You are on page 1of 22

EHV AC Substations : Layout, Equipment, Bus arrangements

Contents:

1.0

a) PURPOSE
b) CLASSIFICATIONS
c) VOLTAGE CLASS & RATINGS
d) Bus switching schemes
e) SLD & Lay outs
f) SUBSTATION EQUIPMENTS.
g) GIS
Purpose:

2.0

1.1 The substations are very much essential to


a) Evacuate power from generating stations.
b) Transmit to the load centers.
c) Distribute to the utilities & ultimate consumers.
1.2. The Electrical power generation from Hydel, Thermal, Nuclear and other generating
stations has to be evacuated to load centers. The generation voltage is limited to 15/18 KV
due to the limitation of the rotating machinery. This bulk power has to be stepped up to
higher voltages depending on quantum of power generated and distance to the load
centers. Again the power has to be stepped down to different lower voltages for
transmission and distribution.
1.3 In between the power houses and ultimate consumers a number of Transformation and
switching stations have to be created. These are generally known as sub-stations

CLASSIFICATIONS

3.0

3.1. Accordingly the substations are classified as


a) Generating substations called as step up substations
b) Grid substations
c) Switching stations

d) Secondary substations
3.1. The generating substations are step up stations as the generation voltage needs to be stepped up
to the primary transmission voltage so that huge blocks of power can be transmitted over long
distances to load centers.
3.2 The grid substations are created at suitable load centers along the primary transmission lines.
3.3 Switching stations are provided in between lengthy primary transmission lines:
a) To avoid switching surges.
b) For easy segregation of faulty zones.
c) For providing effective protection to the system in the A.C. network.
d) The switching stations also required wherever the EHT line are to be tapped and line to be
extended to different load centers without any step down facility at the switching stations.
e) The number of outgoing lines will be more than the incoming lines, depending on the load
points.
3.4. Secondary substations are located at actual load points along the secondary transmission lines
where the voltage is further stepped down to:
a) Sub transmission voltages
b) Primary distribution voltage.
c) Distribution substations are created where the sub-transmission voltage and primary
distribution voltage are stepped down to supply voltage and feed the actual consumers
through a network of distribution and service line
4.0. VOLTAGE CLASS AND RATINGS
Generally the following voltage class substations prevailing in India
a) 6.6 KV, 11 KV, 22KV.

---------- Primary distribution Voltage

b) 33 kV, 66KV, 110/132KV, --------

High voltage

c) 220/230KV , 400 KV, 765 kV ---------- Extra high Voltage


5.0 PLANNING OF SUBSTATION INSTALLATION
5.1 The process of planning sub-station installations consists in
a) Establishing the boundary conditions.
b) Defining the plant concept, type, & Planning principles.

5.2 The boundary conditions are governed by following environmental circumstances &
availability of the land in the required place.
a) Local climatic factors
b) Influence of environment
c) The overall power system voltage level
d) Short circuit rating
e) Arrangement of neutral point
f) The frequency of operation
g) The required availability or reliability
h) Safety requirements
i)

Specific operating conditions

6.0. Types of substations:


a) Out door- Conventional Air insulated substations (AIS)
b)

In door substations

c)

Compressed Air insulated

d)

Gas insulated substations (GIS )

6.1 The types of Sub Stations depends upon:


a) The availability of the land in the required place.
b) Environmental conditions.
7.0. Sub-Station Engineering.
7.1. The Sub Station Engineering comprises,
a) Sub-station site selection
b) Bus Switching schemes.
c) Bus-Bar:
i.

Type.

ii.

Size

d) Safety clearances.
i.

Phase to phase clearances.

ii.

Phase to ground clearances.

e) Sectional clearance.
f) Ground clearance.
g) Bus levels.
i.

First level

---- Equipment interconnection level.

ii.

Second level ---- Bus levels.

iii.

Third level

---- Cross Bus / Jack Bus level.

h) Bay widths
i)

Yard levels.

j)

Single line diagram & Layout.

k) Lightning protection.
l)

Earth mat.

m) Civil Engineering works:


i.

