You are on page 1of 1

EV below PV behind schedule

EV above PV ahead of schedule


AC below EV within budget
AC above EV over budget
EVM
SV = EV PV
CV = EV AC
CPI = EV / AV
CPI > 1 under budget
SPI = EV / PV
SPI > 1 ahead of schedule
TCPI (BAC) = BAC EV / BAC AC
TCPI > 1 ahead of planned value
TCPI (EAC) = BAC EV / EAC AC
EAC = BAC / CPI
continues as currently performing
EAC = AC + (BAC EV)
deviated, but now as planned
EAC = AC + (BAC EV / SPI * CPI
over budget & behind schedule
EAC = AC + New estimates
flawed costs
ETC = (BAC EV) / CPI
ETC = EAC - AC
VAC = BAC EAC
PRESENT VALUE
PV = FV / (1 + I)n
POINT OF TOTAL ASUMPTION
PTA = (Ceiling price Target price / buyers ration) + target cost
ES vs EF vs LS vs LF

You might also like