Professional Documents
Culture Documents
Cash Flow Forecasting 29th October 2015f
Cash Flow Forecasting 29th October 2015f
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Profit margin could be uniform on all items of contract or varying for different items.
In a front loading strategy, profit margins are kept more on early items like foundations
and structural works to improve positive cash flow.
Dr. V. Thiruvengadam
Profit
Cost
Cumulative
Cost
Dr. V. Thiruvengadam
Value
Cost
Cost
Period
Dr. V. Thiruvengadam
Total Cost
Material
Cumulative Costs
Labor
Equipment
Subcontractor
Project Period
Dr. V. Thiruvengadam
Costs
Cost histogram represents the cost incurred during specified intervals (weekly
or monthly) over the project period.
The cumulative costs at specified intervals are obtained as sum of the previous
costs and the cumulative cost profile is developed. The end point of cumulative
cost profile is the project total cost.
Costs
100
500
400
300
200
50
0
M1
M2 M3 M4
M5
M6
M7
100
0
0 M1 M2 M3 M4 M5 M6 M7 M8
M8
Cost Histogram
Months
M1
M2
M3
M4
M5
M6
M7
M8
Monthly Costs
50
60
70
80
60
50
40
20
Cumulative Costs
50
110
180
260
320
370
410
430
Dr. V. Thiruvengadam
Project S-curve
% Cumulative Costs
120
100
80
60
40
20
0
2/3T
1/3
T Time Period
Dr. V. Thiruvengadam
% Cumulative Costs
Project S-curve
120
100
80
60
40
20
0
1/3T
2/3T
Time Period
The shape of S-curve could vary depending upon the project characteristics.
Construction types using prefabrication technology involve more costs in the
initial fabrication period compared to installation costs in the later period.
Dr. V. Thiruvengadam
Project S curve
Example problem on S-curve
90
80
20
70
60
60
50
40
30
80
40
% Cumulative Costs
80
20
20
20
10
Period
Months
Monthly Costs
10
10
20
20
10
10
Cumulative Costs
Dr. V. Thiruvengadam
20
60
80
Project S curve
% Cumulative Costs
Use of S-Curve
120
100
80
60
40
20
0
2/3T
1/3
T Period
Standard S-curves are used for obtaining approximate the cash forecasts during
the early stages of the project like feasibility studies, tendering stage.
Cash flow forecasting of different types of projects like offices, residences,
factories, roads and bridges developed from the cost data of past projects for
usage in the early stages of similar new projects.
Dr. V. Thiruvengadam
Adverse situations (risks) that may occur on cash flows needs to be evaluated to
predict the impact of these risks on the financial outcome of the project.
As lenders of money, financial institutions carry out detailed appraisal on the
projected cash flow of the project to evaluate and decide on financing
Financial viability
Ability to pay the interest and repay loan
Adequacy of equity contribution by borrower (debt-equity ratio)
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
2.
3.
4.
5.
6.
Site not clear for taking up of the construction (work awarded in anticipation of
clear site availability)
7.
Dr. V. Thiruvengadam
2.
Prepare the project schedule in the form of bar chart with activity listings and
durations. Schedules prepared using network techniques are consolidated in bar chart
formats.
3.
Determine activity costs from the itemized costs available in the bill of quantities. One
or more item costs may constitute an activity cost. A raft foundation activity will involve
items of reinforcement, shuttering and concreting items.
4.
Determine the proportional costs that are expended per unit duration (per month) of
an activity. For some activities the expenses may not be in a linear proportion over the
activity duration. Such breakup of activity cost within its duration is important for
activities which consume more resources/ cost in the early part and less cost in the
later part of the activity duration. For example activities involving procurement and
installation of electrical/ mechanical works involve more cost for procurement and less
cost for installation. In such cases it may be better to keep procurement and installation
as separate activities.
Dr. V. Thiruvengadam
For expenses towards overhead charges, the total cost under this subhead may be
distributed equally over the project periods.
6.
Calculate the monthly (or any other unit period) cost expenditure of the project by
summing up the cost expenditure of different activities during the month under
consideration. This means sum the portions of activity costs of different activities
incurred during each monthly interval of the project. These monthly costs are
shown in the first row of the table at the bottom of the bar chart. Calculate the
cumulative monthly costs and show in the second row of the table. (See Fig).These
calculations could also arranged in excel format.
7.
If the value of the activities (which is based on item wise contract cost which
includes profit margin) is used for the generation of cumulative value of works in a
similar manner described above, then cumulative cost of work is obtained by using
the relation:
Cumulative cost = cumulative value/(1 + percentage profit in decimal)
Dr. V. Thiruvengadam
Having calculated the period wise (monthly) cumulative value and cumulative cost
of the work over the project period, the remaining calculations for determining
the monthly cash inflows due to receipts, outflows due to disbursements and
cumulative net cash flow could be worked out in a excel sheet format
incorporating the following details;
9.
