Ceiling,Wall&GeneralIsolation
ResilientHangers
CDMISOPHS/PHR Resilient Hangers are designed to
suspend heavy ceilings, walls, lighting rigs, ducts and pipe
work. By isolating these elements from the main structure,
sound isolation and vibration isolation is maximized.

CDMISOPHR

CDMISOPHS

The choice between CDMISOPHS and CDMISOPHR


depends on the required resonance frequency. To
determine a specific type of PHS/PHR hanger, the load
must be considered.
fres [Hz]

Type

Optimalload perelement[lbf]

8 10 Hz

CDMISOPHS150
CDMISOPHS500

35 (min:22 max:56)
112(min:56 max:135)

CDMISOPHS1000
CDMISOPHS1400

225 (min:135 max:300)


270 (min:225 max:400)

CDMISOPHR80
CDMISOPHR150

18(min:10 max:25)
35 (min:25 max:40)

CDMISOPHR250
CDMISOPHR500
CDMISOPHR1000
CDMISOPHR2000

56 (min:40 max:90)
112 (min:90 max:145)
225 (min:145 max:270)
450 (min:270 max:750)

4 5 Hz

Example:InstallationofaCDMISOPHSwall

Hangers can be manufactured to take


any load and to achieve other natural
frequencies on request (e.g. 3 Hz
spring hangers).
CDMISOPERIMETERSTRIP should
be used around the perimeter of the
suspended wall or ceiling to ensure
that they are acoustically decoupled
from the supporting structures.

CDMISO
PERIMETER
STRIP
CDMISOPHS

MineralWool

Plasterboard
CDMMaterial

RequiredDataforDesign:
Requiredperformance
(insertionlossornaturalfrequency)
Imposedpermanentandtemporaryloads
Contactsurface(typeanddimensions)

Plasterboard

CDMISOWALL/CEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial (CDM)

132
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US03

TECHNICALDATASHEET

Ceiling,Wall&GeneralIsolation
ResilientHangers
FIELDOFAPPLICATION
CDMISOPHS/PHR suspensions are used to resiliently suspend ceilings or
heavy structures such as a wall, HVAC or lighting equipment to a structural
deck. This way, the transmission of structureborne noise and vibrations
can effectively be reduced.

DESCRIPTION
PHS
4
1
2
3

CDMISOPHS/PHR hangers consist of a galvanized steel frame (1) into


which an isolator element (2) is positioned; the isolator element can be a
spring (PHR) or an elastomer in CDMSOLIDS (PHS). The force is
distributed over the isolator by means of a steel washer (3). In case of a
spring isolator, soundstop layers in corkelastomer (5) are installed above
and below the spring to avoid steelonsteel contact. Elastomers resonate
at 8 to 10 Hz, and springs resonate at approximately 4 to 5 Hz. All
elements are glued together. At the top of the frame, a small
corkelastomer pad (4) decouples the steel frame and the structural ceiling.
The hanger can also be spaced off the structural deck using threaded rod.
The following units are standard:

PHR

CDMISOPHS Elastomers(CDMSOLIDS):
35lbf[150N]/112lbf[500N]/225lbf[1000N]/270lbf[1200N]

1
3
5
2
5

CDMISOPHR Springs:
35lbf[150N]/112lbf[500N]/225lbf[1000N]/450lbf[2000N]
Custom units can be designed as required.
The steel hanger frame has external dimensions of 2.4'' [60 mm] x 1.9''
[50 mm] x 3.2'' [80 mm].

CDMISOWALL/CEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial (CDM)

133
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US03

TECHNICALDATASHEET

Ceiling,Wall&GeneralIsolation
ResilientHangers
RECOMMENDATIONS
Alllinearloads(drywallfurringchannelorgrid,lengthsofpiping,
ductwork,cabling,etc.)shallbehungbyaminimumoftwoCDMISO
PHS/PHR elements.
ForSuspended Ceiling Applications:
8 MAX.

Forstabilityreasons,itisbesttolimitthedistancefromahangertothe
edgeofthesuspendedceilingto8''[200mm]maximum.
Theperimeterofthesuspendedceilingconstructionmustbe
completelydecoupledfromthesurroundingstructureusingCDMISO
PERIMETERSTRIP of~0.4''[10mm]thickness.
Itisrecommendedtouselowdensitymineralwoolorfiberglassas
soundabsorptionbetweenthejoists,toavoidstandingwaves.This
absorptivelayershouldnotbecompressed,andshouldallowfreespace
fortheairabovetheceilingtocirculate.
Foraddedisolationof2to3dB,ahighperformancedampingsheetin
corkelastomercanoptionallybeinstalledinbetweentheceilingboard
layers.CDMRCmaterialin0.12''to0.2''[3mmto5mm]thicknessisan
excellentproductforthisapplication.

