PREPARED BY:
Rizal Z. Ismail
DATE:
04 February
2015
REVIEWED BY:
APPROVED BY:
Adi WIbowo
DATE:
DATE:
This document is exclusively property of HUAWEI Technologies. Co., Ltd. and shall
not be used copied or communicated to the third party without its prior authorization.
Contents
1
Description of Change
1.1
Description of Site
1.2
Purpose
1.3
Description of Change and Change Influence
Preparations for Change
2.1
Change Period
2.2
Composition of Change Team and Responsibility of Team Members
2.2.1 Change Team of Customer
2.2.2 Huawei On-site Change Team
2.2.3 Huawei Support & Guarantee Team
2.3 Check of Equipment Running
2.4
Change Risks and Countermeasures
2.5
Check Before Change
Operation Steps for Change
3.1
Change Steps
3.1.1 Overall Description
3.1.2 Operation Steps for Change
3.2
Test and Verification
3.3
Solution for Change back In the Case of Failure
3.3.1 Definition of Change Failure
3.3.2 Overall Description of Changeback
3.3.3 Information Collection Before Changeback
3.3.4 Changeback Steps
3.3.5 Equipment Status Check
3.3.6 Tests After Changeback
3.3.7 Changeback Risk Analysis
3.4
Change of Spare Parts and Emergency Workstation
Work After Change
4.1
Observation
4.2
Provision of Materials
4.3
Provision of Software
4.4 Training
4.5
Matters Needing Attention
Page 2 of 9
1 Description of Change
1.1
Description of Site
1.2
Purpose
Enhanced SlotFormat D10 FACH Expansion
1.3
Page 3 of 9
Change Period
The change period is from 2015/02/10 (Each batch change operation will follow below
steps)
1. Make CR to MS Huawei and get approval from HCPT.
2. Script Execute by OSS team after CR being approved 00:00-01:00, 10 feb 2015
(script attached).
3. Ensure no cells down after activity using command DSP Ucellchk.
4. In above step, if problem, execute the roll back plan
2.2
Position
Name
Site
Company
Phone
Responsibility
Supervisor
name
PIC
Rizal
Z.
Supervisor
Phone
Metrotel
089689026583
Performance
Ismail
Adi
089621674311
WIbowo
Position
Name
Site
Company
Phone
Responsibility
Supervisor
name
Joel
Julian
Supervisor
Phone
Huawei
089603003760
Performance
Adi
089621674311
WIbowo
Siadari
Page 4 of 9
Engineer
On site
MS
NOC/configration
Supervisor
Adi
Vendor
Wibowo
Huawei
089621674311
Performance
Responsibility
Telephone No.
Gunawan Hendro
089639437829
expert
2.3
Risk Description
Possibility
Impact
(High/Middl
(High/Mi
e/Low)
ddle/Lo
Countermeasure
w)
1
low
low
DSP UCELLCHK
Network Problems
Avoid Issue &
Precautions
Checking
2
Impact on NEs
low
low
Risk in change
low
low
duration
Page 5 of 9
2.5
No.
Owner
Completion Date
Ima Erma
Before execution
of failure
Change Steps
Overall Description
HW_BSS3G_FACH_C
S Region_Enhanced SlotFormat D10 FACH Expansion_20150204.xlsx
3.1.2
No.
Change Step
Operation
Implementation
Time
Person
1
NodeB Check
NPM Team
Before
execution
Precautions
Checking(DSP UCELLCHK)
2
Service
verification
CR Status
Check CR Status
H3I/MS Huawei
04 February 04
February 2015
OSS 3G
After CR
submitted
Script Execution
OSS 3G
09:00 19:00,
04 February 04
February 2015
Page 6 of 9
NodeB Down
OSS 3G
After execution
OSS 3G
After execution
Check
7
Closing CR
3.2
Operation Item
Operation Method
Owner
Time
Check
Main KPI
NPM
Performance
3.3
3.3.1
A change failure shall be recognized if the following major problems cannot be resolved
before 4:00 a.m. (within the stipulated period of time) and back-off operations shall be
finished.
(1) Have additional alarm after
(2) Hardware failures
(3) Frequent breakdown
(4) Main KPI degrade very badly
Page 7 of 9
3.3.4
Changeback Steps
execute the roll back plan
3.3.5
Observation
Main Task
Responsibility
Time
NPM Team
1 days after
execution
NPM
1 days after
execution
4.2
Provision of Materials
N/A
Page 8 of 9
4.3
Provision of Software
N/A
4.4
Training
N/A
4.5
Page 9 of 9