Control Room

ii.

D.G & Fire fighting room.

iii.

Cable ducts

iv.

Foundations of all equipments & Mounting structures

v.

Yard leveling

vi.

Approach Roads & Roads inside the substation

vii.

Security fencing & boundary wall.

viii.

Water supply & drainage

ix.

Colony

x.

Anti weed treatment

xi.

Spreading of Jelly ( broken stones) in the substation yard

n) Electrical Installation works:


i.

Station structures: Tower, Beams, Equipment mounting structures, Lightning


cum Lighting masts, Bus bar formation, Insulators, clamps & connectors, corona
rings & rubber mats, etc

o) Main electrical equipments:


i.

Power Transformers ( ICTs).

ii.

Circuit breakers.

iii.

Shunt & Bus Reactors.

iv.

Reactive compensation.

v.

Instrument Transformers

vi.

Isolators

vii.

Lightning / Surge Arrestors

viii.

Control panels

ix.

Protection & Relay panels.

x.

P.L.C.C Equipments

xi.

Control & Power cables.

xii.

Substation Automation

xiii.

Fire Fighting equipments

p) Auxiliary supplies:
i.

A.C Supply:

ii.

D.C. Supply- Battery & Battery chargers

iii.

D.G Sets

iv.

A.C & D.C panels / switch Boards

8.0. Switching schemes


8.1 The selection of switching scheme depend upon:
a) Reliability factor
b) Availability of the space
c) Economics (project cost)
d) There can be several combinations in which the equipments, bus-bars, structures etc.
can be arranged to achieve a particular switching scheme.
8.2.The various types of switching schemes along with its advantages and disadvantages:
a) Single Bus arrangement:

ADVANTAGES
1. Simple in Design
2. Less Expenditure

DISADVANTAGES
1. In case of bus fault or bus bar isolator fault or
maintenance Total Substation is out of service.
2. In case of maintenance of transformer circuit
breaker the associated transformer has also to
be shut-down. Similarly for Line also.

b) Single Bus with bus sectionaliser:

Main Bus is divided into two sections with a Circuit Breaker and isolators in between the adjoining
sections. One complete section can be taken out for Maintenance without disturbing the continuity of
other section. Even if a fault occurs on one section of the Bus, that faulty section alone will be isolated
while the other section continues to be in service. It will be a little more costly with the addition of one
isolator and some cases with Circuit breaker, C.Ts and C&R panel

c) SINGLE BUS & TRANSFER BUS SYSTEM:

T/F-2

T/F-1

TRANSFER BUS COUPLER

TRANSFER BUS

BUS-1
BAY1

BAY2

BAY3

BAY4

BAY5

FEEDER1 FEEDER2

BAY6

BAY7

FEEDER3 FEEDER4

i.

With this arrangement, all the feeders are normally on the Main Bus Bar. If at any time, a
Line Circuit Breaker/ Transformer circuit breaker Maintenance is required or break down of
Circuit breaker or CTs, that particular feeder/ transformer , can be transferred on to the
Transfer Bus. The feeder protection thus gets transferred to trip Transfer Bus Coupler
Breaker. On fault occurrence or maintenance, entire bus becomes de-energized.

ii.

Salient features:

Only one Circuit at a time can be transferred on the Transfer Bus.

For Maintenance or on fault occurrence, total Bus becomes dead.

d) DOUBLE BUSBAR:
There are six types of Bus switching schemes double bus bars
i.

DOUBLE BUSBAR SYSTEM.

ii.

DOUBLE BUS WITH SECTIONALISER SYSTEM.

iii.

DOUBLE BUS & TRANSFER BUS SYSTEM.

iv.

DOUBLE BUS & TRANSFER BUS WITH SECTIONALISER SYSTEM.

v.

ONE & HALF BREAKER SYSTEM

vi.

