METHOD STATEMENT
PROJECT: PROPOSED WAREHOUSE FOR AIRCRAFT SPARES.
CLIENT : OMAN AIR S.A.O.C.
CONSULTANT: M/S. MILES ENGINEERING CONSULTANCY.
Rev : 0
REV
DATE
20-03-15
(i)
TATUS
FA
REVISION DETAILS
First submission for approval
REVIEWER / APPROVER
CONTRACTOR
CONSULTANT
Status Code:
D : Draft
P : Preliminary
Distribution :
FI : For Information
FA : For Approval
FC : For Construction
Table of Contents
Page
1.0 Scope & Objectives
2.0 Reference
3.0 Materials
4.0 Definitions
6.0.
Procedures/Method to be followed :-
6.1.
6.1.1. All the materials shall be delivered at site in original unopened packages.
6.1.2. The material shall be stored in properly covered shed so that it can not come into
contact with rains, moisture etc.
6.1.3. Packages of material shall be kept off the ground by means of wooden pallets.
Materials shall be grouped according to delivery at site.
6.1.4. Materials shall be used on FIFO basis and all the materials shall be used before
its date of expiry.