You are on page 1of 3

Key Highlights of Project- Detail Engineering of Drying System

1. Existing Dryer to be dismantled and removed by Huntsman from site.


2. Piping to be dismantled and removed by Huntsman from site.
3. New dryer and associated equipment along with auxiliary and utility to be sized,
designed and installed.
4. Dryer and associated equipment will be installed inside the same building which is used
for existing dryer now.
5. Following Discipline to be involved for work
A. Process
B. Mechanical
C. Piping
D. Instrument
E. Electrical
F. Civil
G. Structure
H. Fire-fighting
I. Procurement
Scope of Consultant
1. Project

2. Process
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.
2.8.
2.9.
2.10.
2.11.

PFD
P&ID
Sizing of Vessel
Reviewing the vendor input i.e. H & M balance, Dryer Size
Specification for Dryer
Specification for Filter Bag
Hydraulic calculation
Instrument process Datasheet
Calculation required to select, specify or purchase to instrument, equipment
(excluding dryer and filter bag), PSV, Pump etc.
Process Descriptions
Control narratives

3. Mechanical
3.1.
3.2.
3.3.
3.4.

Mechanical Design Basis


Detailed Process, Offsite Storage & Utility Equipment Layouts
Mechanical Data sheets for process equipment as per equipment list
Equipment Layout

4. Piping

4.1.
4.2.

Vendor offer review (up to 3 nos. only), TQ, TBE and TR


Post-order vendor document review for process equipment, process and utility
Packages

4.3.
4.4.

Piping Material Specification


Material Specifications
Insulation
Painting
Specialty piping items like strainer, hoses, sampling systems etc.
Pipe rack Layout
Piping Layout
Piping Isometrics for Lines with diameter 1.5" and above
Pipe support drawings
Mechanical Datasheet for Valves and Specialty Piping Items
Preliminary Estimated BOQ for Piping, Valves & Specialty piping items
Final BOQ for Piping, Valves & Specialty piping items
Scope Of Work (SOW) document for Mechanical and Piping Installation Work
SOW for Equipment installation
SOW for piping work
SOW for Painting and Insulation work
TQ, TBE of Construction Bid Package (up to 3 nos.)

4.5.
4.6.
4.7.
4.8.
4.9.
4.10.
4.11.
4.12.
4.13.

4.14.

5. Instrument
5.1.
5.2.
5.3.
5.4.
5.5.
5.6.
5.7.
5.8.
5.9.
5.10.
5.11.
5.12.
5.13.
5.14.
5.15.

Instrument Index
Instrument datasheet
Material Requisition (MR) for Field Instruments
Vendor offer review (up to 3 nos. for control system and field instruments
Packages as mentioned above), TQ, TBE and TR
Post-order vendor document review for field instruments
Cable Schedule
Junction Box Schedule
Instrument Air Manifold Schedule
Instrument Hook up Drawings
Typical Installation drawings
Instrument Loop drawings
Estimated Preliminary BOQ of instrument bulk items
Final BOQ and specifications of instrument bulk items
SOW Document for Instrument Installation Work
TQ & TBE of Construction Bid Package (up to 4 nos.)

6. Civil
7. Procurement
Following will be deliverables and activities
7.1.
7.2.

Preparation of vendor list


PQ evaluation of vendor

7.3.
7.4.
7.5.
7.6.
7.7.
7.8.
7.9.

Floating of Tender
Pre-BID meeting arrangement
BID Submission follow-up with Vendor
Cost Comparison and High level observation
Post Bid meeting arrangement
Cost compression based on revised Submission
Final negotiation- meeting arrangement and support