You are on page 1of 1

80.

1:2:4(1cement:2coarsesand:4gradedstoneaggregate20mmnominalsize).

Code

Description

Unit

Quantity

Rate

Amount

Detailsofcostfor1cum.
MATERIAL:
0295

StoneAggregate(singlesize):20mmnominalsize

cum

0.67

1700.0

1139.0

0297

StoneAggregate(singlesize):10mmnominalsize

cum

0.22

1750.0

385.0

0982

Coarsesand(zoneIII)

cum

0.445

4950.0

2202.75

0367

PortlandCement(0.2225cum)
LABOUR:

tonne

0.32

8800.0

2816.0

0155

Mason(average)

Day

0.1

900.0

90.0

0114

Beldar

Day

1.63

240.0

391.2

0101

Bhisti

Day

0.7

760.0

168.0

0002

HirechargesofConcreteMixer0.25to0.40cum
withHopper

Day

0.07

2400.0

168.0

0012

Vibrator(Needletype40mm)

Day

0.07

500.0

35.0

TOTAL

7394.95

Costof1.0cum

7394.95

Say

7394.95/

Skilled

0.0

UnSkilled

391.2

SemiSkilled

258.0

Materials

6542.75

TotalAmount(ExcludeCPOH&WaterCharges)

7394.95/