ONE & HALF BREAKER WITH SECTIONALISER SYSTEM

d-i) Double main Bus system (Bus -1 & Bus-2) & Double main Bus with transfer Bus scheme

Lines
Lines

Lines

Lines

Main Bus1
Main Bus
Transfer
Bus

Transformer

Main Bus2

Transformer

Main Bus with Transfer Bus

Transformer

Transformer

Double Main Bus

19

Double main bus:


This system has got flexibility of transferring any Circuit to any of the Bus.For Maintenance or on
fault occurrence on one Bus, then only that Bus becomes dead, while the other Bus remains in
service. For Maintenance of a Circuit Breaker, that particular Circuit has to be taken out of service.
To overcome this, an additional bypass isolator is provided as indicated in figure above
Double main bus with Transfer bus:

This system is a combination of Main and Transfer Bus and Double Bus Arrangement. This has got
flexibility of transferring any Circuit to any of the Main Buses. For Maintenance or any fault
occurrence on a Bus, Particular Bus only becomes dead, while the other Bus continues to be in
service. Any Circuit Breaker can be taken out for Maintenance by transferring that circuit to Transfer
Bus, and transferring its Protection to Transfer Bus Coupler Circuit Breaker.

e) One & half breaker system:


(I-CONFIGUARATION)
FEEDER9

FEEDER11

BAY17

BAY16

DIA6

BAY18

BAY14

BAY13

DIA5

BAY15

BAY10

DIA4

BAY11

BAY7

DIA3

FEEDER7

BAY12

BAY5

BAY4

DIA2

BAY6

BAY3

BAY2

BAY1

BUS-1DIA1

FEEDER5

BAY8

FEEDER3

BAY9

FEEDER1

BUS-2

FEEDER2

FEEDER4

FEEDER6

FEEDER8

FEEDER10

FEEDER12

This system has 3 Circuit Breakers for Two Circuits. (One is Line another is Transformer or Bus
Reactor or both are Lines) No changeover of Line from one Bus to the other is required. For Circuit
Breaker Maintenance of any Line, the load gets transferred Automatically to the other bus. For
Maintenance or an occurrence of a Bus fault, all the interconnections will be on healthy bus and no
disturbance to the Circuits. Even if both Buses become dead, Circuits can still be in service through
the Tie Circuit Breaker.This has got many such advantages to maintain the system stability.
Double Bus & Double breaker system

FEEDER1

FEEDER3

FEEDER1

FEEDER3

BAY6

BAY5

BAY2

BAY1

BAY7

BAY5

BAY3

BAY1

BUS-1

BUS-1

BAY8

BAY7

BAY4

BAY3

BAY8

BAY6

BAY4

BUS-2
BAY2

f)

BUS-2

FEEDER2

FEEDER4

FEEDER2

FEEDER4

FOR ECONOMICAL& RELIABULITY PURPOSE THIS SYSTEM ADOPTED IN 800KV SYSTEM

DOUBLE BUS & DOUBLE BREAKER SYSTEM


FEEDER1

FEEDER3

FEEDER1

FEEDER3

BAY6

BAY5

BAY2

BAY1

BAY7

BAY5

BAY3

BAY1

BUS-1

BUS-1

BAY8

BAY7

BAY4

BAY3

BAY8

BAY6

BAY4

BAY2

BUS-2

BUS-2

FEEDER2

FEEDER4

FEEDER2

FEEDER4

FOR ECONOMICAL& RELIABULITY PURPOSE THIS SYSTEM ADOPTED IN 800KV SYSTEM

Greatest operational flexibility, Greatest operational flexibility , Connection possible to either bus
bar, Each breaker can be serviced without completely disconnecting the branch, High Reliability,
Most expensive as it involves additional breaker, CT Isolators etc for each circuit.
g) Ring Bus in a substation:

Flexibility for breaker maintenance, each breaker removable without disconnecting load, Only
one breaker needed per branch, Each branch connected to network by two breakers, All changeover switching done with circuit-breakers & hence flexible.
9.0. Bus bar:
a) Type of Bus bars Strung Bus/Flexible Bus and Rigid Tubular Bus
b) Strung Bus: The various Types of conductors used for Strung Bus are
i.

