HYDERABAD METRO RAIL PROJECT

DISCIPLINE (CODE)

OETS

AECOM/LTMRHL/TRA/T/11950

AECOM/LTMRHL Transmittal
Number:
Document/Dwg No. / Review/Date:

HM-LE-ALLDEP-M0501-DOC-MS-TRA-01-001

Title of Document:

Procedure for mechanical interlocking of isolators in IBL & Manual wash areas

Document/Dwg No. / Rev:

HM-LE-ALLDEP-M0501-DOC-MS-TRA-01-001 . CR

LTC Current Transmittal No. / Date:

LTC/LTMRHL/TRA/TRANS/1675

22.07.2016

LTC Previous Transmittal No. / Date:

LTC/LTMRHL/TRA/TRANS/1617

08.02.2016

APPROVAL STATUS

SN.

0C1

10.02.2016

Level C

Reference

Employer's Comments

Approval
Status

Contractor's Response

1. Para 2.0 a) item IV: SS 28 is on IBL 4 and not IBL 3 in Uppal Depot.

Noted & Revised

2. Para 2.0 b) : SS 138 on IBL 4 is missing in MYP Depot.

Noted & Revised

3. Para 3.0: The para should specify as to which "key" is being talked
about, viz. the interlock / manual interlock/ pad lock key.

Noted & Revised

4. Para 3.0 c. Line 2: In place of "cancelling", it should be "completion"


and in place of "like", it should be "and".

Noted & Revised

5. Para 4.0 a): Instead of "lock", it should be "padlock".

6. A sketch showing the mechanical handle insert of the isolator, interlock


and padlock needs to be given.

Pictures attached againest the sketches which


shall serve the purpose.

7. The words, "For all practical purposes" need to be removed. Being


concerned with safety, the said keys must always be under the custody of
the PIC who takes the PTW.

Noted & Revised

Noted & Revised