Professional Documents
Culture Documents
2005
Article 1038
c
Copyright
2005
by the authors. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic,
mechanical, photocopying, recording, or otherwise, without the prior written permission of the
publisher, bepress, which has been given certain exclusive rights by the author. International Journal of Emerging Electric Power Systems is produced by The Berkeley Electronic Press (bepress).
http://www.bepress.com/ijeeps
Reshmi M
Abstract
Fixed shunt reactors are traditionally used in long distance EHV and UHV lines to reduce
Ferranti over voltages and over voltages that arise due to load rejection. A new equipment called
Controlled shunt reactor (CSR) has been developed [3] and [4]. Detailed load flow and voltage
stability analysis on a typical 400KV interconnected network prove that replacement of fixed shunt
reactors with CSR is beneficial. This study report is an attempt to justify and quantify the economic
and technical benefits of CSR in a 400KV system
KEYWORDS: Compensation, economics, EHV transmission lines, impedance transformers, interconnected power systems, load flow analysis, reactive power, thyristors, voltage collapse, power
system dynamic stability
The authors express their sincere thanks to Mr. R.K Bhattachaya GM (EM) and Mr.M.P Soni
AGM (TPS) of Corp. R&D, BHEL for encouraging us to carrying out this work. The authors
thank the management of Corp. R&D, BHEL. for giving permission to publish this paper. The
authors also thank Dr. Federico Milano, University of Waterloo for his timely clarifications for the
technical queries.
1.0 Introduction
In India 400 kV transmission was introduced in 1971-72. The first two lines
were Obra-Sultanpur and Dehar-Panipat in Punjab. These long lines were
provided with Fixed Shunt Reactors (FSR) to control over voltages during
line energization and light load conditions that prevailed for longer duration
during the initial period. By 2001, the 400kV network has grown over 42000ckt km. More than th of the lines are compensated with FSRs to 60% of
their charging capacity. The total shunt reactor capacity connected in the
grid was around 10,500 MVAR. The grid was catering to a load of
65,000MW and 39,000 MVAR of reactive power. Permanent connection of
10,500 MVAR shunt reactor capacity was taking the total MVAR load close
to 50,000 MVAR. Today, the above figures could have reached higher levels.
This additional burden of reactive load under peak load conditions results in
reduced voltage profile and additional losses due to increased currents in the
net works. Higher losses and reduced voltage profile also indicate higher
reactive power requirement from generators forcing them to operate nearer to
their reactive power limits. In order to meet this higher reactive power
demand, the generator excitation voltages are kept higher increasing the
possibility of higher dynamic over voltage under sudden load rejection. The
possibility of a voltage collapse also increases in the grid due to sudden loss
of a line with permanently connected reactors in the grid.
Recent blackouts reported in the WREB have drawn the attention of the
power system community in the country. One important inference from these
events was that the grid was short of reactive power support and with
increased load conditions have led to considerable low voltages. The low
voltage trips have virtually split up the grid into two parts. One with more
generation and light loads, and another with weak generation and heavy
loads. The subsequent trips occurred due to low/over voltages and resulted in
total system blackout. Prior to the blackout the grid was experiencing poor
voltages due to increased agriculture loads. Voltages prevailing before the
blackout in some parts of the western grid are shown below.
Station
Indore
Nagda
Satpura
Dhule
Asoj
Voltage(kV)
321
325
367
380
370
Station
Itarsi
Bina
Bhopal
Parli
Kalwa
Voltage(kV)
371
367
355
379
395
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
The recent three blackouts on 6/10/03, 5/11/03 and 7/11/03 were due to low
voltage problem prevailing in the region. The poor voltage profile continues
to prevail causing serious insecurity in the grid. The capacitors already
installed are quite inadequate and that the presently available capacitors have
not come to the rescue of improving the voltages to the desired level. Large
quantum of MVARs is drawn from the grid causing large depression in the
voltages, which is not at all conducive to healthy grid operation.
This situation clearly indicates lack of proper reactive power support, which
can be improved considerably by providing the same. Another important
observation is that the low voltage situation occurred while lines were
carrying power much lower than the natural capacity. The immediate
remedial suggestion could be to install capacitor banks or static var
compensation. Implementation of this suggestion calls for detailed system
analysis and large investments, which may take considerable amount of time
and effort. A significant issue, which has come for discussion during these
disturbances, is the role of shunt reactors in the 400kV system. It is
noteworthy that almost all the shunt reactors connected in the lines and buses
were in operation during the moments of crisis. Definitely, existence of these
reactors must have played a detrimental role leading to deterioration of
system voltages. There is a suggestion that shunt reactors are to be switched
off during such crises. But by permanently removing the shunt reactors, over
voltages may develop during light load conditions leading to grid
disturbance.
