Professional Documents
Culture Documents
No. 13-2215
J.
of
F.
Defendants Appellees,
and
CAPE HATTERAS ELECTRIC MEMBERSHIP CORPORATION,
Intervenor/Defendant - Appellee.
Appeal from the United States District Court for the Eastern
District of North Carolina, at Elizabeth City.
Louise W.
Flanagan, District Judge. (2:11-cv-00035-FL; 2:12-mc-00001-FL)
Argued:
Decided:
August 6, 2014
Banks,
barrier
islands
along
coast.
For
decades,
the
Bridge)
has
provided
highway
North
Herbert
C.
Carolinas
Bonner
access
Bridge
between
Atlantic
(Bonner
mainland
North
threaten the
sought
long-term
transportation
solution
to
currently
exists:
replacing
the
Bonner
Bridge
and
of
Wildlife
and
(Plaintiffs)
claim
Environmental
that
Policy
Act
the
National
responded
Defendants
(NEPA)
Wildlife
with
violated
and
Section
Refuge
this
lawsuit.
the
National
4(f)
of
the
to
the
construction
of
only
one
segment
of
the
public
the
full
review
of
3
the
entire
project
and
its
rejecting
alternatives
that
would
not
have
used
held,
Section
in
4(f)
part,
in
that
Defendants
complied
researching,
designing,
we
decide
and
The district
with
NEPA
selecting
and
their
project.
On
appeal,
do
not
whether
we
agree
with
Rather, we
extensive
administrative
courts decision.
affirm
the
record
underlying
the
district
district
courts
determination
that
Defendants
I.
A.
Since
the
early
1990s,
Defendants
have
been
developing
one
currently
Project.
under
by
this
Courtsimply
as
the
Inlet,
to
the
Village
of
Rodanthe,
the
northernmost
2.4
miles
long
and
carries
over
ten
thousand
vehicles per day during the areas busy summer tourist season.
After
crossing
the
Oregon
Inlet
but
before
reaching
Wildlife
Refuge
(Refuge)
and
the
Cape
Hatteras
owned and managed by the federal government, and they are major
destinations for many of the tourists who visit Hatteras Island.
1938,
President
Roosevelt
established
the
Refuge
(Apr.
During
12,
1938).
1937
and
1938,
the
United
States
is
managed
by
the
United
States
Fish
and
The
Wildlife
1937,
Congress
created
the
Seashore
as
protected
Act of Aug.
Id. at 669.
the land for the Seashore through several deeds from the State
of North Carolina.
J.A. 1413.
be
undertaken
which
would
be
incompatible
with
the
Act of
The
the
1940s,
J.A. 1413.
paved
roads
were
built
between
the
And it was
not until 1954 that DOI formally deeded the easement to North
Carolina.
Unfortunately, both the Bonner Bridge and the road have
suffered from the effects of time, ocean overwash, and erosion.
7
NCDOT has deemed the condition of the Bonner Bridge poor and
given it a sufficiency rating of two out of 100.
The
condition
of
the
surface
road
is
no
J.A. 1256.
better.
In
its
narrowest places in the Refuge, Hatteras Island is just onequarter mile wide, and even under normal weather conditions,
portions
of
overwash.
NC
12
are
threatened
by
shoreline
erosion
and
possible, 1
and
J.A. 1256.
Despite
moving
NC
12
as
far
west
as
NCDOT
has
not
been
able
to
ensure
the
uninterrupted
And
in
2012,
Hurricane
Sandy
tore
up
the
roadbed,
In
light
of
the
impact
of
storm
events
such
as
these,
merely replacing the Bonner Bridge would not achieve the central
purpose of the Project, which is to [p]rovide a new means of
access from Bodie Island to Hatteras Island for its residents,
businesses,
Bonner
services,
Bridges
and
service
tourists
life.
prior
J.A.
to
the
2486.
end
of
Indeed,
the
as
includes
NC
12
J.A. 2493.
between
the
of
Rodanthe
and
J.A. 2486.
