Professional Documents
Culture Documents
Coal Nswec Caroona ProjectDescriptionandPreliminaryEnvironmentalAssessment PDF
Coal Nswec Caroona ProjectDescriptionandPreliminaryEnvironmentalAssessment PDF
Contents
1. Introduction
1.1 Purpose and Structure of this Document
1.2 Background
2. Local and Regional Context
2.1 Location and Mining Tenements
2.2 Land Use and Built Features
1.3 Project Overview
2.3 Topography and Water Resources
2.4 Environmentally Sensitive Areas
3. Project Description and Justification
3.1 Proponent
3.2 Exploration Activities, Geological Features and Coal Resource
3.3 Project General Arrangement
3.4 Development Activities
3.5 Underground Mining Operations
3.6 Product Coal Stockpiling, Handling and Transport
3.7 Water Management Infrastructure and Services
3.8 Power Supply
3.9 Workforce
3.10 Rehabilitation Activities, Remediation Works and Offsets
3.11 Consideration of Alternatives and Project Justification Overview
4. Planning Considerations
4.1 Applicability of Division 4.1 of Part 4 of Environmental Planning
and Assessment Act, 1979
4.2 Planning Provisions
4.3 Planning Strategies
4.4 Permissibility of the Project
5. Preliminary Environmental Assessment
5.1 Overview
5.2 Level and Scope of Assessment
5.3 Gateway Application Assessments
6. Stakeholder Consultation
6.1 Consultation Undertaken to Date
6.2 Stakeholder Engagement Programme
7. References
Attachment A Preliminary Schedule of Lands
1
1
1
4
4
4
4
7
7
8
8
8
8
11
11
12
12
12
12
13
13
14
14
14
15
15
16
16
16
16
21
21
22
23
24
Contents
continued
LIST OF TABLES:
Table 1 Overview of the Caroona Coal Project
Table 2 Key Potential Environmental Issues, Required Level and
Scope of Environmental Assessment and Preliminary Strategies
to Address Potential Impacts
LIST OF FIGURES:
Figure 1 Regional Location
Figure 2 Aerial Photograph of the Project Area and Surrounds
Figure 3a Relevant Land Ownership
Figure 3b Relevant Land Ownership List
Figure 4 Indicative Mining Layout and Surface Infrastructure
Figure 5 Environmental Monitoring Sites
LIST OF PLATES
Plate 1 Doona Ridge
Plate 2 Example of Subsidence Remediation
Plate 3 Soil Investigation
Plate 4 Soil Sampling Field Day
10
18
2
3
5
6
9
17
1
13
21
22
1. Introduction
1.1 Purpose and Structure of this Document
1.2 Background
Within the 344 square kilometres (km2) EL 6505, BHP Billiton has
identified three targeted exploration areas at Doona Ridge
(Plate 1), Nicholas Ridge and Georges Island totalling 126 km2.
Although there are significant coal deposits outside of these
areas, BHP Billiton has focused exploration on the targeted areas
because of the potential for longwall mining subsidence to
adversely impact the alluvial plains which characterise the lands
outside of the targeted areas and is often used for irrigated
cropping.
This application includes proposed longwall mining underneath
the Doona Ridge and Nicholas Ridge targeted exploration areas
(Figure 2) which total approximately 119 km2. Through focusing
proposed underground mining operations under these elevated
and gently sloping lands, and with the implementation of other
mitigation measures, the Project has been designed to minimise
impacts on the alluvial plains.
The Project will also be referred to the Federal Minister for the
Environment to determine whether the Project is a Controlled
Action and requires approval under the Commonwealth
Environment Protection and Biodiversity Conservation Act, 1999
(EPBC Act).
In parallel, BHPBilliton seeks DGRs from the DirectorGeneral of
the NSW Department of Planning and Infrastructure (DP&I) to
inform the EIS.
It is anticipated that the DGRs will be prepared by the DP&I in
consideration of:
this document;
any key issues raised by State regulatory agencies following
their review of this document;
the recommendations of the Gateway Panel set out in a
conditional Gateway Certificate; and
the decision of the Commonwealth Minister for the
Environment regarding the referral under the EPBC Act.
