EN allows to use by-pass systems as safety devices, giving more
plant operation flexibility, while saving safety valves and associated costs.
6. Unlike ASME, EN fittings must be designed and manufactured for specific pipe cases.
7. Valves sourcing for EN code is more difficult than ASME, because numerous valve
suppliers are not yet ready to supply valves according to EN. Consequently, EN valves
are more expensive than ASME valves.
Compared to ASME code, and based on the same boiler performances, the EN design is
currently about 3% more expensive, and the project planning is extended by about 2 months
longer. However, this difference tends to reduce. EN is a more sophisticated code, which
allows further design optimisation, and providing greater flexibility in plant operation.
As HRSG designer, CMI can design and supply equally according to either ASME or EN.
15. References
[1] Euro Norm NBN EN 12952, February 2002 Water-tube boilers and auxiliary
installations, design and calculation for pressure parts
[2] ASME Boiler and Pressure Vessel Code Section I and Section VIII, Rules for
construction of Pressure Vessels, ASME, New York , 2001 Edition , 2002 Addenda
[3] TRD 301 Code, April 1979, Zylinderschalen unter innerem Uberdruck
[4] HRSG optimization for cycling duty based on Euro Norm EN 12952-3, Power Gen
2007, Jean-Franois Galopin and Pascal Fontaine
Page 18 of 18