CDMISOWALL/CEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial (CDM)

134
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US03

TECHNICALDATASHEET

Ceiling,Wall&GeneralIsolation
ResilientHangers
CDMISOPHR asaWallHanger

CDMISOPHR

MineralWool
Plasterboard
CDMMaterial

Plasterboard

CDMISOPHS asaWallHanger

CDMISOPHS

MineralWool
Plasterboard
CDMMaterial

Plasterboard

CDMISOWALL/CEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial (CDM)

135
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US03

TECHNICALDATASHEET

Ceiling,Wall&GeneralIsolation
ResilientHangers
CDMISOPHS asaWallHanger TESTRESULTS
CDM product tested
Description
Tested by
Test site
Test date
Test method
Measured parameter(s)

CDM-ISO-PHS
Resilient hanger
EMI (HU)
EMI lab in Szentendre
3/09/2004
Following ISO 140-3 (1998)
Rw

Setup
1) CDM-ISO-PHS wall hanger
2) double layer in gypsum board (2 x 12,5mm)
3) 100mm mineral wool as absorption (lightweight wall)
4) masonry wall of 300mm,plastered at both sides (15mm)
5) NA
6) NA
7) NA
8) NA
9) NA
10) NA
R base [dB]

R [dB]

100
125
160
200
250
315
400
500
630
800
1000
1250
1600
2000
2500
3150
4000
5000

34,5
42,8
38,7
44,3
38,4
38,3
40,9
41,8
42,1
44,0
44,6
42,6
43,6
47,0
48,3
52,7
56,3
59,6

43,8
48,9
51,6
52,0
55,9
57,7
60,9
67,0
69,0
72,4
73,0
71,7
74,6
76,5
74,7
76,5
79,3
74,5

Rw(C;Ctr) [dB]
STC

44(0;-1)
46

67(-2,-7)
69

2
3
4

R base [dB]

Acoustical isolation

R [dB]

90
80
70
60

R [dB]

Results
Frequency [Hz]

50
40
30
20
10
0
100

125

160

200

250

315

400

500

800 1000 1250 1600 2000 2500 3150

Third octaves [Hz]

CDMISOWALL/CEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

630

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial (CDM)

136
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

SupermarketNieuwVennep,NL
PROJECTDATASHEET

BoxinBoxSystem
CDMISOSUSPENSIONBOX
JobType
GeneralContractor

Isolationofmachinerooms
DirkvandenBroek
Supermarkets
Installation
2003/2004
ContractorMachinery FriJado
DeltaL, the Dutch partner of CDM, is part of the
building team for one of Hollands biggest chains of
supermarkets, Dirk van der Broek. When supermarkets
are built under or next to apartments, DeltaL has to
provide a solution for the isolation of the machine
rooms with cooling machines.
The shopping centre of Nieuw Vennep is a mall
combining 40 shops with a library, several offices and
52 apartments. In order to avoid noise in the
apartments, the machine room had to be isolated.
Therefore in the machine room, a CDMISOBOX
system was used, combining CDMISOLAT, CDMISOT
and CDMISOCLIPS. For the fixation of the piping,
CDMISOPHS hangers were used. This setup provides a
reduction of the noise level from 85 dB(A) in the
machine room to < 25 dB(A) in the neighboring
houses.

CDMISOPHShangerswereused
forthefixationofthepiping.

CASESTUDY CDMISOSUSPENSION
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial (CDM)

137
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US02

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers

InstallationManual CEILINGSUSPENSION
CDMISOPHS

Contents
A.CDMISOPHS/PHR
B.Hardware&FixationBracket
C.DrywallFurringChannelorGridInstallation
D.FirstBoardLayer
E.SoundAbsorptionLayer
F.SubsequentBoardLayers

CDMISOPHR

Figures
Fi
1.CompletedinstallationofCDMISOPHS

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

137
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US03

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers

STEPSTOFOLLOW
A.CDMISOPHS/PHR
CDMISOPHS/PHR resilient hangers consist of a galvanized steel frame into
which an isolator element is positioned. This isolator can be either a CDM
SOLID elastomer (PHS) or a steel spring (PHR). Hangers are attached to the
structural ceiling deck with one fixation. Install hangers at the prescribed
spacing per project drawings. If no drawings are provided, spacing shall be
limited to 2 ft [600 mm] x 3.3 ft [1000 mm] for ceilings with up to (2) layers
g
should be no more than 8 from the ceilingg
of board material. Hangers
perimeter to avoid a cantilever effect.

B.Hardware&Brackets
Pass the threaded rod through the isolator body and install adjustment nuts,
washers, and hardware as shown.
For installation using Drywall Furring Channel (2025 ga, 7/8 or 1 height),
install the Cshaped bracket (face legs upward) to the lower end of the
threaded rod and secure with hardware.
For installation using the recommended prefabricated drywall grid system,
install the Lprofile bracket to the lower end of the threaded rod and secure
with hardware.

C.DrywallFurringChannelorGridInstallation
Attach the furring channel or grid to the hanging brackets using selftapping
screws. For furring channel, use a minimum of (2) screws through the wings
of the channel. For prefabricated grid, use a minimum of (2) screws through
th vertical
the
ti l leg
l off the
th grid.
id
E
Ensure
th t a minimum
that
i i
off (2) hanger
h
units
it
support any one length of furring channel or grid main runner.