NARRABRI
URALLA
SHIRE COUNCIL
BARRABA
NARRABRI
SHIRE COUNCIL
Narrabri Coal Mine
Maules Creek
Coal Project
Boggabri
Coal Mine
Tarrawonga
Coal Mine
Canyon
Coal Mine
BOGGABRI
MANILLA
Rocglen
Coal Mine
TAMWORTH
REGIONAL COUNCIL
Vickery Coal
Project
CARROLL
Sunnyside
Coal Mine
GUNNEDAH
KOOTINGAL
MOONBI
TAMWORTH
CURLEWIS
Watermark
Coal Project
WERRIS CREEK
Werris Creek
Coal Mine
NUNDLE
QUIRINDI
MURRURUNDI
COOLAH
LEGEND
Town
Protected Lands
NSW State Forest
Native Vegetation
Local Government Area Boundary
Exploration Licence (EL 6505)
Mine Site
0
12
18
24
MERRIWA
ABERDEEN
30
Kilometres
Source: Geoscience Australia (2006); NSW
Department of Premier and Cabinet, Office of
Environment and Heritage (2011) and Minerals
NSW (2012)
SCONE
MUSWELLBROOK
Mangoola
Coal Mine
Muswellbrook No.2
Coal Mine
DENMAN
C A R O O N A
C O A L
P R O J E C T
FIGURE 1
Regional Location
HVE-13-02_PEA_201B
300
450
0
40
HVE-13-02_PEA_202A
k
Cree
400
0
Source: Land and Property Management Authority - Topograpraphic40Base
2010 and
Orthophoto (Curlewis 2011 & Tamworth 2010)
Kilometres
K RAI
LW AY
400
400
LEGEND
0
Exploration Licence (EL 6505)45
Targeted Exploration4Area
50
350
350
0
35
0
35
30
35
0
WERRIS
CREE
Doona Ridge
35
0
40
0
40
40
BINNAW
AY
Coonabarabran Road
350
400
0
35
45
300
Caroona
300
a Ro
450
6520000
300
EL 6505
300
rin
ewa
Willi
400
0
40
350
30
6530000
400
45
450
ama
Yarr
400
35
0
Road
RI
VE
R
Mystery
Nicholas Ridge
35
0
bran R
Road
Bundella
Coonab
ara
400
Waverley Road
Wer
ris
300
oa d
35
Cree
k
C O A L
Aerial Photograph of the
Project Area and Surrounds
FIGURE 2
C A R O O N A
Quirind
i
0
35
350
300
250000
300
400
300
0
450
35
260000
I
OK
MO
WAY
HIGH
300
300
Waverley Road
300
260000
300
6520000
P R O J E C T
Creek
oad
Gap R
6530000
350
300
AROI
350
250000
L
KAMI
300
450
400 350
ad
0
35
400
1. Introduction
continued
The land within the Project area is primarily used for agricultural
and rural residential purposes. Agricultural enterprises include
cattle grazing and both dryland and irrigated cropping.
The Caroona Feedlot owned by JBS Australia, located to the
south-west of the Doona State Forest within the Project area, is
a 23,500head capacity, 1,390hectare (ha) feedlot, which
includes a number of holding yards, sheds, mills, silos and other
associated infrastructure. Figures 3a and 3b show local land
ownership, including the Caroona Feedlot owned by
JBS Australia.
The most common enterprises within the Project underground
mining area are producing cattle (weaners/vealers) on natural
pastures and dryland cropping (La Tierra, 2014). There are also a
number of dryland and irrigated cropping enterprises within the
Project area, predominantly located in the southern portion of
the Doona Ridge, and the eastern portion of the Nicholas Ridge
underground mining area. Parts of the underground mining area
are comprised of denser woodland vegetation (generally on the
steeper slopes), including the Doona State Forest, which are
occasionally used to graze cattle.
Surrounding the Project area are alluvial plains which are often
used for dryland and irrigated cropping.