All Aluminum conductor (AAC)

ii.

All Aluminum alloy conductor (AAAC)

iii.

Aluminum conductor with aluminum alloy reinforced (ACAR)

iv.

Aluminum conductor with steel reinforced (ACSR)

c) Rigid tubular conductors are also used in substations, which are more advantageous than
the flexible conductors
d)

Sizes of Bus Bar


The important factors for selection of the conductor sizes in a sub-station are,
i.

Normal current carrying capability

ii.

Short circuit heating with stand capability

iii.

Surface gradient

iv.

Corona free performance

10.0 Electrical safety clearances:


a) The various clearances which need to be defined.
i.

Phase-to-earth clearance.

ii.

Phase-to-phase clearance.

iii.

Sectional clearance.

iv.

Ground clearance.

v.

Equipment to equipment spacing

b) The electrical and safety clearances to be adopted in substation are governed by following
parameters.
i.

Basic Impulse Insulation levels (BIL).

ii.

Basic Switching Impulse level (BSL).

iii.

IE Rules.

iv.

Allowances in tolerance in dimensions of structural work.

v.

Safety margins for unforeseen errors

c) The standard clearances for various voltage classes;


Standard Clearances & Bay widths
220 kV
Sl No

Particulars

765 kV

400 kV

Rigid
bus

Strung
bus

Bay width in Mtrs

45

27

14

17

Phase to phase
clearance in Mtrs

12

3.65

Phase to earth
clearance in Mtrs.

10.5

6.5

3.35

3.5

Ground clearance in
Mtrs.

12

5.5

Sectional clearance
in Mtrs

10

6.5

4.3

11.0 Single Line Diagrams:


a) This diagram indicates the proposed bus bar arrangement and relative positions of various
equipments. There are numerous variations of bus bar arrangement.
b)

The choice of a particular arrangement depends on various factors viz. System voltage, position
of the substation in the system, flexibility, expected reliability of power supply and cost.

c) The following technical consideration must be borne in mind while deciding upon any one
arrangement.
i.

Simplicity is the key note of a dependable system

ii.

Maintenance should be easy with minimum interruption of supply

iii.

Safety to the operating personnel

iv.

Alternative arrangement should be available in the event of an outage on any of the


equipments or sections of sub station

v.

The layout should not hinder for expansion and/or augmentation at a later date, to meet
the future load growth

vi.

The installation should be as economical as possible keeping in view of the requirements


and continuity of supply

d) SLD for 220 kV substation with single bus both on 220 kV & 66 kV side:

e) SLD for 220 kV substation with Double Bus bar system on 220 kV & 110 kV side:

68

f) SLD for 400 kV substation with One & half breaker system on 400 kV and Double Bus & Transfer
bus system on 220 kV side

12.0. Substation lay out:


The single line diagram, bus switching scheme, bay widths, section & ground clearances, is to
be translated the selected scheme into a layout so as to physically achieve the feeder
switching required for ease in erection and maintenance:

81

13.0 INSULATION CO-ORDINATION:


a) Insulation coordination is the total of all measures taken to restrict flash over or break down
of the insulation caused by over voltages at places with in an installation at which the
resulting damage is as slight as possible. This is achieved by using lightning arresters to limit
over voltages.
b) The equipment are also to be designed to withstand lightning and switching surges. The
nominal lightning impulse withstand voltage and power frequency withstand voltage for
various voltage classes are as follows:

Maximum
voltage of
equipments

Nominal
lightning
impulse
Peak value

Nominal power
frequency
withstand voltage
RMS value

36 KV

170 KVP

90 KV

72.5 KV

325 KVP

140 KV

123 KV

550 KVP

230 KV

245 KV
1050 KVP
460 KV
420 KV
1425 KVP
1050 KVP*
* Nominal Switching impulse with stand voltage

c) LIGHTNING PROTECTION:
In H.V.& EHV substations, the protection from the lightning is done either by shield wire or
lightning mast (high lattice structure with a spike on top) and sometimes combinations of
both depending upon type of layout of substation.
i.

