1:2:4(1cement:2coarsesand:4gradedstoneaggregate20mmnominalsize).
Code
Description
Unit
Quantity
Rate
Amount
Detailsofcostfor1cum.
MATERIAL:
0295
StoneAggregate(singlesize):20mmnominalsize
cum
0.67
1700.0
1139.0
0297
StoneAggregate(singlesize):10mmnominalsize
cum
0.22
1750.0
385.0
0982
Coarsesand(zoneIII)
cum
0.445
4950.0
2202.75
0367
PortlandCement(0.2225cum)
LABOUR:
tonne
0.32
8800.0
2816.0
0155
Mason(average)
Day
0.1
900.0
90.0
0114
Beldar
Day
1.63
240.0
391.2
0101
Bhisti
Day
0.7
760.0
168.0
0002
HirechargesofConcreteMixer0.25to0.40cum
withHopper
Day
0.07
2400.0
168.0
0012
Vibrator(Needletype40mm)
Day
0.07
500.0
35.0
TOTAL
7394.95
Costof1.0cum
7394.95
Say
7394.95/
Skilled
0.0
UnSkilled
391.2
SemiSkilled
258.0
Materials
6542.75
TotalAmount(ExcludeCPOH&WaterCharges)
7394.95/