240000
99
116
143
143
116
143
143
69
30
30 28
116
118
143
143
143
118
118
69
190
118
118
117
11
143
143
143
101
73
101
73
117
117 118
31
117
118
29
29
117
118
118
117 118
118
30
11
29
29
101
101
73
73
118
29
31
48
152
152
152
152
17
Road
152
107
17
152
152
152
152 152
152
152
152
152
17
152
Tribella
152
17
107
107
152
132
17
162
161
17 162
161
17
161
161
152
152
22
161
72
152
161
161
29
48
48
150
83
72
161
121
161
166
50
2003
57
111 111
111
135 111
135
57
Road 57
49
135
135
83
158
121
131
83
Road
75
83
83
2001
131
83
158
18
111
57
57
160
2003
70
2001 126
135
135
158
121
121
oad
4D R
158
27
135
135
135
31 29
48
2004
161
31
29
29
11
101
152
21
48
27
27
48
48
48 Rossmar Park
101
11
11
101
101
189
101
2004 116 2004
101
Coonabarabran
BINNAWAY
WERRIS CREE
4
K 2004
4
55
83
2004
4
RAILWAY
54
2004
190
55
83
152
54
171
99
143
143
28
31
28
28
EL 6505 28
28
11
27
27
27
23
18
57
70
139
2003
71
126
35
35
160
160 160
160
Caroona
93
18
70
156
156 2003
2003
156 7 7
149
156
18
56
56
130
130
160
164
160
160
Pine Ridge
160
18
56
130
40
127
115 8
26
128
51
5 2004
38
rina
112
125
86
125
125
129
129
125
129
2004
81
2003
6
6
98
45
19
87
13
13
2004
125
92
95
95
Road
92
24
24
24
Road
125
125
41
86
6 68
134
163
66
2003
2003
2003
124
66
133
59
2005
60
113
124
64
67
67
114
114
114
114
144
12
RA
ILW
AY
63
63
158
122
94
14
103 14
46
78
7778 84
14 46 85
124
123
62
66
62
AY
62 66 K RAILW
62
CREE
IS
R
66
R
E
W
WA Y
BINNA
66
64 64
HIG 63
HW
AY
66
64
64 64
64
64
114
108
102
102
Werris Creek
LEGEND
Exploration Licence (EL 6505)
State Forest
Crown Land
6520000
Coal Mines Australia Pty Ltd
Conceptual Surface Infrastructure Area
Indicative Underground Mining Layout
Gap Road
6530000
Roa
44 90
44
68 61 61 d
6 68 68 61
61
44 90
61
6 61 61
43
138
90
138
58
95
138
43 43
0
1
2
3
4
5
95
58
95 136
136
138
95
95
Kilometres
136
136
136
GDA 94 MGA Zone 56
95
136
92
42 Source: Land and Property Management Authority (2010) and
110 134
24
163
2003
66
2003
2004
41
108
108
102
a
dell
FIGURE 3a
Bun
Note: Other minor ancillary infrastructure such as water and
Relevant Land Ownership
gas management infrastructure would be required,
(Refer Figure 3b for Details)
however their locations are not shown.