B.
began
They
NEPA
Corridor.
to
plan
completed
preferred
J.A. 785.
for
a
replacement
feasibility
alternative 2
the
of
the
study
and
1993
Parallel
Bonner
selected
as
Bridge
replacement
bridge.
In
1993,
Defendants
completed
Draft
J.A. 786.
J.A. 1787.
Defendants
began
assessing
different
These
Draft
Environmental
Impact
Statement/4(f)
Evaluation).
The
2005
Supplemental
Draft
Environmental
Impact
The first
and the two alternatives within this corridor involved an 18mile-long bridge that extended from Bodie Island in the north to
Rodanthe
in
the
south.
Both
of
these
alternatives,
titled
west
of
Hatteras
Island
into
Pamlico
Sound
before
J.A. 78182.
These alternatives
J.A. 783.
beach
nourishment
plus
dune
enhancement
to
J.A. 783.
be
replenished
with
dredged
sand
every
11
few
yearswould
The
second
alternativetitled
Road
North/Bridge
South
J.A.
J.A. 783.
The final alternative within the Parallel Bridge Corridor
was called the All Bridge Alternative, in which NC 12 would
be constructed on a bridge to the west of the existing road.
J.A. 783.
would also include two surface road segmentsone near the Oregon
Inlet and another just north of the Refuges ponds where access
from NC 12 to the Refuge would be provided.
2005
Supplemental
Draft
Environmental
Impact
J.A. 783.
The
Statement/4(f)
alternatives
separate
alternatives,
were
described
their
and
components
12
addressed
could
be
as
mixed
three
and
J.A. 783.
2005
Supplemental
Statement/4(f)
Evaluation
Draft
did
Environmental
not
select
Impact
preferred
Supplemental
Draft
Environmental
explains
Impact
Statement
and
that
it
was
issued
to
Draft
The 2007
address
the
J.A.
Bridge
Nourishment.
Corridor
J.A. 1096.
With
Phased
Approach/Rodanthe
J.A.
1093.
The 2007 Supplements two new alternatives were variations
on
Phased
Approach
to
the
Project.
Both
alternatives
J.A. 1097.
Both alternatives
the
new
remaining
Oregon
phases
Inlet
would
shoreline erosion.
bridge
be
as
the
constructed
first
as
phase.
The
necessitated
by
J.A. 1097.
erosion.
Under
the
Phased
Approach/Rodanthe
Bridge
J.A. 1097.
bridge
would
Refuge/Rodanthe
begin
border.
0.3
mile
Beach
protect NC 12 in Rodanthe.
Supplemental
Supplement
Draft
that
nourishment
J.A. 1097.
Environmental
explained
all
Impact
of
south
would
of
be
the
used
to
the
the
Parallel
2007
Bridge
J.A. 1097.
Statement
and
alternatives:
its
(1)
2007
Supplement
Pamlico
14
Sound
analyzed
Bridge
in
Corridor
detail
With
Rodanthe
Nourishment;
North/Bridge
Bridge;
(4)
South;
(6)
Terminus;
(3)
Parallel
Parallel
Bridge
(5)
Parallel
Parallel
Bridge
Bridge
Corridor
Bridge
Corridor
With
Corridor
Corridor
Road
With
With
All
Phased
2008,
Statement
Defendants
(2008
Final
issued
Final
Environmental
Environmental
Impact
Impact
Statement)
that
Approach/Rodanthe
Environmental
Impact
Bridge.
Statement
J.A.
clearly
1229.
The
explained
Final
that
the
was
added
in
the
2007
Supplementthe
Parallel
Bridge
J.A. 1230.
The Final
and
need;
environmental
consequences;
opportunities
the
2005
Supplemental
Draft
15
Environmental
Impact
presented
Statement].
in
this
[Final
Environmental
Impact
J.A. 1231.
the
Section
4(f)
Evaluation
to
have
obtained
included
J.A. 1812.
additional
in
the
[Final
Defendants also
information,
which
also
1812.
This
additional
information
consisted
of
what
J.A.
16
1814.
J.A. 1814.
J.A. 183448.
Defendants
this
distributed
document
at
meeting
with
The
meeting
Defendants
planned
to
agenda
for
designate
that
the
day
Road
that
meeting,
indicates
North/Bridge
that
South
J.A. 1811.
representative
from
the
17
J.A. 1886.
