Professional Documents
Culture Documents
CHAPTER 2
Unless the development site has already been identified, it is necessary to roughly
examine (i) whether or not the construction of a small-scale hydropower plant near the
power demand area is feasible, and (ii) how much power generation capacity can be
secured and where, and then to select a potential site among the candidate sites.
The above examination is basically desk work using existing reference materials and
information and the procedure involved and important issues to note are explained
below.
- 2-1 -
Figure 2.1.1(a)
- 2-2 -
2.2
Range of Finding
- 2-3 -
2.3
Among the river flow data mentioned earlier, past flow observation data for the are-a
surrounding the project site should be used to estimate the river flow, taking the rainfall
distribution characteristics into consideration.
Qp = RrQoAo
Where,
Qp : river flow per unit catchment area in project area (m3/skm2)
Rr : rainfall ratio between cactchment area of the proposed site for micro-hydro
project and of existing gauging station
Qo : observed river flow at existing gauging station or existing hydro-power station
(m3/s)
Ao : catchment area of existing gauging station (km2)
[See Reference 2-3: Considerations when estimating river flow at the project site
indirectly from existing data of vicinity gauging stations for the important points to
note for estimation of the river flow based on the existing gauging station nearby.]
Particularly in the micro-hydro scheme, it is important that firm discharge, which is the
river flow in the dry season, is estimated accurately. We have experienced that the firm
discharge in the northern part of South Sulawesi is estimated approximately 0.020 to
0.025 m3/skm2.
If no flow data are available, it is possible to estimate the rough flow duration referring
to Reference 2-3: Simple calculating method of river flow by the water balance model
of drainage area.
- 2-4 -
2.4
- 2-5 -
section
for
power
Elevation
Suitable
Catchment Area
River
Confluence
Fig 2.4.1 River Profile and Changes in Drainage Area of River to Assist Extraction of
Promising Hydropower Generation Sites
- 2-6 -
While it is difficult to judge the suitability for development based on the absolute
volume of firm discharge, a potential site with a relatively high level of firm discharge
is a more advantageous site for a small-scale hydropower plant, including micro-hydro,
which is required to supply power throughout the year as constantly as possible because
of its purpose of supplying power to specific power demand facilities in most cases.
When the estimated specific discharge of firm discharge, i.e. discharge per unit drainage
area, differs for each potential site, it must be noted that the relative construction cost of
an intake weir or bank protection, etc. increases for a river with a smaller specific
discharge because of the larger drainage area and greater scale of possible flooding
associated with such a river.
Fig 2.4.2 shows the relation of specific firm discharge and the ratio of firm discharge to
maximum discharge (Qmax/QF: refer to following figure) in existing small-scale
hydropower plants. Generally, the Qmax/QF value of Micro-hydro Power plant and mini
hydropower plant are shown about 1.0 and 0.7~0.9 respectively, and the specific firm
discharge in this Qmax/QF range is 1.2~1.5 m3 /s100km2 on the average. When
developing a micro or mini hydropower plant in a river where specific firm discharge is
lower than 1.0 m3/s100km2, a cost reduction method such as use of existing irrigation
facilities as mentioned after should be considered.
Qmax
Duration Curve
QF
Days
- 2-7 -
Micro
(m3/s)
2.0
Large
1.8
1.6
1.4
Small
Mini
1.2
1.0
0.8
0.6
0.4
0.2
0.0
0
10
20
30
40
50
60
70
80
Firm discharge / Maximum discharge (%)
90
100
(2)
L/H [ratio between waterway length (L) and total head (H)]
A site with a smaller L/H value is more advantageous for small-scale hydropower.
Fig 2.4.3 shows the relation of the ratio between the total head (H) and the waterway
length (L) (L/H) among existing small-scale hydropower sites where the total head is
not less than 10 m (the minimum head which can be interpreted on an existing
topographical map). As is clearly indicated in the figure, the L/H of existing sites is
generally not higher than 40 or is an average of 20.
And Fig 2.4.4 shows the relation of firm discharge to L/H. This shows a tendency
whereby L/H is smaller at sites where the firm discharge is also small. The L/H of
existing sites in which firm discharge is less than 0.2m3/s is roughly less than 15.