19
19
19
bara
bran
157
108W 108
108
ERR
IS
CR 108
128
2004 EEK
108
128
MU
86
86
86 2004 NGIN
DI
86
41
41
2004
86
86
Waverley
125
129
128
125
Coon
a
129
129
129
40
Breeza
2004 126
163
126
37 36
126
79
2004 126
2004 37
36 39 126 126
79 33
34
74 74
2003
32
20
79
170
20
34
39
137 137
32 32
74
137 137
32
137
32
137
98
2
Road
HVE-13-02_PEA_203B
6520000
Spring Ridge
State Forest
Spring Ridge
6530000
31
31
31
Road
Breeza
State Forest
Clift
Park
Rossmar
Roa
iewa
Will
R
RIVE
250000
Road
I
OK
MO
Wa
Road
240000
AROI
WA
270000
250000
Mystery
260000
L
KAMI
erle
y
270000
I
RO
260000
IL A
KAM
H
HIG
Fisher ME & GC
Fisher ME, GC & HR
Fisher RC
Fletcher BI & VR
Frofour Pty Ltd
Fuller JW & RM
Fullers Transport Pty Ltd
G.S.S.H Pty Ltd
Carbon Minerals NL
Glencohen Pty Ltd
Coal Mines Australia Pty Ltd
SCMB Pty Ltd and BGI Pty Ltd
Green T
Green TD
Hamlin CR & VJ
Hamblin NJ
Hamblin RJ, FJ, PG & NJ
Graham JW, Smith MEL
Hanuta Pty Ltd
Hickman JM
Hickman SSM & Ross-Hickman DS
Holifall Pty Ltd
Hurley JK
Ingall IG,Lyttle KN,Cohen RJF,Squires JA,Bruce JHP,Hosking J
Church - Croaker, AMA; Croaker, GDH; and James, MJ Trustees
Jarret H & M
Shenhua Watermark Coal Pty Ltd
Karapiti Holdings Pty Ltd
Pursehouse Properties Pty Ltd
Lawlor MW & Gorsch JB
Lindenow Pastoral Company Pty Limited
Hollis M & V
Lingard TL
Bailey TN
Malden J
Maraig Pty Ltd
Maylan Pty Ltd
McBeth W & PE, & AJ
McIlrick TW & JA
Bradfield NG & MJ
Shenhua Watermark Coal Pty Ltd
Shenhua Watermark Coal Pty Ltd
Mills RA Estate:Perpetual Lease
Moore GN & JC
Munro NM
Murphy PJ & KN
Pursehouse Properties Pty Ltd
N.R.L.F Pty Ltd
AR Grant Estate Perpetual Lease
Newcombe IR
Nicholson RP
Nilwon Pastoral Co Pty Ltd
Norman CF
Norman GS
NSW Grain Corporation Ltd
Penick RE
Permaid Pty Ltd
Pike CT
Pike CT & VL
Pike MG & CT
Piper SL & MJ
Priestley JC & CL
Pursehouse AL
Pursehouse AL & CI
Pursehouse Investments Pty Ltd
Pursehouse Properties Pty Ltd
Rado Ranch Pty Limited
Ranken DCL,HRL & JWL
Rex Fisher Pty Ltd
RG & HD Thompson Pty Ltd
Rossmar Park Pastoral Co Pty Ltd
Rutter EO & SA
Rutter PR
Rutter RA & DA
Ryan WH & EC
Frankham DR & DW
Seymour MG & CL
Seymour MG & Lingard CL
Single Tree Pty Ltd
Small HR
Shenhua Watermark Coal Pty Ltd
Stackman BA & Lingard KL
Tandim Investments Pty Ltd
Taylor MG Estate
Todman, Anthony Reginald & Jennifer Ruth
Thyrek Pty Ltd
Shenhua Watermark Coal Pty Ltd
Tribella Pty Ltd
Trustees Of The Roman Catholic Church,
Diocese of Armidale
Shenhua Watermark Coal Pty Ltd
Wadwell KG & SN
Walhallow Local Aboriginal Land Council
Walhallow Murri Enterprise Aboriginal Corporation
Wallalla Holdings Pty Limited
Warren CS
Williewarina Pty Ltd
Willis SNB & RNB
Willis SN & MJ
Wilson BM & E
The Peel-Cuningham County Council
Doona State Forest
Coal Mines Australia Pty Ltd
Elsley FE & DE
Willis
Shenhua Watermark Coal Pty Ltd
TS&CR 32492
Penunga Pty Ltd
Doona State Forest
State of NSW
State Rail Authority
The Council of The Shire of Tarmang
The Minister for Public Roads
C A R O O N A
C O A L
P R O J E C T
FIGURE 3b
Relevant Land Ownership List
(as at 10 February 2014)
HVE-13_02 _PEA_001A
3.1 Proponent
Website: http://www.bhpbilliton.com
a Ro
250000
Creek
HVE-13-02_PEA_204B
LEGEND
Exploration Licence (EL 6505)
Conceptual Surface Infrastructure Area
Conceptual Rail Infrastructure Alignment
Indicative Underground Mining Layout
rin
ewa
Willi
ER
RIV
Caroona
260000
Kilometres
K RAI
LW AY
KI
MOO
man
WERRIS
CREE
Coonabarabran Road
260000
Mystery
Road
Bundel
arabra
n Ro
ad
Quirind
i
Cree
k
C A R O O N A C O A L
FIGURE 4
Note: Other minor ancillary infrastructure such as water and gas
management infrastructure would be required, however Indicative Mining Layout and
Surface Infrastructure
la Road
their locations are not shown.
