Agenda of Weekly meeting 24/7/2016

Technical
1. Last week work done
CY Indian
Carried out annual survey and management change.
Repaired VDR(renewed part : Battery, Acoustic beacon, USD backup drive)
CY Arabian
Repaired ACC deck AC(replaced compressor with new spare)
CY Pacific
Carried out annual survey, after repair VDR, will get SE cert from KR.
Ordered M/E turbo charger rotor 1set, nozzle ring 1pc from KMC.
Finished hull cleaning by JVS diving.
Renew split AC for galley.
Check refrigerator again, change thermostat.
Tugs and barges:
Best link deck maintenance completed
Uranus ADMATechncial observation has closedout.

CY Vessel
Ordered M/E turbo charger bearing 8sets, and nozzle tip 150sets
from Korea.
2. This week plan & safety issue
CY INDIAN: generator Alarm control panel need to be supply ,

CY Atlantic
Annual survey & Management change(Solas marine & SEAEX
marine)
Hull cleaning(JVS diving)
CY Arabian
Order M/E turbo charger rotor, nozzle ring & diffuser.
Tug & Barge
STI Pluto Fire alarm control panel repair
STI Jupiter Air con system cooling pump need to be order and
annual fire alarm test
certification need to do.