- 2-8 -
100
Head (m)
80
60
40
20
0
0
500
1000
1500
2000
Waterway length (m)
2500
3000
0.5
0.4
0.3
0.2
0.1
0
0
10
20
30
40
- 2-9 -
50
Aluminum Conductor
11kV, 300kW
ratio
Distance (km)
Diameter of line
[Ref. 2-1 Transmission and distribution line distance and voltage drop]
- 2-10 -
Aluminum Conductor
6.6kV, 300kW
Diameter of line
Distance (km)
Relation of transmission line
distance and voltage drop II
Permissible voltage
drop ratio
- 2-11 -
400V, 50kW
Aluminum Conductor
Distance (m)
Relation of transmission line
distance and voltage drop III
Permissible voltage
drop ratio
Diameter of line
[Ref. 2-2 The relationship between voltage drop and distribution line distance in the Indonesia]
- 2-12 -
400
600
800
1000
Length of Transmission line (15kW)
1200
1500
200
200
400
600
800
1000
- 2-13 -
1200
1500
[Ref. 2-3 Considerations when estimating discharge at the project site indirectly from existing
data of nearby gauging stations]
If there are multiple gauging stations near the project site, the following matters should be taken
into consideration when selecting the gauging station that will be applied.
1. Drainage area ratio
When estimating discharge based on the observed data of existing gauging stations, its drainage
area should be taken into consideration. From the discharge characteristic as shown in the
following figure, if drainage area ratio between existing gauging station and project site is large,
the flow duration curves may be crossing. This means that the discharge computation using
Day
2. Rainfall
The flow-duration and the characteristic of rainfall in the upper portion of the river have a close
correlation. Particularly in the long-term discharge, a close correlation is recognized between
rainfall and discharge. Therefore, the rainfall data of both drainage areas are useful information to
evaluate discharge of the project site from the gauging station.
The simplest method to grasp the rainfall around the project site is to use the isohyetal maps that
show contour lines of average rainfall, and can be used to compare the amount of rainfall of the
Day
- 2-14 -
3. Geological conditions
Although checking discharge of the project site and gauging station by the rainfall in their
drainage areas is useful for knowing their magnitude relation, it is not exactly effective for
judging the correlation of flow duration curves.
The factor which influences the similarity of flow duration curves is not only the drainage areas
but also geological conditions, particularly existence of Quaternary volcanic rock area.
A Quaternary volcanic rock is known as the geology of high moisturizing action. The flow
duration curves through this geology is relatively flat, indicating smaller discharge in the wet
season and larger discharge in the dry season, compared to through non-Quaternary volcanic
Existence of Quaternary
volcanic rock in the
drainage area
Not existence of
Quaternary volcanic rock
Day
It is possible to know distribution of Quaternary volcanic rocks from existing geological maps,
however, it is difficult to analyze quantitatively the relation of the share of Quaternary volcanic
rocks in the drainage area and the characteristic of discharge as a general pattern. With this view,
realistically, when Quaternary volcanic rocks exist in the project area, it is reasonable to select
gauging stations with an equivalent share.
Besides Quaternary volcanic rock, although limestone is the geology that affects the river
discharge, it is very difficult to gauge this influence qualitatively and quantitatively. Generally the
river where limestone is distributed shows irregular change in its discharge, as the discharge of the
upstream and the downstream may be reversed partially, or the discharge may fluctuate rapidly at
a certain point. Therefore, in the case where much limestone exists in the drainage area, in
principle it is necessary to measure the stream flow at the intake point of the project site.
4. Geographical conditions
Geographical conditions are mentioned as an auxiliary judgment material of discharge. Generally,
a tendency whereby rainfall is larger at higher altitude and steeper mountain is recognized. From
this point, selection of gauging stations to which conditions, such as altitude, geographical feature,
and direction of a drainage area are similar is set as a method to raise presumed accuracy.
If a non-dissecting plain exists in the drainage area of project site and its outline falls down, the
rainfall may be discharged out side of the drainage area by the sub-surface seepage.
- 2-15 -
[Ref. 2-4 Simple calculating method of river flow by the water balance model of drainage area]
If there are no discharge observation data but only rainfall data, it is possible to estimate river
discharge from the water balance data of the drainage area.
1. Calculation method
(1) Water balance of the drainage area
The relation of rainfall, runoff (direct runoff, base runoff), and evaporation is indicated by the
viewpoint of annual water balance as follows. In this case, there is no concern about pooling of
drainage area, and inflow and runoff to and from other drainage areas.