2.0 Role of Shunt Reactors and Proposed Application Criteria
During the early 70s when 400kV transmission was introduced, there were
some trials to use breaker controlled shunt reactors. Due to the inherent
problems involved in reactor switching and also due to lack of suitable
breakers it was decided to use permanently connected shunt reactors for line
compensation. In the initial days of 400kV grid, as the lines were lightly
loaded, the 60% permanent compensation of line charging capacity was not
imposing any limitations.
The 400kV network has become the main constituent in the national grid
today. The dependency on 400kV grid for transmission of power to load
centers from the remote generating centers has increased. In this context,
maintenance of healthy voltages, maximum power transfer capacity,
increased voltage stability margin and reduced line losses in the 400kV grid
assumes maximum importance. With the backdrop of recent black outs it is
http://www.bepress.com/ijeeps/vol2/iss1/art1038
necessary to redefine the guidelines for the use of shunt reactors for line and
bus applications.
1.A shunt reactor connected at either ends of the line (line reactor) should not
remain connected on permanent basis. The line reactor should be in circuit
during line energization, during light load conditions and when the line
voltage is above the permissible limit.
2.The line reactor should get disconnected as the loading of the line increases
or when the steady state line voltage decreases below the permissible limit.
3.The line reactor should be able to protect the line and associated equipment
from possible over voltages that may occur due to sudden load throw off
conditions.
4.A line reactor should facilitate successful auto reclosure during single line
to ground fault conditions.
Under the present conditions of the Indian grid, Controlled Shunt Reactor
(CSR) will be an ideal choice of equipment. CSR will provide the necessary
reactive power support to the lines during line energization and during
sudden load rejection. During full load and reduced voltage conditions CSR
cuts itself out of circuit. In simple words CSR is a switchable reactive load
which will come into the circuit only when it is required thus eliminating the
unnecessary permanent burden on the grid.
3.0 Principle and Implementation
The principle behind the CSR is to control the reactive current of the shunt
reactor by using a thyristor valve, which can provide the necessary speed of
switching and control by means of firing angle control. It is not practical to
use a thyristor valve at transmission voltage levels and the concept of a
reactor transformer with primary winding connected to high voltage side and
a secondary (control) winding suitable for connection of a thyristor valve
forms the basis for CSR. In other words, CSR is a high impedance
transformer controlled by an anti parallel pair of thyristors (valve) on the
secondary side at a suitable voltage level. The impedance of CSR can be
controlled by varying the firing angle of the pair through a Controller.
CSR can be controlled to vary reactive power consumption anywhere
between zero to its full capacity by varying the firing angle of the thyristors.
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
400kV line
Reactor
transformer
Thyristors
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
installed at only one end of the line and that Itarsi bus has a very high short
circuit level, where only one reactor is converted into CSR out of a total of
eleven.
d) CSR has operated in AUTO mode with ON/OFF control successfully
responding to the voltage variations.
e) A single line to ground fault (SLG) was simulated by momentarily
removing feedback of one of the phase voltages to the controller. The CSR
came into full conduction within the planned response time.
f) Continuous control mode was also tested with manually changing the
firing angle from full conduction to zero conduction. The reactive power at
each of the firing angles was noted. It was found to be varying smoothly with
the firing angle from full MVAR to zero.
g) CSR is functioning without any operational problems. It does not require
any operator intervention during normal operation and comes in and goes out
of circuit at the set limits automatically.
CSR provides reactive power support depending on the bus/line voltage
levels. At Itarsi an upper voltage limit (UVL) of 415 kV and a lower voltage
limit (LVL) of 400kV were set. Depending on the voltage condition CSR will
be operating. The ON and OFF times are continuously logged. Fig.2 depicts
the operation pattern of CSR in the year 2002-03. The graph shows percentage
time for which CSR has been providing the 50 MVAR reactive power support
based on the prevailing voltage condition. On the contrary, a fixed shunt
reactor will be continuously in circuit resulting in drop in voltage as well as
higher equipment and line losses. CSR was in circuit for an average period of
10.85% of time during a year.
n,
03
Ja
ov
,0
2
Se
p,
0
ly
,0
2
Ju
,0
ay
M
ar
ch
,0
2
40
30
20
10
0
TIME
IN CIRCUIT % OPERATING
C S R O P E R A T IO N 2 0 0 2 -0 3
M O NT H & YEAR
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
http://www.bepress.com/ijeeps/vol2/iss1/art1038
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
TABLE I
VOLTAGE PROFILES AT
Load Bus
Bus C
Bus E
Bus F
Bus G
Bus H
Bus I
Voltage(kV)W
ith all the
reactors in
circuit
405.85
352.80
361.62
336.00
347.76
375.00
DIFFERENT
LOAD BUSES
Voltage(kV)Wit
h all the
reactors
removed
409.00
376.70
378.00
359.00
365.40
386.00
Voltage(kV)
With reactors
removed at
strategic
locations
406.00
361.00
367.90
344.40
355.70
377.60
In the above case at Bus G for example, the voltages have improved from
336kV to 344.4kV which is about 8.4kV increased voltage, with and without
reactors at strategic locations respectively.