J.A. 1886.
idea,
however.
Specifically,
Pete
Benjamin,
he
was
appropriate
trying
for
this
to
decide
project
if
but
adaptive
had
management
reservations
was
regarding
the
agencies
need[ed]
J.A. 1887.
more
than
He went on to say
just
the
hope
J.A. 1887.
[of
After the
that
Defendants
presented
to
the
meeting
Refuge,
assessments
and
he
J.A. 1892.
regarding
expressed
the
the
environmental
belief
that
impact
NCDOT
on
cannot
such
reservations,
J.A. 1896.
Defendants
began
to
Revised
Final
Section
its
first
notice
of
4(f)
Evaluation
(2009
new
Preferred
Alternativethe
J.A. 1904.
19
Section
4(f)
J.A. 1907.
applied
only
to
Pea
Island
National
it
J.A. 1913-14.
claimed
governments
demonstrate[d]
preserved
the
that
Hatteras
the
Federal
Island
area
and
State
with
an
20
wildlife
while
maintaining
vehicular transportation.
means
for
J.A. 1913.
safe
and
efficient
J.A. 1913.
May
7,
2010,
Defendants
J.A. 1913.
issued
an
Environmental
21
J.A. 2151.
The Environmental
J.A. 2178.
of
multiple
phases.
The
first
phase
would
be
the
previously
appellate
been
brief
that
evaluated.
the
replacement
2493).
The
Defendants
amorphously
clarify
bridge
would
in
their
use
the
Later
Phasesalso
J.A. 218283.
NC
12
Transportation
Management
Plan
Alternative
coastal
barrier
island
environment.
J.A.
2182.
Environmental
transportation
understood. 8
management
Assessment
plan
as
J.A. 2182.
does
that
not
term
contain
is
typically
program,
J.A.
2183,
[e]nvironmental
[r]eview
for
Defendants plan
23
can
claimed
and
be
2182.
that
delaying
better
Defendants
[b]y
actively
decisionmaking,
quantified,
also
the
minimized,
stated
that
monitoring
the
environmental
and
[t]his
mitigated.
process
is
J.A. 2182.
bridge)
to
be
J.A. 2488.
built
as
as
possible,
followed
by
24
Record
of
Decision
J.A. 2488.
also
contains
section
that
preferred
alternative.
The
Army
Corps
of
Engineers
(on
which
the
Environmental
Assessment
was
based)
J.A.
The
proposal
in
Section
4.6.8.6
of
the
Final
Environmental Impact Statement to confine future NC 12
maintenance activities within the existing easement
applied only to the Phased Approach Alternatives,
which were developed with the requirement that all
work within the Refuge must be confined within the
existing easement.
That requirement does not exist
with the NC 12 Transportation Management Plan.
J.A. 2587 (emphasis added).
Given the foregoing, this Court understands the Project as
follows:
Construction
of
new
two-lane
bridge
that
runs
easement,
followed
by
the
study
and
selection
of
future
with
the
purpose
of
said
25
Plan
being
to
guide
the
On
for
summary
September
judgment
16,
2013,
in
the
July
and
district
September
court
of
granted
Defenders of
Plaintiffs
NEPA
claim,
the
district
court
[that]
only
covers
the
Bonner
Bridge
replacement,
with
can
conditions
Id. at 526.
stand
and
alone
weather
Hatteras Island.
due
events
to
concerns
impacting
as
the
to
changing
shoreline
on
Id. at 524.
segmentation,
which
require
that
project
have
logical
future
phases.
The
district
26
court
explained
that
the
525,
and
constitutes
that
the
logical
northern
terminus
end
for
of
the
Hatteras
Project
Island
due
to
the
independent
improvements,
maintenance
replacing
life.
and
.
of
that
the
does
not
bridge
that
is
Id. at 52526.
additional
fact
ruin
that
the
reaching
transportation
NC
12
substantial
the
end
of
requires
utility
its
of
service
Id. at 526
district
court
properly
respect
to
the
also
held
that
Defendants
did
not
relied
on
Refuge.
the
joint
Id.
at
planning
534.
exception
The
district
with
court
the
district
court
Id.
relied
In reaching this
on
the
following
Id. 53334.
of
Section
no
prudent
4(f)
and
concluded
that
FHWA
had
existed,
that
the
[selected]
alternative will cause the least overall harm, and that FHWA .