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

138
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US03

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers
D.FirstBoardLayer
Before installation of board materials, install resilient perimeter strip on the
walls of the room around the entire perimeter from the elevation of the
finished ceiling layer to the elevation of the top of the furring channel or grid.
Ensure no rigid connection will be made between the floating ceiling and the
surrounding structure or stationary fixtures.
Install the first layer of plasterboard to the furring channels or grid system
using appropriate selftapping screws. As this layer is being installed, lay in the
mineral wool absorptive layer (see Step E.)

E.SoundAbsorptionLayer
During installation of the first layer of board material, in the void between the
structural ceiling and the plasterboards, lay low density mineral wool as sound
absorption. This mineral wool should not be compressed in the void, and should
leave a free space for air to circulate.

F.SubsequentBoardLayers
Attach the remaining layers of board material onto the first layer, alternating
seams. All subsequent layers shall be isolated by the perimeter strip already
installed on the wall. Make sure that the perimeter is decoupled by the
resilient strip.
InstallationofCDMISOPHS

CDMISOPHS
FurringChannel
Mineral Wool
MineralWool
Plasterboard
CDMISO
PERIMETERSTRIP

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

139
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US02

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers

InstallationManual WALLSUSPENSION
CDMISOPHS

Contents
A.CDMISOPERIMETERSTRIP
B. CDMISOMAT
B.CDM
ISO MAT
C.SoundAbsorptionLayer
D.FirstBoardLayer
E.CDMDampingMaterial(optional)
F.SubsequentBoardLayers
G.Finishing

CDMISOPHR

Figures
1.CDMISOPHS/PHR installation
2.Firstboardlayerinstallation
3.Secondboardlayerinstallation
y

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

140
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US02

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers

STEPSTOFOLLOW
A.CDMISOPERIMETERSTRIP
Installll CDMISOPERIMETERSTRIP on the
h floor,
fl
side
d walls,
ll and
d ceiling
l
as
illustrated in Figure 1 to decouple the entire floating wall construction.

B.CDMISOPHS/PHR
Attach the CDMISOPHS/PHR to the structural ceiling with an appropriate
fixation For CDMISOPHS,
fixation.
CDMISOPHS install the fixation until the isolator is compressed
approximately 50% of its total design deflection (refer to project
documentation). Typical spacing between isolators is 20 [~500 mm] but this
should be verified with loading (refer to project documentation regarding
spacing). Mount the structure of the hung wall on top of the resilient strip
installed at the floor (Figure 1), and connect to the resilient hangers through
the header usingg threaded rods.

CDMISOPHS/PHR

CDMISOPERIMETER
STRIP

Figure1:CDMISOPHS/PHRinstallation

C.SoundAbsorptionLayer
Install mineral wool within the stud bays of the wall. Make sure that the
entire wall surface is well covered.

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

141
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US02

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers
D.FirstBoardLayer
Attach the first layer of board material to the stud wall construction using
appropriate screws with a limited length, making sure that the perimeter is
decoupled by the resilient strip.
strip

CDMISOPHS/PHR

BoardLayer1

CDMISOPERIMETER
STRIP

Figure2:Firstboardlayerinstallation

E.CDMDampingMaterial(optional)
i
i l( i
l)
For added isolation of 2 to 3 dB, a highperformance damping sheet in
corkelastomer can optionally be installed in between the ceiling board layers.
CDMRC material in 0.12'' to 0.2'' [3 mm to 5 mm] thickness is an excellent
product for this application. Staple the material between the first and second
layers of board material.
material

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

142
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

CDMISOPHS/PHR

V_US02

INSTALLATIONMANUAL

Ceiling,Wall&GeneralIsolation
Resilient Hangers
ResilientHangers
F.SubsequentBoardLayers
Attach subsequent layers of board material to the first layers using appropriate
screws with a limited length, making sure that the perimeter is decoupled by
the resilient strip.
strip Alternate seams.
seams

CDMISOPHS/PHR
BoardLayer1
y
DampingMaterial

BoardLayer2
CDMISOPERIMETER
STRIP

Figure3:Secondboardlayerinstallation

F.Finishing
i i hi
Install finishing wall covering and plinth (skirting board). The floating wall
should have no rigid contact with the surrounding structure. Please note that,
if the isolators are made of rubber, there will be some deflection over time,
called creep. In case the room is finished with plinths along the perimeter
directly after the installation,
installation it is advised to use flexible putty between the
floor and the plinth in order to accommodate creep.

CDMISOCEILING
CDM
Reutenbeek911
BE3090Overijse
Belgium
T:+3226877907
F:+3226873552
Email:general@cdm.be
www.cdm.be

noise&vibrationcontrol
ThisdocumentistheexclusivepropertyofCompositeDampingMaterial(CDM)

143
RPGDiffusorSystems,Inc.
651CCommerceDrive
UpperMarlboro,MD20774
USA
T:+13012490044
F:+13012493912
Email:info@rpginc.com
www.rpginc.com

You might also like