Coonab
Waverley Road
Wer
ris
WAY
HIGH
Source: Land and Property Management Authority - Topograpraphic Base 2010 and
Orthophoto (Curlewis 2011 & Tamworth 2010)
ra
Yar
BINNAW
AY
AROI
6520000
6530000
EL 6505
L
KAMI
ad
Waverley Road
250000
6520000
P R O J E C T
Creek
oad
Gap R
6530000
Project
Mine Life
Mining Areas
Hours of Operation
Development and operation of a mine infrastructure area comprising administration offices, bathhouse,
workshop, store, coal stockpile areas, bunded hydrocarbon tanks, laydown areas, car parking, electrical
substation and associated linear infrastructure and access road on Doona Ridge.
Development and operation of a men and materials shaft on southern Doona Ridge with access off
4D Road.
Development and operation of a mine infrastructure area comprising coal stockpiles, bathhouse, car
parking, administration offices, linear infrastructure and an access road on Nicholas Ridge.
Road access to Doona Ridge off Rossmar Park Road and Nicholas Ridge off Waverley Road.
Construction and operation of train load-out facilities including a rail spur and loop at Doona Ridge and
Nicholas Ridge.
Construction and operation of coal handling infrastructure on Doona Ridge for sizing and handling of coal,
incorporating an event CPP (1 Mtpa ROM coal capacity) for washing of occasional high-ash ROM coal.
Construction and operation of coal handling infrastructure on Nicholas Ridge for sizing and handling of
coal.
Development and operation of a rail spur and loop and coal loading infrastructure on both Doona Ridge
and Nicholas Ridge to allow access to the Binnaway-Werris Creek Railway.
Construction and operation of a coal unloading facility on Doona Ridge to allow the transportation of
high-ash ROM coal from Nicholas Ridge to Doona Ridge for washing at the CPP.
Co-disposal of fine and coarse rejects in an emplacement on Doona Ridge, with rejects to be transported
within an infrastructure corridor.
Development of ventilation shafts and gas drainage infrastructure.
Construction and operation of a connecting gas pipeline between infrastructure areas.
Development of a water management system comprising of water storages, sumps, pumps, pipelines,
sediment control, mine dewatering and sewage treatment.
Development of a water management strategy based on a detailed site water balance which may include
reuse of water on-site, storage of water on-site, licensed water extraction for water supply and/or
treatment and beneficial use or controlled licensed release of excess water.
Construction and operation of a connecting water pipeline between Doona Ridge and Nicholas Ridge.
24 hours per day, seven days per week, including drift construction and development.
Operational Workforce
Exploration
Power Supply
Construction Workforce
Construction and use of internal power reticulation infrastructure (substations and internal transmission
lines) as required.
Construction and operation of a 132 kV electricity transmission line from the Werris Creek substation to the
Caroona Coal Project (subject to separate approvals).
Monitoring of subsidence and subsidence impacts over the proposed underground mining and mine
development areas.
Progressive rehabilitation of surface disturbance areas (e.g. exploration drill pads).
Ongoing remediation of subsidence effects.
Rehabilitation of mine related infrastructure areas at the end of the Project life.
Average number of construction employees approximately 400 with up to 600 at peak construction.
surface conveyors;
CPP;
train load-out facility including rail spur and loop; and
ROM and product coal stockpiles.
3.9 Workforce
Project Justification
4. Planning Considerations
4.1 Applicability of Division 4.1 of Part 4 of
Environmental Planning and Assessment
Act, 1979
Mining SEPP;
State Environmental Planning Policy No. 33
Hazardous and Offensive Development (SEPP33);
State Environmental Planning Policy No. 44
Koala Habitat Protection; and
State Environmental Planning Policy No. 55
Remediation of Land.