P = R + Et
= Rd + Rb + Et
where,
P : Annual rainfall (mm)
R : Annual runoff (mm)
Rd : Annual direct runoff (mm)
Rb : Annual base runoff (mm)
Et : Annual evaporation (mm)
Runoff (R) is obtained from calculated evaporation (Et) by the presumption formula and
observed rainfall (P).
A pattern figure of the relation of rainfall (R), possible evaporation (Etp), and real evaporation
(Et) is shown Figure 1-1. Indicated as diagonal line is real evaporation, and area above line b-c
is river runoff including sub-surface water. Possible evaporation (a-b-c-d) is obtained by
presumption formula.
(2) Direct runoff and base runoff
A pattern figure of annual runoff is shown Figure 1-2. The runoff is provided from sub-surface
water, and it contains base runoff which is subject to less seasonal fluctuation and direct runoff in
which rainfall immediately becomes runoff. The ratio of sub-surface water to annual runoff (R) is
as shown Table 1-1. Where, Rg = Rb, Rb / R = 0.25 constant, and the base runoff is posited
annually constant.
- 2-16 -
Amount of rainfall
Possible evaporation
(Etp)
Runoff (R)
Amount of real
evaporation (Et)
Month
Figure 1-1 Pattern figure of amount of rainfall and evaporation
Month
Figure 1-2
- 2-17 -
Table 1-1
Area
Rainfall
(P)
Runoff
(R)
Direct runoff
(Rd)
Subsoil
water
Evaporation
(Et)
Rg / R
Asia
Africa
Europe
Australia
Japan
726
686
670
1648
734
736
1788
293
139
287
583
319
226
1197
217
91
203
373
210
172
76
48
84
210
109
54
433
547
383
1065
415
510
597
26
35
32
36
34
24
CA106
86,400n
Data of Japan from Ministry of Land, Infrastructure and Transport
( 45.7t + 813 )
100
where,
u : Monthly evaporation (mm)
K : Monthly coefficient of vegetation
P : Monthly rate of annual sunshine (%)
t : Monthly average temperature ()
Monthly average temperature and monthly rate of annual sunshine
Monthly average temperature ; Using temperature at the drainage area of dam site
Monthly rate of annual sunshine ; Obtained by the latitude at the drainage area of dam site
In the northern hemisphere, using Table 1-2, and in the southern hemisphere, using Table 1-3.
K value
It is turned on by the vegetation condition. Here is pointed constant as 0.6.
(b) Example of calculation
Conditions : Position of drainage area
lat. 16N
- 2-18 -
(%)
North
Latitude
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov. Dec.
65
64
63
62
61
3.52
3.81
4.07
4.31
4.51
5.13
5.27
5.39
5.49
5.58
7.96
8.00
8.04
8.07
8.09
9.97
9.92
9.86
9.80
9.74
12.72
12.50
12.29
12.11
11.94
14.15
