Project Weekly Status Report

PROJECT STATUS REPORT


GENERAL SUPPLIES Ecommerce Website
WEEK ENDING: March 25, 2016
PROJECT STATUS SUMMARY
Scope

Schedule

Percent Complete:
Cost

Risks

30%
Quality

The project is currently on schedule. Having successfully finished the Business Case (WBS
1.1), Planning (WBS 1.2), and Design (WBS 1.3) phases of the project, we are now in the
position to commence the Build (WBS 1.4) phase.
All elements of the project status remain in the green thus far with little or no variance to
cause for concern.
The current actual value of the project as of 3/25/2016 is $124,855.00. To date, this matches
with the earned value of the project (or budgeted cost) of $124,855.00. With no variances in
either cost or scheduling, the Estimate at Completion remains at $235,560.00 which is inline
with the original proposed budget of the project of $235,560.00. With 70% of the project
remaining based on the schedule, there is a remaining cost of $128,704.00 for the project.
As of the date of this report both Cost Performance Index (CPI) and Schedule Performance
Index (SPI) are both registering at 1 (One) which is an indication that the progress of the project
both in cost and in schedule is going according to the project plan. However, should there be
any variance reported, we will make sure to communicate these and take appropriate steps
necessary for correction.

WORK PLANNED FOR LAST WEEK

1.3.2.2 Prototype Draft Submission


1.3.2.3 Client Review of Prototype

Project Weekly Status Report

WORK COMPLETED LAST WEEK

1.3.2.2 Prototype Draft Submission


1.3.2.3 Client Review of Prototype

WORK PLANNED FOR NEXT WEEK

1.4.1 CSS & HTML Coding

OPEN ISSUES
Awaiting sign off from client on site design to move forward with Build Phase (WBS 1.4)

OPEN RISKS
Currently there are no open risks

DELIVERABLES AND MILESTONES


Milestone

WBS

Planned

Forecasted

Actual

Status

Sign off Project Schedule


Sign Off Business Case
Sign Off Planning
Sign Off Design
Sign Off Development

1.1.1
1.1.3
1.2
1.3
1.5

12/22/15
1/14/16
2/24/16
3/25/16
5/26/16

12/22/25
1/14/16
2/24/16
3/25/16
5/26/16

Met
Met
Met

Completed
Completed
Completed
On Schedule
On Schedule

Sign Off Testing

1.6

7/18/16

7/18/16

On Schedule

Sign Off Soft Launch

1.7

8/17/16

8/17/16

On Schedule

OPEN CHANGE REQUESTS


No Open Change Requests
Change Request
Name

Change Request
Number

Request Date

Current Status

Project Weekly Status Report

KEY PERFORMANCE INDICATORS (KPI'S)


Schedule - Project is ON Schedule
Schedule Variance (SV): $0.00
Schedule Performance Index (SPI): 1
Cost - Project is ON Budget
Cost Variance (CV):
$0.00
Cost Performance Index (CPI):