6.2 Increased Loadability of Lines
PV curves of different load buses are obtained using continuation power flow
method for the voltage stability analysis. These curves are used to determine
the maximum loading point (MLP), the maximum power transfer among
system areas, the voltage stability indices, and to compare planning strategies.
Fig. 4. PV curves at all load Buses with all the reactors in the circuit
http://www.bepress.com/ijeeps/vol2/iss1/art1038
10
Fig. 5. PV curves at all load Buses with all the reactors removed.
L
O
A
D
V
O
L
T
A
G
E
S
V, pu
Fig. 6. PV curves at all load Buses with reactors removed at strategic locations.
In figure 4, PV curves at all the load buses are generated with all the reactors
remaining permanently connected in the circuit. It is evident that the maximum
loading of the system in this case is 1.087 pu. Removal of reactors at some
strategic locations increases maximum loading to 1.142 pu as shown in figure 5.
The maximum loading point further improves to 1.2537 pu with all the
permanently connected reactors removed as shown in figure 6. However,
keeping in view the dynamic voltages that may arise due to sudden load throwoff or line outages, utilization of CSR is recommended as a replacement for
permanently connected shunt reactors.
11
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
Load
Buses
Bus G
Bus H
Voltage
stability
index with
all the
reactors in
circuit
15.8
18.6
Voltage
stability
index with
all the
reactors
removed
16.8
19.6
Voltage
stability index
with reactors
removed at
strategic
locations
16.2
19.0
The voltage stability indices of Bus G and Bus H have increased with the
removal of reactors which indicate that the bus has moved away from the
voltage instability or voltage collapse.
The Fig.7. below shows the PV curves under different conditions at Bus G. The
curves clearly illustrate the improvement in the voltage stability margin.
6.4 Reduced Transmission Losses
In the above study, transmission loss analysis is done which shows that the
transmission losses of the system with all the reactors remaining permanently
connected is reduced from 0.0937 pu (93.7MW) to 0.08277pu (82.77MW) with
all the reactors removed from the system. Similarly, the transmission losses are
reduced from 0.0937pu (93.7MW) to 0.08933 pu (89.33 MW) removing 4
http://www.bepress.com/ijeeps/vol2/iss1/art1038
12
13
International Journal of Emerging Electric Power Systems, Vol. 2 [2005], Iss. 1, Art. 1038
http://www.bepress.com/ijeeps/vol2/iss1/art1038
14
Authors
S. V .N ..Jithin Sundar is a Deputy General Manager with Corporate Research
& Development Divn Bharat Heavy Electricals Limited, Vikas nagar,
Hyderabad, India (e-mail: jithin@bhelrnd.co.in).
M. Reshmi. is a post graduate student of power engineering, JNTU presently
under training at Corp.R&D, Bharat Heavy Electricals Limited, Vikas nagar,
Hyderabad, India (e-mail: reshmimehboob@yahoo.co.in).
References
[1] V. Ajjarapu, C. Christy, "The Continuation Power Flow: A tool for Steady
State voltage stability," IEEE Trans. Power Systems, vol. 7, No. 1, pp. 416423, February 1992.
[2] G. N. Alexandro, V. P. Lunin, Y. G. Selesney, L. N. Shifrin, S. V. N.
Jithin Sundar, S. C. Bhageria, C. D. Khoday , Amitabh Singhal, Fast-Acting
Controlled Shunt Reactor. Vii SEPOPE, MAY, 2003, Curitiba, Brazil.
[3] S. V. N. Jithin Sundar, S. C. Bhageria, C. D. Khoday , Amitabh Singhal ,
A. K. Tripathy, G. N. Alexandrov, M. M. Goswami, I. S. Jha, Subir Sen, V. K.
Prasher Controlled Shunt Reactor-A member of FACTS family Eleventh
National Power system Conference.(NPSC-2000), Bangalore. India.
[4] S. V. N. Jithin Sundar, S. C. Bhageria, C. D. Khoday, Dr. M.
Arunachalam, Amitabh Singhal, M. I. Khan, A. R. C. Rao, J. S. Kuntia, G. N.
Alexandrov, M. M. Goswami, M. Arunachalam, Design, Testing and
Commissioning of First 420kV, 50 MVAR Controlled Shunt Reactor in India,
14-120,CIGRE 2002, Paris.
[5] D. A. Alves, L. C. P. Da Silva, C. A. Castro,V. F. Da Costa, Study of
Alternative Schemes for the Parameterization step of the Continuation Power
Flow Method Based on Physical Parameters-part I:Mathematical Modelling,
Electric Power Components and Systems, vol. 31, no. 12, pp. 1151-1166,
December 2003.
[6] Report on Grid disturbances in Western region WRLDC, December
2003.
15