Shield wire

Shield wire lightning protection system will be generally used in smaller sub stations of
Lower voltage class, where number of bays are less, area of the substation is small. &
height of the main structures are of normal height. The major disadvantage of shield
wire type lightning protection is, that it causes short circuit in the substation or may
even damage the costly equipments in case of its failure (snapping ).
d) Lightning masts (LM)
This type of protection will be generally used in large, extra high voltage sub stations where
number of bays are more. It has the following advantages,

i. It reduces the height of main structures, as peaks for shield wire are not required
ii. It removes the possibility of any back flashover with the nearby equipment/structure,
etc. During discharge of
iii. lightning strokes
iv.

Provides facility for holding the lightning fixtures in the substation for illumination
purposes.

v.

Aesthetic look.

14.0 Earth mat requirement:


a) The main objective of earthing system in the substation is,

b)

i.

To ensure that a person in the vicinity of substation is not exposed to


shock

danger of electrical

ii.

To provide easy path for fault currents into earth under fault condition without affecting the
continuity of service

iii.

Hence intentional earthing system is created by laying earthing rod of mild steel in the soil of
substation area. All equipments/structures which are not meant to carry the currents for
normal operating system are connected with main earth mat

iv.

The earthing system in a substation serves the following

Protects the life and property from over-voltage

To limit step & touch potential to the working staff in substation

Provides low impedance path to fault currents to ensure prompt and consistent
operation of protective device

Stabilizes the circuit potentials with respect to ground and limit the overall potential
rise

Keeps the maximum voltage gradients within safe limit during ground fault condition
inside and around substation

The main earth mat shall be laid horizontally at a regular spacing in both X & Y
direction based upon soil resistivity value and short circuit value at substation. The main earth mat
shall be designed to limit the following;
i.

Touch Potential The potential difference between two points, one on the ground
where a man may stand and any other point which can be simultaneously touched by
either hand.

ii.

Step Potential The potential difference between any two points on ground surface
which can be simultaneously touched by feet.

iii.

Maximum ground mat resistance shall be less than 1.0 ohm for substations of 220kV
class and below, and shall be 0.5 ohms for 400kV and above voltage class.

iv.

The earth rods shall be capable of with standing short circuit current for specified
period.

v.

For I KA SC current for 1 second the minimum cross sectional area of M.S. Rod / Flat
shall be 12.16 sq mm with welded joints.

15.0 . INSULATORS:
a) Types of insulators : Disc type & Post type :
i. Disc type
Sys tem
voltage in
KV
400
400
220
220

Tens ion
s trength in
KN
160
120
120
90

Tens ion
25 s tring
16
-

Sus pens i
- on s tring
23
14

110

90

90

66
33 ii.

No. of units per s tring

2 type and Solid core


2 type
Post type70
: Pedestal post or stacking

The design considerations are,


The phase to earth clearance which determines the height

Insulation level

Power frequency withstand level


Mechanical strength i.e., mainly cantilever strength
Minimum creepage dimensions

System voltage in Height of stack


KV
(mm)
400
220
110
66
33

3650
2300
1220
770
380

Nol of units per


stack
3
2
1
1
1

Minimum
creepage
dimension in mm
at 25 mm/KV
10500
6125
3075
1815
900

Cantilever
strength
KN
8
6
4.5
4.5
4

16.0 Illumination:
The indoor & out door areas of sub station are to be properly illuminated. The minimum lux levels
to be maintained in the different areas are follows.

Sl No

Area in s ub s tation

Minimum lux levels to be provided

Control Room

350

L.T.Room .

150

CableGallery

150

Battery Room

100

Entrance Lobby

150

Corridor Landing

150

Conference
Room

Res t Room

Out Door Switch Yard

Room

&

Dis play

300
250
Main Equipment -- 50
Balance area. --

10

Street / Road

30

30

You might also like