Professional Documents
Culture Documents
R35 Capital Budgeting
R35 Capital Budgeting
Capital Budgeting
www.irfanullah.co
Contents
1. Introduction
2. The Capital Budgeting Process
3. Basic Principles of Capital Budgeting
www.irfanullah.co
1. Introduction
Capital budgeting is the process that companies use for decision making
on long-term projects
Capital budgeting
helps decide the future of many corporations
can be adapted for many other corporate decision such as investment in
working capital, leasing, mergers and acquisitions
www.irfanullah.co
Project Categories
Replacement projects
Expansion projects
New products and services
Mandatory projects
www.irfanullah.co
www.irfanullah.co
Key Concepts
Sunk cost (not included in investment appraisal)
www.irfanullah.co
Project Sequencing
www.irfanullah.co
www.irfanullah.co
www.irfanullah.co
10
Example
Cost of Capital = 10%
Expected Net After Tax Cash Flows
Year (t)
Project A
Project B
- $1,000
- $1,000
500
100
400
300
300
400
100
600
Answer:
NPV for A = 78.82; NPV for B = 49.18
www.irfanullah.co
11
Display
CF0= 0
1000 [][ENTER]
CF0 = -1000
[] 500 [ENTER]
C01= 500
[]
F01= 1
[] 400 [ENTER]
C02= 400
[]
F02= 1
[] 300 [ENTER]
C03= 300
[]
F03= 1
[] 100 [ENTER]
C04= 100
[]
F04= 1
[NPV] 10 [ENTER]
I = 10
[] [CPT]
NPV= 78.82
www.irfanullah.co
12
IRR is the discount rate that makes the present value of the future cash flows equal
to the investment outlay; we can also say that IRR is the discount rate which makes
NPV equal to 0.
13
Example
Cost of Capital = 10%
Expected Net After Tax Cash Flows
Year (t)
Project A
Project B
- $1,000
- $1,000
500
100
400
300
300
400
100
600
Answer:
IRR of A = 14.49% ; IRR of B = 11.79%
www.irfanullah.co
14
Display
CF0 = 0
1000 [][ENTER]
CF0 = -1000
[] 500 [ENTER]
C01 = 500
[]
F01 = 1
[] 400 [ENTER]
C02 = 400
[]
F02 = 1
[] 300 [ENTER]
C03 = 300
[]
F03 = 1
[] 100 [ENTER]
C04 = 100
[]
F04 = 1
[IRR] [CPT]
14.49
www.irfanullah.co
15
16
Drawbacks:
Does not consider any cash flow beyond payback period
Poor measure of profitability
www.irfanullah.co
17
Example
Year
0
Project C -800
1
340
2
340
3
340
4
340
Compute the payback period and discounted payback period assuming a rate of 10%.
www.irfanullah.co
18
www.irfanullah.co
19
20
Project X
-400
160
160
160
160
www.irfanullah.co
21
Crossover
Draw the NPV profiles for Projects X and Y. Discuss the significance of the
cross over point.
Year
Project X
-400
160
160
160
160
Project Y
-400
800
www.irfanullah.co
22
Example
The initial investment on a project is 200. The after-tax cash flows from this project are 80 annually for
four years. Improvements on the project equipment increase the cost by 30 and the after-tax cash flows
by 10. What is the impact on the NPV profile?
A. Vertical intercept shifts up and horizontal intercept shifts left
B. Vertical intercept shifts up and horizontal intercept shifts right
C. Vertical intercept shifts down and horizontal intercept shifts right
www.arifirfanullah.com
23
Conventional
Cash Flows
Project A
Project B
Conventional
Cash Flows
Conventional
Cash Flows
Project C
OR
Project D
24
1
160
2
160
3
160
4
160
Project Y -400
800
NPV
IRR
Which project do you select according to the NPV rule using a rate of 10%?
Which project do you select according to the IRR rule?
Show the NPV profile for both projects.
www.irfanullah.co
25
1
100
2
100
3
100
4
100
Project D -800
340
340
340
340
NPV
IRR
Which project do you select according to the NPV rule using a rate of 10%?
Which project do you select according to the IRR rule?
Show the NPV profile for both projects.
www.irfanullah.co
26
Example
For the projects shown below what discount rate would result in the same NPV? The required rate of
return is 10%.
A. A rate between 0% and 10%
B. A rate between 10% and 25%
C. A rate between 25% and 35%
Year
NPV
IRR
Project C
-200
100
100
100
100
117
35%
Project D
-800
340
340
340
340
278
25%
www.irfanullah.co
27
Cash Flow
-200
1,000
-1,200
Show the NPV profile for this project? Hint: use these
rates: 0%, 50%, 100%, 150%, 200%, 250%
Time
Cash Flow
100
-300
250
www.irfanullah.co
28
IRR
Advantages
Shows the return on each dollar invested
Allows us to compare return with the
required rate
Disadvantage:
Does not consider project size
Disadvantage:
Incorrectly assumes that money is
reinvested at IRR rate
Might conflict with NPV analysis
Possibility of multiple IRRs or no IRR for
a project
www.irfanullah.co
29
www.irfanullah.co
30
www.irfanullah.co
31
Example
A company is undertaking a project with a NPV of $500 million. The company
currently has 100 million shares outstanding and each share has a price of $50.
What is the likely impact of the project on the stock price?
www.irfanullah.co
32
Summary
Capital budgeting process
NPV calculation and NPV rule
33
Conclusion
Read summary
Review learning objectives
www.irfanullah.co
34