You are on page 1of 4

Cost Planning Exercise

Elemental Cost Comparison


Group Name
Building Type
Gross Floor Area
Contract Sum
/m2
Element
1 Substructure
2AFrame
2BUpperFloors
2CRoof
2DStairs
2EExternalWalls
2FExternalWindowsandDoors
2GInternalWallsandPartitions
2HInternalDoors
2 Superstructure
3AWallFinishes
3BFloorFinishes
3CCeilingFinishes
3 Finishes
4 Fittings and Furnishings
5ASanitaryAppliances
5BServicesEquipment
5CDisposalInstallations
5DWaterInstallations
5EHeatSource
5FSpaceHeatingandAirConditioning
5GVentilatingSystems
5HElectricalInstallations
5IFuelInstallations
5JLiftandConveyorInstallations
5KFireandLightningProtection
5LCommunicationsandSecurity
Installations
5MSpecialInstallations
5NBuilder'sWorkinConnection
5OManagementoftheCommissioningof
Services
5 Services
Building Sub-total
6ASiteWorks
6BDrainage
6CExternalServices
6DMinorBuildingWorks
6EDemolitionandWorkOutsidetheSite
6 External Works
7 Preliminaries

#DIV/0!

#DIV/0!

#DIV/0!

/m2 of Contract
Sum
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

/m2 of Contract
Sum
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

/m2 of Contract
Sum
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0

0
0
0

0
0
0

0
0

0
0
0
0
0
0
0

0
0

0
0
0
0
0
0
0

0
0

0
0
0
0
0
0
0

8 Contingencies
Total Contract sum
Check - should be zero

0
0

0
0
-1

0
0
-1

-1

Average

0
0
#DIV/0!
/m2 of Contract
Sum
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

#DIV/0!
/m2 of Contract
Sum
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0

0
0
-1

-1

You might also like