Cluster Acceptance Report

Cluster Name: 115


Cluster Stage 100%
(With Respect to Launch Sites)

Prepared By:
Reviewed By:

Page 1 of 14

Table of Contents
1 INTRODUCTION..................................................................................................3
1.1 DT Route/Area............................................................................................3
1.2 On-Air Status of Cluster............................................................................4
2 PROCEDURE......................................................................................................5
3 CALL SUMMARY................................................................................................5
4 RF INDICATORS DISTRIBUTION PLOTS.........................................................6
4.1 RxLev(Sub).................................................................................................7
4.2 RxQuality(Sub)...........................................................................................8
4.3 C/I....................................................................Error! Bookmark not defined.
4.4 Handover Failure......................................................................................11
4.5 Call Drop...................................................................................................11
4.6 Data Throughput(Downlink)....................................................................11
5 UPDATED ENGINEERING PLANNING DATA:......ERROR! BOOKMARK NOT
DEFINED.
6 RECOMMENDATION & TECHNICAL OVERVIEW..........................................13
7 PUNCH LIST......................................................................................................13

Page 2 of 14

1 Introduction
1.1 DT Route/Area

Page 3 of 14

1.2 On-Air Status of Cluster

Cluster Completion : 100% with Respect to Launch Sites)

Page 4 of 14

2 Procedure
The procedure for the drive tests is described below:
Cluster drive tests shall perform 3 call scenarios: short call, long call, and PS call. GPRS functionality
drive tests were performed by downloading a huge file from an FTP server throughout the cluster drive
test route. Configuration of MS is as follows in the DT Kit:
MS1= Long call (MS to MSC Test Number ,continous call )
MS2 = Short call (MS to MSC Test Number, 30sec., 3 sec. delay)
MS3 = EGPRS downloading
MS4 = Idle

3 Call Summary
Content
Call Drop(Long Call)

Call Setup(Short Call)

Handover(Long Call)

Downlink Throughput

Couter & KPI

Value

Number of Call Drops

Total Call duration

Contionous call

Call Drop Rate(<=1.2%)

0%

Number of call setup failed

Number of Call Attempt

91

Call Setup Succ. Rate(>=97%)

100%

Handover Success

38

Handover Attempt

38

HO Succ. Rate( >=97%)

100%

Average Downlink Throughput

57.35

Remark

Page 5 of 14

4 RF Indicators Distribution Plots


4.1 Serving Cell ID

4.2 RxLev(Sub)
Page 6 of 14

In this cluster most of the places having terrian issue(Hilly terrian)


Area 1& 2: Rx level was poor due to terrian issue in those places. (attached radiation pattern below)

Legend
-68 to 0

Bin count
3598

Percentage
50.22
Page 7 of 14

-76 to -68
-84 to -76
-92 to -84
-110 to -92
Total

1429
1467
622
48
7164

19.95
20.48
8.68
0.67
100

4.3 RxQuality(Sub)

Page 8 of 14

Legend

Bin count

Percentage

0-4
5
6
7
Total

6992
93
64
15
7164

97.60
1.30
0.89
0.21
100

4.3 C/I
Page 9 of 14

Legend
20 to 35

Bin count
6257

Percentage
91.08

Page 10 of 14

12 to 20
9 to 12
5 to 9
0 to 5
-10 to 0
TOTAL

611
1
1
0
0
6870

8.89
0.01
0.01
0
0
100

4.4 Handover Failure


No Handover failure

4.5 Call Drop


No call drop

4.6 Data Throughput(Downlink)

Page 11 of 14

GPRS was not connected in Gandhinagar site & Muvattupuzha sites 2nd sector, informed to OMCR.

Page 12 of 14

5 Recommendation & Technical Overview


In this cluster most of the places having terrian issue(Hilly terrian)
We couldnt able to change the azimuth of Muvattupuzha sites 3rd sector, due to another
antenna obstraction.
There is an over shoot from Muvattupuzha site , On 3rd sector mainlobe of Gandhi
nagar,Because Gandhi Nagar Sites antenna height is 40m and Muvattupuzha sites antenna
ht is 49 m and sharp variation in AMSL also.
We have attached the radiation patterns for the issue sites.
Muvattupuzha 3rd sector antenna photo:

Vellorekunnam 2nd sector :

Vellorekunnam 3rd sector :

Page 13 of 14

Gandhi Nagar 1st sector :

Market Area 1st sector :

6 Punch List
Sr. No.

Item

Date Closed

Name / Signature of closing


authority

ALL TEST COMPLETED WITHOUT ANY ITEMS ON PUNCH LIST


Yes

No

Page 14 of 14