Cable Inspection and Testing Checklist

This document summarizes test results for a cable including: - A visual inspection checking cable data matches specifications and that supports, shield grounding, glanding and terminations are properly installed. - Continuity testing to check for open circuits. - Insulation resistance testing to check cable insulation integrity both before and after a high potential dielectric test. - A high voltage test applying voltage between phases and from each phase to earth while measuring leakage currents over time.

Uploaded by

rakeshrao1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views4 pages

Cable Inspection and Testing Checklist

This document summarizes test results for a cable including: - A visual inspection checking cable data matches specifications and that supports, shield grounding, glanding and terminations are properly installed. - Continuity testing to check for open circuits. - Insulation resistance testing to check cable insulation integrity both before and after a high potential dielectric test. - A high voltage test applying voltage between phases and from each phase to earth while measuring leakage currents over time.

Uploaded by

rakeshrao1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Cable From :

Cable To :

Cable Size :

Cable Length:

Runs per Phase:

Make:

Drawing Ref:
Remarks:

VISUAL INSPECTION
Description

Checked

1.

Cable data matching with project specification.

2.

Check both ends.

3.

Check cable supports shield grounding, glanding &


terminations.

4.

Check the bending radius meet with prescribed values.

5.

Check for proper identification and supports.

Page 1 of 4

Remarks

2.1

SITE ACCEPTANCE TESTS


CONTINUITY TEST:
Cable Details

Status

RESULT:

REMARKS:

2.2

INSULATION RESISTANCE TEST:

Cable Details

Description

Applied Voltage

Time
Duration

Before HIPOT

Page 2 of 4

R (Y+B+E)

Y (R+B+E)

B (R+Y+E)

After HIPOT

RESULT:

REMARKS:

2.3

HIGH VOLTAGE TEST:

Cable
Details

RESULT:

Voltage
Applied

Phase

Earth

Y-B

B-R

R-Y

Leakage Current (A)


1 min

Page 3 of 4

2 min

3 min

5 min

10 min

15 min

REMARKS:

Page 4 of 4