. . conducted all possible planning to minimize harm.
Id. at
535.
This appeal followed.
court
erred
Defendants
in
its
engaged
in
determinations
improper
regarding:
segmentation
in
(1)
whether
violation
of
Section
4(f);
and
(3)
whether
Defendants
complied
with
the
We turn now to a
II.
A.
At the outset, we must correct a major error on which the
district courts analysis was based:
defined the scope of the Project when it noted that the current
[Environmental Impact Statement] only covers the Bonner Bridge
replacement, . . . .
Id. at 526.
the entire record, and in making it, the district court invented
a project that Defendants NEPA documents under review expressly
disown. 10
10
Bodie
businesses,
Island
to
services,
Hatteras
and
Island
tourists
for
prior
to
J.A. 2486.
its
the
residents,
end
of
the
See,
e.g.,
that
J.A.
2493
(stating
in
the
Record
of
Decision
[b]uilding Phase I alone would not meet the purpose and need of
the project).
As
Defendants
stated
in
their
Record
of
Decision,
the
J.A. 2488.
interagency
warrant.
collaboration
as
project
area
conditions
J.A. 2488.
time
is
the
construction
of
Parallel
Bridge
across
Defendants
have
clearly
committed
J.A. 2497.
themselves
to
Project
that
Defendants
proposed.
However,
[a]n
appellee may defend, and this Court may affirm, the district
31
Sloas
v. CSX Transp., Inc., 616 F.3d 380, 388 n.5 (4th Cir. 2010).
Because
both
parties
have
adequately
briefed
and
argued
the
Fed. R.
Natl Audubon Socy v. Dept of the Navy, 422 F.3d 174, 185 (4th
Cir. 2005), taking the facts in the light most favorable to the
non-moving party.
255 (1986).
Because
disposed
of
the
district
cross-motions
courts
for
grant
summary
of
summary
judgment,
we
judgment
consider
In considering each
motion,
and
we
resolve
all
factual
disputes
any
competing,
agency
actions
under
NEPA
and
Section
4(f).
See
N.C.
Wildlife Fedn v. N.C. Dept of Transp., 677 F.3d 596, 601 (4th
Cir. 2012); Hickory Neighborhood Def. League v. Skinner, 893
F.2d 58, 61 (4th Cir. 1990).
agency
action
discretion,
that
or
was
otherwise
arbitrary,
not
in
capricious,
accordance
an
with
abuse
law[.]
of
5
but
the
Marsh,
490
ultimate
U.S.
at
standard
378
of
(quoting
review
is
Citizens
narrow
to
Pres.
Our
III.
A.
The National Environmental Policy Act of 1969, 42 U.S.C.
43214370f,
establishes
productive
and
environment,
and
enjoyable
was
national
harmony
intended
policy
between
to
reduce
[to]
encourage
man
and
or
his
eliminate
ecological
systems
United States.
and
natural
resources
important
to
the
42 U.S.C. 4321).
with
may
effects
subject
to
that
Federal
be
major
control
and
and
which
are
potentially
responsibility[,]
and
all
regulated,
or
approved
by
federal
agencies
must
40 C.F.R. 1508.18.
that
agencies
take
hard
look
at
environmental
results,
but
simply
prescribes
the
necessary
12
34
action.
Id.
information
at
35051.
mandated
by
[T]he
NEPA
broad
permits
dissemination
the
public
and
of
other
the
quality
of
the
human
environment,
the
agency
42 U.S.C.
40 C.F.R. 1502.1.
action
is
the
heart
statement
because
it
provid[es]
basis
clear
of
sharply
for
the
environmental
defin[es]
choice
the
among
impact
issues
options
40 C.F.R. 1502.14.
by
and
the
Therefore,
Id. 1502.14(a).
