Professional Documents
Culture Documents
This article
clarifies the
principles and
practices in the
new ASTM
Standard and
presents how
the new
standard will
impact the ISPE
C&Q Baseline
Guide Revision.
38
40
critical aspects are defined earlier in 6.4.1 as functions, features, abilities, and performance
characteristics necessary for the
manufacturing process to ensure
consistent product quality and
patient safety.
b. 7.4.2.3 describes use of an overall verification plan to define the
verification strategy, what constitutes acceptable documentation, etc. The verification plan
41
43
ate subject matter experts, which implies that the documentation need be
understandable by a subject matter
expert. The only specific requirement
regarding documentation in the standard is found under Acceptance and
Release 7.5.3, The documentation
should contain a clear statement as to
whether or not the manufacturing system is fit for intended use
5. The GMPs require pre-approval by
the quality unit of changes once
manufacturing operations have commenced. Many project teams have
extended this pre-approval further
and further into the early stages of
inspection and testing, even as far
back as design. The ASTM standard
makes the distinction between preapproval by the quality unit, and
change management as may be practiced by subject matter experts. The
standard requires that change management processes be established
ing, packing, or holding of a drug
product shall be of suitable size, construction and location to facilitate cleaning, maintenance, and proper operations.
(several specific items are listed in
subsequent sections and subsections)
211.63 (Equipment) Design, size and
location. Equipment used in the manufacture, processing, packing, or holding of a drug product shall be of appropriate design, adequate size, and suitably located to facilitate operations for
its intended use and for its cleaning and
maintenance.
211.65 Equipment construction.
(a) Equipment shall be constructed so
that surfaces that contact components, in-process materials, or drug
products shall not be reactive, additive, or absorptive so as to alter the
safety, identity, strength, quality,
or purity of the drug product beyond
the official or other established requirements.
(b) Any substances required for operation, such as lubricants or coolants,
shall not come into contact with
components, drug product contain-
44
45
Implementation Options
and Case Studies
What follows are some suggestions and
a case study for restructuring qualification, while meeting GMPs and ASTM
E2500. Other approaches are also possible. Again, it is important to note
that to be in conformance with the
standard, one does not have the option
of picking and choosing which aspects
of E2500 to implement on a particular
project.
Alternative Approach #1
One could simply follow the ASTM
standard and not worry about whether
documents are called IQ/OQ or comdiscussed in terms of verifying the
operating parameters and limits for the
critical variables of the operating equipment.
Annex 11 Computerized Systems
Where a computerized system replaces
a manual operation, there should be no
resultant decrease in product quality or
quality assurance.
Persons should be appropriately
trained and have appropriate expertise
as applicable to a computerized system. The extent of validation necessary will depend on the intended use,
whether validation is to be prospective
or retrospective, and whether or not
novel elements are incorporated.
The computerized system is further
discussed, including, but not limited
to, topics such as:
Software should be produced in
accordance with a system of Quality Assurance.
Access to data should be limited.
When critical data is entered, there
should be a check on the accuracy.
The identify of operators editing or
confirming critical data should be
recorded.
Alterations should be via a defined
46
Alternative Approach #2
Follow the ASTM standard, and consider the final acceptance phase the
act of qualifying. There is some logic
to this approach. If the purpose of qualiprocedure.
Data should be secure and protected by backup, etc.
Procedures to be followed when the
system fails should be established.
When outside agencies are used,
there should be a formal agreement,
including responsibilities of the outside agency.
Only authorized, Qualified Persons
should have the ability to release a
batch.
ICH Guidance Documents
ICH Q7A Good Manufacturing Practice
Guidance for Active Pharmaceutical
Ingredients
Before initiating process validation activities, appropriate qualification of critical equipment and ancillary systems
should be completed. Qualification is
usually carried out by conducting the
following activities, individually or combined: DQ, IQ, OQ, PQ.
ICH Q9 Quality Risk Management
[Quality Risk Management can be used]
to determine the scope and extent of
qualification of facilities, buildings, and
production equipment... To determine
design of facilities/equipment.
fication was to demonstrate that equipment and systems were fit for their
intended use, then one would need to
show that the equipment and systems
can support manufacture of a particular product using a particular process.
The final acceptance phase includes a
review of the verification work to confirm that process requirements have
been met and risks to the patient adequately controlled. In short, progressively qualified.
47
48
Alternative Approach #3
Follow the ASTM standard, and label
the verification documentation IQ/OQ/
PQ as appropriate. However, if this
approach is to achieve cost/schedule/
quality improvements over todays
practices, then the current non-valueadded qualification practices need to
be stripped away. This is easier said
than done since current qualification
practices that would need to be eliminated can be many, but the major ones
that impact cost/schedule/quality are:
A discrepancy handling process that
mimics batch record deviations
instead, let the subject matter expert deal with the situation. If a
critical aspect cant be met AFTER
efforts have been made to correct,
then quality needs to be involved to
review the impact on patient safety
with implementation of other measures to control a particular risk or
otherwise meet a process requirement.
Pre-mature implementation of QA
pre-approved change control this
is not required if product for human
use is not yet being manufactured.
However, project teams must implement a workable system of change
management using good engineering practice to ensure changes are
noted, appropriate documents up-
49
Case Study
A biotech process development/clinical manufacturing facility was being
brought out of mothball status. It was
desired to both leverage commissioning to streamline qualification, and
also to use a risk-based approach to
focus qualification. Risk assessments
were used to identify the risks to the
patient that could result from the
manufacturing process. Risk control
mechanisms were identified for each
risk. These risk control mechanisms
took the form of automation controls,
detection mechanisms, design features, procedures, and other means.
These risk control mechanisms became the substance of the IQ/OQ protocols. The protocols were developed
50
Reference
1. In similar vein, process validation
is the confirmation that the overall
manufacturing process has been
properly designed, monitored, and
controlled so that the resulting drug
product is of consistently high quality and meets all of its specifications.