Professional Documents
Culture Documents
G
D,E
7
9
11
H
C,F,G
2
3
4
Question 2
Given the network
C(8)
A(5)
I(7)
D(5)
B(6)
G(2)
E(4)
H(3)
J(4)
F(3)
a. compute the project completion time dan determine the critical path
b. what will happen if B cannot be finished in day 6 but it can be finished day 9
c. how long delay can be done for F so that project completion time will not change
Question 3
Given the activities and their relation :
Activity No.
Activity
1
A
2
B
3
C
4
D
Duration
3
6
5
5
Constrain
FF(1-2)=7
FS(2-3)=4
SF(2-4)=12
FS(3-4)=2
FS(2-5)=2
SS(4-5)=4
SF(3-6)=13
FS(5-6)=2
By Precedence Diagram Method, determine critical part and the completion time
I
F,G
3
4
11