Professional Documents
Culture Documents
2. Process
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.
2.8.
2.9.
2.10.
2.11.
PFD
P&ID
Sizing of Vessel
Reviewing the vendor input i.e. H & M balance, Dryer Size
Specification for Dryer
Specification for Filter Bag
Hydraulic calculation
Instrument process Datasheet
Calculation required to select, specify or purchase to instrument, equipment
(excluding dryer and filter bag), PSV, Pump etc.
Process Descriptions
Control narratives
3. Mechanical
3.1.
3.2.
3.3.
3.4.
4. Piping
4.1.
4.2.
4.3.
4.4.
4.5.
4.6.
4.7.
4.8.
4.9.
4.10.
4.11.
4.12.
4.13.
4.14.
5. Instrument
5.1.
5.2.
5.3.
5.4.
5.5.
5.6.
5.7.
5.8.
5.9.
5.10.
5.11.
5.12.
5.13.
5.14.
5.15.
Instrument Index
Instrument datasheet
Material Requisition (MR) for Field Instruments
Vendor offer review (up to 3 nos. for control system and field instruments
Packages as mentioned above), TQ, TBE and TR
Post-order vendor document review for field instruments
Cable Schedule
Junction Box Schedule
Instrument Air Manifold Schedule
Instrument Hook up Drawings
Typical Installation drawings
Instrument Loop drawings
Estimated Preliminary BOQ of instrument bulk items
Final BOQ and specifications of instrument bulk items
SOW Document for Instrument Installation Work
TQ & TBE of Construction Bid Package (up to 4 nos.)
6. Civil
7. Procurement
Following will be deliverables and activities
7.1.
7.2.
7.3.
7.4.
7.5.
7.6.
7.7.
7.8.
7.9.
Floating of Tender
Pre-BID meeting arrangement
BID Submission follow-up with Vendor
Cost Comparison and High level observation
Post Bid meeting arrangement
Cost compression based on revised Submission
Final negotiation- meeting arrangement and support