Note: As of Date, no new IFC drawing yet be issued for
duta waja.
PROPOSED D Week 1
Week2
Aug-16 Week 3
PROPOSED DUTA PILING SCHEDULE
Week 4
Week 1
Week2
16-Sep Week 3
(as of 26/8 - 14 point balance- Expected completion on 29/8/16)
(At present - One (1) Piling machine been used) (as of 26/8 - 162 points been driven out of 332. After 29/8, all 4 piling machine will be shifted to Tank A) (At Present - Three (3) piling machine been used)