13.63
13.24
12.92
12.66
13.59
13.26
12.97
12.73
12.51
11.18
11.08
10.97
10.87
10.77
8.55
8.56
8.56
8.55
8.55
6.53
6.63
6.73
6.80
6.88
4.08
4.32
4.52
4.70
4.86
2.62
3.02
3.36
3.65
3.91
60
59
58
57
56
4.70
4.86
5.02
5.17
5.31
5.67
5.76
5.84
5.91
5.98
8.11
8.13
8.14
8.15
8.17
9.69
9.64
9.59
9.53
9.48
11.78
11.64
11.50
11.38
11.26
12.41
12.19
12.00
11.83
11.68
12.31
12.13
11.96
11.81
11.67
10.68
10.60
10.52
10.44
10.36
8.54
8.53
8.53
8.52
8.52
6.95
7.00
7.06
7.13
7.18
5.02
5.17
5.30
5.42
5.52
4.14
4.35
4.54
4.71
4.87
55
54
53
52
51
5.44
5.56
5.68
5.79
5.89
6.04
6.10
6.16
6.22
6.27
8.18
8.19
8.20
8.21
8.23
9.44
9.40
9.36
9.32
9.28
11.15
11.04
10.94
10.85
10.76
11.53
11.39
11.26
11.14
11.02
11.54
11.42
11.30
11.19
11.09
10.29
10.22
10.16
10.10
10.05
8.51
8.50
8.49
8.48
8.47
7.23
7.28
7.32
7.36
7.40
5.63
5.74
5.83
5.92
6.00
5.02
5.16
5.30
5.42
5.54
50
48
46
44
42
5.99
6.17
6.33
6.48
6.61
6.32
6.41
6.50
6.57
6.65
8.24
8.26
8.28
8.29
8.30
9.24
9.17
9.11
9.05
8.99
10.68
10.52
10.38
10.25
10.13
10.92
10.72
10.53
10.39
10.24
10.99
10.81
10.65
10.49
10.35
9.99
9.89
9.79
9.71
9.62
8.46
8.45
8.43
8.41
8.40
7.44
7.51
7.58
7.64
7.70
6.08
6.24
6.37
6.50
6.62
5.65
5.85
6.05
6.22
6.39
40
38
36
34
32
6.75
6.87
6.98
7.10
7.20
6.72
6.79
6.85
6.91
6.97
8.32
8.33
8.35
8.35
8.36
9.55
9.47
9.41
9.34
9.28
8.39
8.37
8.36
8.35
8.34
7.75
7.80
7.85
7.90
7.95
6.73
6.83
6.93
7.02
7.11
6.54
6.68
6.81
6.93
7.05
30
28
26
24
22
7.31
7.40
7.49
7.58
7.67
7.02
7.07
7.12
7.16
7.21
8.37
8.37
8.38
8.39
8.40
8.71
8.67
8.64
8.60
8.56
9.54
9.46
9.37
9.30
9.22
9.49
9.39
9.29
9.19
9.11
9.67
9.58
9.49
9.40
9.32
9.21
9.17
9.11
9.06
9.01
8.33
8.32
8.32
8.31
8.30
7.99
8.02
8.06
8.10
8.13
7.20
7.28
7.36
7.44
7.51
7.16
7.27
7.37
7.47
7.56
20
18
16
14
12
7.75
7.83
7.91
7.98
8.06
7.26
7.31
7.35
7.39
7.43
8.41
8.41
8.42
8.43
8.44
8.53
8.50
8.47
8.43
8.40
9.15
9.08
9.01
8.94
8.87
9.02
8.93
8.85
8.77
8.69
9.24
9.16
9.08
9.00
8.92
8.95
8.90
8.85
8.80
8.76
8.29
8.29
8.28
8.27
8.26
8.17
8.20
8.23
8.27
8.31
7.58
7.65
7.72
7.79
7.85
7.65
7.74
7.83
7.93
8.01
10
8
6
4
2
8.14
8.21
8.28
8.36
8.43
7.47
7.51
7.55
7.59
7.63
8.45
8.45
8.46
8.47
8.49
8.37
8.34
8.31
8.28
8.25
8.81
8.74
8.68
8.62
8.55
8.61
8.53
8.45
8.37
8.29
8.85
8.78
8.71
8.64
8.57
8.71
8.66
8.62
8.58
8.53
8.25
8.25
8.24
8.23
8.22
8.34
8.37
8.40
8.43
8.46
7.91
7.98
8.04
8.10
8.16
8.09
8.18
8.26
8.34
8.42
8.50
7.67
8.49
8.22
8.49
8.22
8.50
8.49
8.21
8.49
8.22
8.50
- 2-19 -
(%)
South
Latitude
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov. Dec.