The above steps completes the procedure of developing the cash flow forecasting
of a construction project for a contractor. The above procedure enables
determination of working capital requirements, profitability, assessment of impact
of risks like delayed payments from the client.
Dr. V. Thiruvengadam
Row 3Enter receipts of monthly payments less retention money with respect to billing
cycle usually one month after the value of work executed.
Row 4Enter cumulative values of retention money received back, 50% one month after
end of project execution and balance 50%, 6 months after project execution (defect liability
period)
Dr. V. Thiruvengadam
Make suitable assessment of the labour cost as fraction of total cost (say 25%) paid at the
end of each month right from project starting month.
Row 8 Enter cumulative labour payment made
Row 9Enter cumulative material costs
Row 10 Enter cumulative material payment made
Make suitable assessment on the material cost component (say 50%) and decide on the
payment to material supplier (say one month after the receipt of the payments from the
client)
Row 11Enter cumulative equipment component (say 15%) and payment cycle similar to
material supplies
Row 12 Enter cumulative equipment component payment made
Row 13Enter cumulative subcontractor cost (say 15%)
Row 14 Enter cumulative subcontractor payment made
Cash Flow
Peaks due to
release of
retention
money
Negative cash
flow period
Dr. V. Thiruvengadam
Positive cash
flow period
Project Period
Profit
Row 12The difference between row 10 (cash inflow) and row 11 (cash outflow) provides
the net cash flow.
Cumulative Value
1.15
2.88
5.75
8.63
11.50
14.38
17.25
1.035
2.587
5.175
7.762
10.35
12.937
1.035
2.587
5
5.175
7.762
5
10
11
12
13
14
15
16
17
18
23.00
28.75
30.48
31.05
31.63
31.63
31.63
31.63
31.63
31.63
31.63
15.525
20.7
25.87
27.427
27.945
28.462
28.462
28.462
28.4625
28.4625
28.4625
28.4625
12.9375
15.52
5
20.7
25.875
27.4275
27.945
28.4625
28.463
28.463
28.463
28.463
28.463
1.581
3.162
1.035
2.587
5.175
7.762
10.35
12.937
15.52
20.7
25.875
27.427
27.945
30.043
28.463
28.463
28.463
28.463
31.625
Cumulative Cost
1.00
2.50
5.00
7.50
10.00
12.50
15.00
20.00
25.00
26.50
27.00
27.50
27.50
27.50
27.50
27.50
27.50
27.50
0.250
0.625
1.250
1.875
2.500
3.125
3.750
5.000
6.250
6.625
6.750
6.875
6.875
6.875
6.875
6.875
6.875
6.875
0.250
0.625
1.250
1.875
2.500
3.125
3.750
5.000
6.250
6.625
6.750
6.875
6.875
6.875
6.875
6.875
6.875
6.875
0.400
1.000
2.000
3.000
4.000
5.000
6.000
8.000
10.00
10.600
10.800
11.000
11.000
11.000
11.000
11.000
11.000
11.000
10
11
12
13
14
15
16
10.35
0.400
1.000
2.000
3.000
4.000
5.000
6.000
8.000
10.000
10.600
10.800
11.000
11.000
11.000
11.000
11.000
11.000
0.200
0.500
1.000
1.500
2.000
2.500
3.000
4.000
5.000
5.300
5.400
5.500
5.500
5.500
5.500
5.500
5.500
5.500
0.200
0.500
1.000
1.500
2.000
2.500
3.000
4.000
5.000
5.300
5.400
5.500
5.500
5.500
5.500
5.500
5.500
0.150
0.375
0.750
1.125
1.500
1.875
2.250
3.000
3.750
3.975
4.050
4.125
4.125
4.125
4.125
4.125
4.125
4.125
0.150
0.375
0.750
1.125
1.500
1.875
2.250
3.000
3.750
3.975
4.050
4.125
4.125
4.125
4.125
4.125
4.125
0.250
1.375
3.125
5.625
8.125
10.625
13.125
16.25
21.25
25.375
26.625
27.125
27.500
27.500
27.500
27.500
27.500
27.500
-0.250
-0.340
-0.538
-0.450
-0.363
-0.275
-0.188
-0.725
-0.550
0.500
0.803
0.820
2.544
0.963
0.963
0.963
0.963
4.125
example
35.00
Fund Requirement
based on Negative
Cash flow
30.00
= area of graph of
negative cash flow
region
25.00
20.00
= average vertical
coordinate x base
15.00
= .409 X 8 =
Rs.3.27lakhs
10.00
5.00
0.00
1
10
11
12
13
14
15
16
17
-5.00
Cumulative Value
Cumulative Cost
Cumulative Cash (Net) flow (3+4-14)
18