The assessment
for
1502.16.
the
comparison[]
of
alternatives.
40
C.F.R.
environmental
effects
of
proposed
35
actions.
Conclusory
statements
that
the
indirect
and
cumulative
effects
will
be
omitted).
NEPA does not require agencies to adopt any particular
internal decisionmaking structure.
require
process.
agencies
For
Environmental
to
follow
example,
Impact
particular
Environmental
Statements
must
be
decisionmaking
Assessments
completed
see
also
id.
1500.1(c)
But NEPA
(stating
and
before
40 C.F.R.
that
the
NEPA
agency
Statement
must
if
the
issue
agency
supplemental
makes
Environmental
substantial
changes
Impact
in
the
[t]here
are
significant
new
circumstances
or
information
36
F.3d
2012)
411,
426
(4th
Cir.
(quoting
Coal.
on
W.
Valley
Nuclear Wastes v. Chu, 592 F.3d 306, 311 (2d Cir. 2009)).
Specifically, [p]roposals or parts of proposals which are
related to each other closely enough to be, in effect, a single
course
of
action
statement.
40
shall
C.F.R.
be
evaluated
1502.4(a).
which
may
require
in
Proposed
single
impact
projects
are
environmental
impact
statements[;]
(ii) Cannot or will not proceed unless other actions are taken
previously
or
simultaneously[;
or]
(iii)
Are
interdependent
[c]umulative
Id. 1508.25(a)(1).
actions,
and
[s]imilar
actions
with
Id.
FHWAs
ensure
anti-segmentation
meaningful
regulations
evaluation
of
are
alternatives
designed
and
to
to
avoid
23 C.F.R. 771.111(f).
must:
(1) Connect logical termini and be of sufficient
length to address environmental matters on a broad
scope;
(2)
Have
independent
utility
or
independent
significance, i.e., be usable and be a reasonable
expenditure even if no additional transportation
improvements in the area are made; and
(3) Not restrict consideration of alternatives for
other
reasonably
foreseeable
transportation
improvements.
Id. 771.111(f)(1)-(3).
To
evaluate
whether
project
connects
logical
termini,
Volpe,
484
F.2d
11,
18
(8th
1973)
(If
the
major
are
crossroads,
Impact
often
Statement].).
obvious
population
because
centers,
Additionally,
of
major
their
connection
to
traffic
generators,
or
38
logical
The
independent
related
actions
Environmental
or
utility
projects
Impact
test
must
Statement.
also
be
determines
evaluated
Webster,
685
in
whether
a
F.3d
single
at
426.
Courts inquire into whether each project would have taken place
in
the
others
absence.
If
so,
[the
projects]
have
courts
consider
the
benefits
and
uses
that
will
occur
as
Authority,
this
Court
upheld
determination
that
Richmonds
359 F.
Supp. 611, 636 (E.D. Va. 1973), affd per curiam, 481 F.2d 1280
(4th Cir. 1973).
Highway Admin., 950 F.2d 1129, 114142 (5th Cir. 1992) (holding
that
one
because,
improved
portion
of
standing
access
to
highway
alone,
the
residential,
loop
had
project
independent
alleviated
commercial,
and
utility
traffic,
recreational
for
agencies
that
39
are
contemplating
large
or
complex projects.
tier
their
environmental
impact
statements
to
eliminate
40 C.F.R. 1502.20.
properly
tiered
analysis
environmental
impact
statement
environmental
or
statement
consists
followed
assessment
by
.
of
broad
subsequent
on
an
action
40
C.F.R.
1502.20
(emphasis
added).
The
may
never
alternatives
be
by
used
to
making
Id.
avoid
a
consideration
binding
of
site-specific
of
site-specific
issues
to
[subsequent
Ilioulaokalani
line
between
illegal
segmentation
and
And the
permissible
753, 761 (9th Cir. 1982) (internal quotation marks omitted); see
also 42 U.S.C. 4332(2)(C)(v).
D.
When reviewing a NEPA decision, a court must not reduce
itself to a rubber-stamp of agency action.