0
2
4
6
8
8.50
8.55
8.64
8.71
8.79
7.67
7.71
7.76
7.81
7.84
8.49
8.49
8.50
8.50
8.51
8.22
8.19
8.17
8.12
8.11
8.49
8.44
8.39
8.30
8.24
8.22
8.17
8.08
8.00
7.91
8.50
8.43
8.20
8.19
8.13
8.49
8.44
8.41
8.37
8.12
8.21
8.20
8.19
8.18
8.18
8.49
8.52
8.56
8.59
8.62
8.22
8.27
8.33
8.38
8.47
8.50
8.55
8.65
8.74
8.84
10
12
14
16
18
8.85
8.91
8.97
9.09
9.18
7.86
7.91
7.97
8.02
8.06
8.52
8.53
8.54
8.56
8.57
8.09
8.06
8.03
7.98
7.93
8.18
8.15
8.07
7.96
7.89
7.84
7.79
7.70
7.57
7.50
8.11
8.08
7.08
7.94
7.88
8.28
8.23
8.19
8.14
8.10
8.18
8.17
8.16
8.14
8.14
8.65
8.67
8.69
8.78
8.80
8.52
8.58
8.65
8.72
8.80
8.90
8.95
9.01
9.17
9.24
20
22
24
26
28
9.25
9.36
9.44
9.52
9.61
8.09
8.12
8.17
8.28
8.31
8.58
8.58
8.59
8.60
8.61
7.92
7.89
7.87
7.81
7.79
7.83
7.74
7.65
7.56
7.49
7.41
7.30
7.24
7.07
6.99
7.73
7.76
7.68
7.49
7.40
8.05
8.00
7.95
7.90
7.85
8.13
8.13
8.12
8.11
8.10
8.83
8.86
8.89
8.94
8.97
8.85
8.90
8.96
9.10
9.19
9.32
9.38
9.47
9.61
9.74
30
32
34
36
38
9.69
9.76
9.88
10.06
10.14
8.33
8.36
8.41
8.53
8.61
8.63
8.64
8.65
8.67
8.68
7.75
7.70
7.68
7.61
7.59
7.43
7.34
7.25
7.16
7.07
6.94
6.85
6.73
6.59
6.46
7.30
7.20
7.10
6.99
6.87
7.80
7.73
7.69
7.59
7.51
8.09
8.08
8.06
8.06
8.05
9.00
9.04
9.07
9.15
9.19
9.24 9.80
9.31 9.87
9.38 9.99
9.51 10.21
9.60 10.34
40
42
44
46
48
10.24
10.39
10.52
10.68
10.85
8.65
8.72
8.81
8.88
8.98
8.70
8.71
8.72
8.73
8.76
7.54
7.49
7.44
7.39
7.32
6.96
6.85
6.73
6.61
6.45
6.33
6.20
6.04
5.87
5.69
6.73
6.60
6.45
6.30
6.13
7.46
7.39
7.30
7.21
7.12
8.04
8.01
8.00
7.98
7.96
50
11.03
9.06
8.77
7.25
6.31
5.48
5.98
7.03
7.95
(Note) Southern part more than lat. 50S will be calculated using example from Table 1-2.
Concretely, the monthly rate of southern latitude is corresponding to below showing
months of northern latitude.
Southern lat. January February March
April
May
June
-
Northern lat.
July
August
September
October
November
December
- 2-20 -
Month
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
7.91
7.35
8.42
8.47
9.01
8.85
9.08
8.85
8.28
8.23
7.72
7.83
86.4
85.6
103.8
108.4
114.2
110.4
111.8
108.7
101.9
100.0
88.6
85.4
Total
(
(
(
(
(
(
(
(
(
(
(
(
1,205.2
91.0
106.4
129.7
138.2
116.3
91.1
81.2
72.7
74.6
79.7
73.4
80.2
)
)
)
)
)
)
)
)
)
)
)
)
8.5
16.8
38.3
62.3
170.0
180.3
202.9
197.7
207.7
123.0
30.2
17.9
8.5
16.8
38.3
62.3
114.2
110.4
111.8
108.7
101.9
100.0
30.2
17.9
( 1,134.5 )
1,255.6
821.0
(Note) : obtained data : from Table 1-2 : parenthetic numbers are observed evaporation
value from water surface
Runoff
-
of Chart 1-4
(mm)
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
0
0
0
0
55.8
69.6
91.1
89.0
105.8
23.0
0
0
0
0
0
0
41.9
52.2
68.3
66.8
79.4
17.3
0
0
9.2
8.3
9.2
8.9
9.2
8.9
9.2
9.2
8.9
9.2
8.9
9.2
9.2
8.3
9.2
8.9
51.1
61.1
77.5
76.0
88.3
26.5
8.9
9.2
Total
434.3
325.7
108.6
434.3
- 2-21 -
1.03
1.03
1.03
1.03
5.72
7.07
8.69
8.51
10.22
2.96
1.03
1.03
[Ref. 2-5 Example of Use of Natural Topography and Various Man-Made Structures]
1. Using existing irrigation channel and naturally formed pool downstream of fall
River
Intake weir
Headrace
Water fall
River
Power house
Spillway
Penstock
Irrigation channel
- 2-22 -
Headtank Screen
Headrace
Intake weir
River
Intake weir
Headtank
Screen
Penstock
River
-2-5
Power house
Tailrace
- 2-23 -
Irrigation
channel
Intake
-2-6
Headtank
Head drop
structure
Penstock
Power house
- 2-24 -
-2-7
River
Intake
Headrace
Irrigation
channel
Road
Headtank
Penstock
Power house
Tailrace
- 2-25 -
- 2-26 -