The Gunnedah LEP and Liverpool Plains LEP are discussed further
in Section4.4.
4. Planning Considerations
continued
(1) Mining
Development for any of the following purposes may be carried
out only with development consent:
(a) underground mining carried out on any land,
(b) shafts, drill holes, gas and water drainage works, surface
rehabilitation works and access pits associated with that
mining (whether carried out on or beneath the earths
surface),
but does not include open cut mining.
300
6530000
350
6520000
450
!
(
k
Cree
400
0
Source: Land and Property Management Authority - Topograpraphic
Base 2010 and
40
Orthophoto (Curlewis 2011 & Tamworth 2010)
+ C23
U
K RAI
LW AY
+
U
C243
35
0
35
0
C168a
!
( SW14
+ C17
U
LEGEND
50
Exploration Licence (EL46505)
Targeted Exploration
Area
50
0
35
#
*
50
+
U
C282a
+ C76
U
DDG05 #
*
#
* Air Quality
+ Groundwater
U
DDG09
#
*
300
+
U
+C285
U
C102
300
+ GW030380
U
+
U
!
( SW03
GW030078
!
(
RI
VE
R
SW11
Meteorological Station
+
U
300
C78a
C153a U
+
+
U
30
0
C11 U
+
DDG07
bran R
Road
Bundella
Coonab
ara
400
+ C162
U
Nicholas Ridge
#
*
GW030083
+
U
!
(
SW13
Waverley Road
C50
!
( U
+
+
U
+ GW030012
U
!
( Surface Water
!
( SW01
+ GW030010
U
+ C199
U
+ C37
U
#
* DDG06
Doona Ridge
35
+
U
#
*DDG03 +
U50
350
#
* DDG02
+
U
C193a
C188-1
400
SW08
WERRIS
CREE
+
U
400
!
(
0
35
Kilometres
BINNAW
AY
+ GW965576 !
U
(
+
U
C43
SW09
Coonabarabran Road
*DDG08
C151 U
+#
+
U
C180a
C119a
40
0
40
Yarraman Creek
#
* DDG01
350
+ C137
U
SW06
30!
(
0
ad
HVE-13-02_PEA_206C
Mystery
Road
a Ro
SW07
350
35
0
+ C113
U
450
0
40
400
Wer
ris
C268-3 U
+
oa d
Quirind
i
GW030063
Creek
C O A L
Environmental Monitoring Sites
FIGURE 5
35
C A R O O N A
+
U
Cree
oad
Gap R
6530000
350
EL 6505
250000
300
30
#
*
400
rin
ewa
Willi
35
300
400
300
400
0
35
450
n
300
Waverley Road
450
45
!
(
P R O J E C T
!
(
SW16
6520000
SW12
450
400
450
300
0
35
260000
ama
Yarr
350
#
*
300
#
*
250000
300
400
300
350
#
*
#
*
I
OK
MO
300
Y
HWA
40
0
260000
I HIG
400 400
LARO
KAMI
300
450
350
350
450
400
400
Impacts on agricultural
land resources.
Potential impacts of
surface water flow and
flood regimes in the
Mooki River as a result
of the rail spur.
Detailed flood impact assessment, including hydrologic modelling, Investigation of design opportunities to minimise impacts on local
and regional flood regimes (i.e. consideration of flood impacts
which identifies impacts on local and regional flood regimes,
during design of infrastructure).
including consideration of flood levels and extent and flow
velocities and distribution.
Investigation of measures to avoid, mitigate, monitor and/or offset
the potential impacts of the Project.
Expert Peer Review of the assessment.
Potential impacts on hydrology Detailed site water balance for the Project incorporating all sources
Impacts on surface
of water inflow to demonstrate sufficient water for mine
and surface drainage regimes,
water resources as a
operations.
result of subsidence and including localised effects on
site water management. water quality and/or persistence Development of a water management strategy for the life of the
of low flows.
Project and assessment of potential impacts.