N.C. Wildlife
data
and
FCC
v.
the
Fox
agency
Television
has
examine[d]
Stations,
Inc.,
the
556
relevant
U.S.
502,
513
(2009)
An agencys
may
not
substitute
our
judgment
for
that
of
the
proposed
action.
Webster,
685
F.3d
at
421
(internal
[the]
agencys
environmental
analysis,
422
F.3d
at
186
for
any
(alteration
looking
in
original)
(internal
Statement]
analysis.
in
light
of
how
they
affect
the
entire
Id.
E.
Plaintiffs
principles
of
argue
NEPA
that
and
Defendants
engaged
in
violated
illegal
the
basic
segmentation
by
counter
that
[n]othing
in
NEPA
requires
an
[Environmental
Impact
[Record of Decision].
Statement]
at
the
time
it
issues
They maintain
Impact
Statement]
42
and
[Environmental
Assessment,]
by
conducting
full
end-to-end
study
of
is
distinct
from
approving
only
40 C.F.R. 1502.4(a).
the
impacts
of
the
entire
Projectincluding
those
parties
agree
that
the
studied
alternatives
are
adequately
analyzed
the
impacts
associated
with
the
five
complete
the
Project:
(1)
Parallel
Bridge
Corridor
With
(3)
Parallel
Bridge
(Preferred);
Bridge
Corridor
and
(5)
Corridor
With
Phased
Parallel
Approach/Rodanthe Nourishment.
With
All
Bridge;
Approach/Rodanthe
Bridge
Corridor
With
(4)
Bridge
Phased
Decision
that
committed
to
any
oneor
any
combinationof
at
least
alternatives,
with
Defendants
respect
have
to
the
neither
previously
attempted
to
press
that
the
Record
of
Decision
seems
to
44
J.A. 2500.
it
is
possible
to
read
such
statements
as
scope
of
what
their
NEPA
documents
have
analyzed
and
And
pursue
the
five
studied
alternatives
that
pass
through
for
future
could
example,
phases
change
of
so
Defendants
the
much
wait
Project,
that
the
too
long
conditions
current
to
on
implement
the
Hatteras
Island
Environmental
Impact
statements
their
in
Environmental
Assessment
Defendants
and
Record
of
IV.
A.
Unlike
NEPA,
unwiseagency
which
action[,]
prohibits
Robertson,
uninformedrather
490
U.S.
at
351,
than
Section
Section
4(f),
the
Secretary
of
Transportation
uses
alternative
to
unless
the
there
non-park
is
use
no
of
feasible
the
land.
and
prudent
Coal.
for
Responsible Regl Dev. v. Brinegar, 518 F.2d 522, 525 (4th Cir.
13
47
1975). 14
includes
the . . . wildlife
all
possible
and
planning
waterfowl
to
minimize
refuge[.]
49
harm
to
U.S.C.
303(c)(2).
The Secretary must perform a Section 4(f) evaluation and
comply
substantive
requirements
The same is
not
with
that
required,
applies.
provisions
however,
if
other
the
joint
planning
exception
that
uses
Section
4(f)
property
to
escape
the
48
Id.
Second, the
Section
4(f)
property
will
be
Id.
used
and
no
exception
applies, the Secretary must show that the project includes all
possible planning to minimize harm to the Section 4(f) property
and that no prudent and feasible alternatives are available.
49 U.S.C. 303(c)(1)-(2).
The all possible planning prong of the analysis cannot be
met until a projects design is complete.
Civic Assns v. Volpe, 459 F.2d 1231, 1239 (D.C. Cir. 1971).
all
possible
planning
to
minimize
harm
to
the
Section
If
4(f)
finalized
plan . . ., it
is
hard
to
see
how
the
Id.
49
23
find
imprudent,
an
the
alternative
Secretary
must
to
using
Section
determine
that
49
4(f)
the
property
impacts
or
adverse
effects
extraordinary
or
associated
unique.
with
See
id.
that
at
alternative
413.
The
are
Secretarys
alternative
routes
Hickory
Neighborhood
Overton
Park,
401
reach[]
Def.
U.S.
League,
at
413).
extraordinary
893
See
F.2d
at
also,
magnitudes.
