Balance work as on date 02/11/2015

Fuel Oil Tank area


Sl. No.
1

Description of work
RCC drain at the periphery of dike wall area
Earth dressing
PCC
Reinforcement work
Shuttering work
RCC (For raft & wall)

RCC drain at the periphery of fuel oil tank


Earth dressing
PCC
Reinforcement work
Shuttering work
RCC (For raft & wall)

Pedestal over grade slab area( for fuel oil pipeline)


Shuttering work
RCC (For raft & wall)

Balast laying for paving (inside dike wall area)

PCC for paving (inside dike wall area)

RCC for paving (inside dike wall area)


Reinforcement work
Concrete work

Dike wall with raft


Excavation
PCC
Reinforcement work
Shuttering work
RCC (For raft & wall)

date 02/11/2015
ank area
Location/Level

Approx quantity
35 m3

F. F. L.

5.25 m3
1.45 M.T.
210 m2
23 m3

1.9 m3
F. F. L.

1.8 m3
0.9 M.T.
144 m2
12 m3

F. F. L.

11 m2
2 m3

F. F. L.
F. F. L.

F. F. L.

114 m3
51 m3

5.8 M.T.
71 m3

122 m3
F. F. L.

3.6 m3
1.8 M.T.
161 m2
28 m3

Remarks