KEY LEARNINGS

Standard Pitch Time (S.P.T) = Basic Pitch Time (B.P.T) + Allowances (%)
Target = (Total Manpower per line * Total Working Minutes per Day/ S.A.M.)
* 100%
Theoretical Manpower = Benchmark Target per Hour/ Process Capacity per
Hour
Labour Productivity = Total Number of Output per day per line/ Number of
workers worked
Machine Productivity = Total Number of output per day per line/ Number of
Machines used
Line Efficiency =
( Total output per day per line * S.A.M. / Total manpower per line* Total
working minutes per day) *100%