D.G.

Building
Balance work as on date 15/12/2015
Sl. No.
1

Description of work
300 wide RCC drain at the periphery
Earth excavation
PCC (1:3:6)
Reinforcement work
Shuttering work
RCC (For raft & wall)

1 M. wide plinth protection all round


Earth excavation
75 thk bed of dry brick aggregate
M 15 grade concrete work

Ramp at north side ( 4 nos.)


Earth excavation
250 thk rubble soling (63 mm down size)
100 thk PCC
Brick work
Reinforcement work
Shuttering work
RCC

Aluminium glazed window fixing


Fixing Aluminium glazed window shutter (For W1 - 6 nos.)
Fixing Aluminium glazed window shutter (For W2 - 4 nos.)

Water proofing
Polystyrene block fixing
15 mm thk cement plaster
Elastometric membrane
Precast concrete tiles fixing

Inside painting (Acrylic distemper paint of approved make)


Wall
Ceiling

Exterior finishing / painting


Cement paint of approved brand

10

Door/Rolling shutter painting


Door painting (1 no.)
Rolling shutter painting ( 4 nos.)

lding
date 15/12/2015
Location/Level

Approx quantity
25 m3

G. L.

7 m3
0.85 M.T.
186 m2
18.75 m3

28 m3
G. L.

7.2 m3
9.6 m3

4.9 m3
7 m3
4.3 m3
G. L.

2.5 m3
0.3 M.T.
7.5 m2
4.8 m3

10.8 m2
36 m3

552 m2
Roof level

552 m2
552 m2
566 m2

780 m2
673 m2

1364 m2

Remarks

2.52 m2
56 m2