Potential impacts on ephemeral Assessment of potential subsidence effects on streams and
drainage lines including
potential for subsidence induced impacts.
potential cracking, change in
Groundwater assessment, including numerical modelling of
alignment and/or acceleration
potential impacts on groundwater users and baseflow
of erosion processes.
contributions to local watercourses.
Surface water assessment of potential impacts of predicted
subsidence effects and changes in baseflow contribution.
Investigation of measures to avoid, mitigate, monitor and/or offset
the potential impacts of the Project.
Expert Peer Review of the assessment.
Potential depressurisation of
Impacts on
coal seam aquifers as a result of
groundwater resources.
dewatering of the coal seam to
facilitate underground mining
leading to potential effects on
overlying groundwater system.
Potential impacts on other
groundwater users in the
vicinity of the Project and
potential reduction in baseflow
contributions to local
watercourses.
Key Potential
Environmental Issue
Table 2. Key Potential Environmental Issues, Required Level and Scope of Environmental Assessment and Preliminary Strategies to Address Potential Impacts.
Impacts on ecology as a Potential impacts of vegetation Comprehensive flora and fauna surveys of the disturbance area in
accordance with relevant survey guidelines.
disturbance associated with the
result of vegetation
Project including potential
disturbance.
Assessment of potential impacts on any terrestrial and aquatic
disturbance of threatened flora
species, populations, ecological communities or their habitats.
species and potential loss of
Assessment
of alternative locations of surface infrastructure in
fauna habitat.
consideration of potential impacts on ecology.
Identification of measures that would be implemented to maintain
or improve the biodiversity values of the surrounding region in the
medium to long-term.
Subsidence related
impacts on key built
infrastructure and
residences.
CONTINUED
Impacts on heritage as
a result of subsidence
and direct disturbance.
Key Potential
Environmental Issue
Table 2. Key Potential Environmental Issues, Required Level and Scope of Environmental Assessment and Preliminary Strategies to Address Potential Impacts.
CONTINUED
Modelling and assessment of potential noise impacts as a result of Reasonable and feasible mitigation measures on-site to minimise
Potential noise impacts
Noise impacts on the
noise generation during construction and operation.
mining operations, including road and rail traffic.
surrounding community. resulting from Project related
mining activities as well as road Assessment of potential cumulative impacts resulting from the
Noise monitoring network.
and rail movements.
Project and nearby developments and mines.
Acoustical mitigation at receivers where required (which may
include measures such as enhanced glazing, insulation and/or
Investigation of measures to avoid, mitigate and/or monitor the
air-conditioning), in consultation with the relevant landowner.
potential impacts of the Project.
Negotiated agreements with landowners where required.
Key Potential
Environmental Issue
Table 2. Key Potential Environmental Issues, Required Level and Scope of Environmental Assessment and Preliminary Strategies to Address Potential Impacts.
6. Stakeholder Consultation
6.1 Consultation Undertaken to Date
6. Stakeholder Consultation
continued
7. References
BHP Billiton (2006a) Exploration Environmental Management
Plan for the Caroona Project EL 6505, July 2006.
BHP Billiton (2006b) Review of Environmental Factors for
Exploration Borehole C44
Caroona Exploration Area.
BHP Billiton (2007) Review of Environmental Factors for Caroona
Exploration Program Reconnaissance Drilling and Associated
Activities 2007 to 2011, September 2007.
BHP Billiton (2009) Review of Environmental Factors for Caroona
Exploration Program Exploration Drilling and Associated
Activities 2009 to 2011, March 2009.
BHP Billiton (2010a) Review of Environmental Factors for
Caroona Exploration Program
EL6505 3D Seismic Survey 2010, October2010.
BHP Billiton (2010b) Review of Environmental Factors for
Caroona Exploration Program
EL6505 3D Seismic Survey 2010 Addendum, December 2010.
BHP Billiton (2011a) Review of Environmental Factors for
Caroona Exploration Program
Large Diameter Boreholes 2011, April 2011.
BHP Billiton (2011b) Caroona Exploration Program REF for
Large Diameter Boreholes 2011, June 2011 Classification of
Issues. Addendum to the original REF dated April 2011.