61
(quoting
Monroe
Cnty.
Conservation Council, 472 F.2d at 700 ([A] road must not take
parkland, unless a prudent person, concerned with the quality of
the human environment, is convinced that there is no way to
50
F.2d at 526.
The
project
issued
Secretarys
must
and
be
completed
before
Alternatives,
Section
Inc.
work
v.
on
4(f)
before
the
Slater,
evaluation
the
Record
project
166
F.3d
of
the
of
entire
Decision
is
begins.
Corridor
368,
(D.C.
373
Cir.
The
and
shall
summarize
23 C.F.R. 774.7(a).
51
the
results
of
all
possible
4(f)
property,
the
Secretary
may
select
only
the
4(f)s]
774.3(c)(1).
factors,
preservation
This
determination
including:
impacts;
(2)
purpose.
(1)
the
23
involves
C.F.R.
balancing
several
adverse
the
ability
to
mitigate
relative
severity
of
the
harm
after
reasonable
mitigation,
the
magnitude
of
any
adverse
23
C.F.R. 774.3(c)(1)(i)(vii).
B.
In
reviewing
an
agencys
Section
4(f)
determination,
we
700
quotation
(internal
whether
the
Secretary
marks
acted
omitted).
within
the
First,
scope
of
we
his
consider
or
her
Overton
alternatives
to
using
Section
4(f)
property
existed.
Secretarys
choice
to
use
Section
4(f)
property
was
in
accordance
with
law.
Id.
(quoting
us
to
review
whether
the
Administrative
This determination
Secretarys
decision
was
factors
actually
support
the
Secretarys
determination.
marks
the
omitted).
Secretary
Finally,
followed
we
all
must
procedural
also
determine
requirements.
contend
that
the
district
court
erroneously
when
the
Refuge
was
created,
NC
12
had
not
They argue
yet
been
same
time,
as
Section
53
4(f)
property,
23
C.F.R.
exception
applicablethe
1942
Coast
Guard
map,
the
North Carolina highway maps from 1944 and 1949, the 1951 Senate
debate, the public law from 1951 authorizing DOI to grant an
easement to North Carolina, the 1954 quitclaim deed, and the
1954 easementprove nothing about the status of NC 12 when the
Refuge was established.
None of this
Instead, the
Id.
But the
Indeed, the
law
authorizing
DOI
to
grant
an
easement
to
North
Because
these
establishment
of
Refuge,
the
substantially
they
cannot
postdate
the
possibly
show
on
which
we
could
affirm
the
district
courts
In other words,
condemnation
proceedings
used
by
the
United
States
to
time
require
an
that
the
odyssey
Refuge
was
into
the
established.
facts
of
But
the
that
will
condemnation
55
not
subject
to
Section
4(f)s
substantive
4(f)
analysis
is
irrelevant
if
the
Because a
joint
planning
V.
For the foregoing reasons, we affirm the district courts
grant of summary judgment regarding Plaintiffs NEPA challenge,
and we reverse the district courts grant of summary judgment
regarding Plaintiffs Section 4(f) challenge.
We remand this case for further proceedings in accordance
with
this
opinion.
Specifically,
56
the
district
court
must
formally
reserved
before
or
at
the
same
time
that
the
whether
when
alternative
existed. 15
it
to
FHWA
acted
determined
the
use
of
in
an
that
Refuge
arbitrary
no
and
prudent
property
for
capricious
and
the
feasible
Project
determination
regarding
the
lack
of
prudent
and
feasible
15
57
whether FHWA has selected the alternative that causes the least
overall harm to the Refuge.
To the extent the district court previously analyzed the
substantive requirements of Section 4(f), we expressly vacate
that analysis
legal
and
framework
determinations
thorough,
instruct
set
Secretarys
requirements.
forth
enumerated
probing,
the
in
above,
indepth
determination
district
court
this
opinion,
and
engage
review
to
complies
to
with
in
follow
the
make
the
the
ensure
requisite
that
Section
the
4(f)s
700.
AFFIRMED IN PART,
REVERSED IN PART,
AND REMANDED
58