Department of Environment and Conservation (2004) Interim
Community Consultation Requirements for Applicants.
Department of Environment and Conservation, (2005) Draft
Guidelines for Aboriginal Cultural Heritage Impact Assessment
and Community Consultation.
Department of Environment, Climate Change and Water (2010)
Aboriginal Cultural Heritage Consultation Requirements for
Proponents 2010.
Department of Trade, Investment, Regional Infrastructure and
Services, Division of Resources and Energy (2014) Gunnedah
Basin Geological overview.
Website: http://www.resources.nsw.gov.au/ geological/overview/
regional/sedimentary-basins/gunnedah.
Accessed: 9 January 2014.
Gunnedah Shire Council (2012) Gunnedah Community Strategic
Plan 2012-2022.
HydroSimulations (2014) Caroona Coal Project Gateway
Application Preliminary Groundwater Assessment.
La Tierra (2014) Caroona Coal Project Gateway Application
Agricultural Impact Assessment.
McKenzie Soil Management (2014) Agricultural Resource
Assessment for Gateway Application: Caroona Coal Project.
Mine Subsidence Engineering Consultants (2014) Caroona Coal
Project Gateway Application Subsidence Assessment.
Namoi Catchment Management Authority (2012) Namoi
Catchment Management Authority Extractive Industries Policy.
Namoi Catchment Management Authority (2013) Namoi
Catchment Action Plan 2010-2020.
NSW Government (2012) New England North West Strategic
Regional Land Use Plan. Released September 2012.
NSW Government (2013) Interim Protocol for Site Verification
and Mapping of Biophysical Agricultural Land.
NSW Office of Water (2012) NSW Aquifer Interference Policy.
Project Description and Preliminary Environmental Assessment 23
Tenure Type
Freehold
Freehold
Lot Number
14
15
7005
16
1
5
6
7
8
9
10
11
12
13
14
1
2
1
2
3
859
1
1
2
1
2
3
4
5
8
9
1
1
2
3
3
4
5
1
2
2
1
1
Deposited
Plan
Number
Tenure Type
Lot Number
Deposited
Plan
Number
44196
Freehold
356063
44196
96311
111786
114872
114872
114872
114872
114872
114872
114872
114872
114872
114872
114872
129778
129778
131920
131920
131920
131937
131971
133607
133607
133608
133608
181826
181826
181826
181826
181826
188016
245275
245275
245275
254049
254419
254419
254511
254511
254647
254715
300039
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
98
Freehold
99
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
102
1
192
27
28
41
57
62
63
70
72
78
356063
366686
366686
366686
366687
367398
367399
367399
367400
377642
406517
433533
433533
433533
435063
435063
450224
450224
510667
510667
575271
582892
582892
595873
595873
612664
612664
614451
628700
628700
654494
725841
751018
751032
751032
751032
751032
751032
751032
751032
751032
751032
Tenure Type
Lot Number
Deposited
Plan
Number
Freehold
80
751032
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
79
81
82
83
84
85
86
87
88
89
90
109
117
118
128
129
135
150
158
1
3
4
6
12
13
35
36
82
83
114
116
117
122
124
199
200
201
202
203
204
205
206
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
751032
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
755494
Tenure Type
Lot Number
Deposited
Plan
Number
Freehold
210
755494
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
Freehold
207
211
212
213
215
217
19
51
52
99
177
178
1
3
6
15
16
17
18
22
23
32
33
34
36
64
65
66
67
70
71
74
75
82
96
97
99
101
104
171
172
310
755494
755494
755494
755494
755494
755494
755520
755520
755520
755520
755520
755520
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
755529
Tenure Type
Lot Number
Deposited
Plan
Number
Freehold
837358
Freehold
Freehold
Freehold
Freehold
Freehold
33
2
1
2
1
41
7001
1
2
3
1
2
1
2
3
4
7017
1
7005
1
1
2
3
2
6
7302
837193
837358
848069
848069
952649
1019504
1026452
1080644
1080644
1080644
1081798
1081798
1088131
1088131
1088131
1088131
1096115
1108256
1109398
1110085
1110519
1110519
1110519
1116407
1130609
1147060